Highway Plan Phase Info
Phase Funding FY Amount
Right of way SPP 2025 $580,000.00
Utility Relocation STP 2025 $1,000,000.00
Construction STP 2027 $9,710,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D SPP $0.00 2025 AUTHORIZED 7/17/2023 $900,000.00
R SPP $580,000.00 2026 ESTIMATED $0.00
U STP $1,000,000.00 2026 ESTIMATED $0.00
C STP $8,000,000.00 2027 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 16894 1689401D $900,000.00 $0.00 $243,323.72 $125,975.00 $531,792.34
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: ENHANCING CUMBERLAND AVENUE FROM US 25E TO 18TH STREET WITH STREET IMPROVEMENTS FOR VEHICLE AND PEDESTRIANS, AS WELL AS STORM WATER MANAGEMENT TO IMPROVE SAFETY, CONGESTION, AND ENVIRONMENTAL IMPACT. (2020CCR) (2024CCR)
Location:
Route 1 Bell County KY-74 from MP 15.19 to MP 16.75
Route 2 County - from MP to MP
Item #: 11-167.00
Project Manager: KYTC\SHERRI.CHAPPELL
Road Engineer:
Type of Work: BIKE/PED FACIL(O)
Concerns:
Bridge Engineer:
Bridge Structure Number: 007B00084N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 77.8
NBI Rating: Not Deficient
Posting: YES
Project Manager: KYTC\SHERRI.CHAPPELL       Item #: 11-167.00
Project Description: ENHANCING CUMBERLAND AVENUE FROM US 25E TO 18TH STREET WITH STREET IMPROVEMENTS FOR VEHICLE AND PEDESTRIANS, AS WELL AS STORM WATER MANAGEMENT TO IMPROVE SAFETY, CONGESTION, AND ENVIRONMENTAL IMPACT. (2020CCR) (2024CCR)

This Project has no Milesones defined.
Project Manager: KYTC\SHERRI.CHAPPELL       Item #: 11-167.00
Project Description: ENHANCING CUMBERLAND AVENUE FROM US 25E TO 18TH STREET WITH STREET IMPROVEMENTS FOR VEHICLE AND PEDESTRIANS, AS WELL AS STORM WATER MANAGEMENT TO IMPROVE SAFETY, CONGESTION, AND ENVIRONMENTAL IMPACT. (2020CCR) (2024CCR)
Authoritative Source for Environmental Data:  EATS
This Project has no Environmental data.

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\SHERRI.CHAPPELL       Item #: 11-167.00
Project Description: ENHANCING CUMBERLAND AVENUE FROM US 25E TO 18TH STREET WITH STREET IMPROVEMENTS FOR VEHICLE AND PEDESTRIANS, AS WELL AS STORM WATER MANAGEMENT TO IMPROVE SAFETY, CONGESTION, AND ENVIRONMENTAL IMPACT. (2020CCR) (2024CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 11-167.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\SHERRI.CHAPPELL       Item #: 11-167.00
Project Description: ENHANCING CUMBERLAND AVENUE FROM US 25E TO 18TH STREET WITH STREET IMPROVEMENTS FOR VEHICLE AND PEDESTRIANS, AS WELL AS STORM WATER MANAGEMENT TO IMPROVE SAFETY, CONGESTION, AND ENVIRONMENTAL IMPACT. (2020CCR) (2024CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\SHERRI.CHAPPELL       Item #: 11-167.00
Project Description: ENHANCING CUMBERLAND AVENUE FROM US 25E TO 18TH STREET WITH STREET IMPROVEMENTS FOR VEHICLE AND PEDESTRIANS, AS WELL AS STORM WATER MANAGEMENT TO IMPROVE SAFETY, CONGESTION, AND ENVIRONMENTAL IMPACT. (2020CCR) (2024CCR)
Phase Vendor
D SITECH