Highway Plan Phase Info
Phase Funding FY Amount
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D UNK $600,000.00 AUTHORIZED 2/28/2024 $1,473,750.00
R SP $5,790,000.00 2016 ESTIMATED $0.00
U SP $3,380,000.00 2016 ESTIMATED $0.00
C SP $4,160,000.00 2018 ESTIMATED 2/28/2024 $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 61837 6183701D $1,018,863.18 $205,329.18 $765,449.76 $0.00 $1,177.20
R/W Clearance:
Utility Clearance:


Check Prints:
Final Plans:
Projects Due to PS&E/ Central Office:
Projects Due to Construction Procurement:
Last day to Advertise Federal-Aid Projects
(Notice to Contractors):
Last Day to Advertise State Funded Projects
(Notice to Contractors):
Letting Date:
Project Description: US 42 SAFETY IMPROVEMENTS FROM HARRODS CREEK BRIDGE TO RIVER ROAD.(10CCR)
Location:
Route 1 Jefferson County US-42 from MP 9.628 to MP 10.548
Route 2 County - from MP to MP
Item #: 5-972.00
Project Manager: KYTC\CARL.JENKINS
Road Engineer: HALL-HARMON
Type of Work: SAFETY-HAZARD ELIM(P)
Concerns:
SPECIAL CONCERN
Bridge Engineer:
Bridge Structure Number: 056B00004N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 54
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\CARL.JENKINS       Item #: 5-972.00
Project Description: US 42 SAFETY IMPROVEMENTS FROM HARRODS CREEK BRIDGE TO RIVER ROAD.(10CCR)

Milestones
Milestones Status Status Date Scheduled
TRAFFIC PLANS - SIGNALS SCHEDULED COMPLETION DATE 02/01/2012 02/01/2012
RIGHT OF WAY PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 06/15/2013 06/15/2013
TRAFFIC PLANS - TRAFFIC CONTROL SCHEDULED COMPLETION DATE 02/01/2012 02/01/2012
DRAINAGE INSPECTION INSPECTION HELD 03/31/2011 03/31/2011
JOINT INSPECTION INSPECTION HELD 03/31/2011 03/31/2011
ADVANCE SITUATION TO CENTRAL OFFICE NOT REQUIRED 02/17/2010 02/17/2010
PRELIMINARY LINE AND GRADE DES APPROVED 01/11/2011 01/11/2011
GEOTEC ENGINEERING - ROADWAY COMPLETED 08/24/2012 08/24/2012
TRAFFIC PLANS - LIGHTING NOT REQUIRED 02/17/2010 02/17/2010
RIGHT OF WAY PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 06/15/2013 06/15/2013
TRAFFIC PLANS - SIGNING NOT REQUIRED 02/17/2010 02/17/2010
GEOTEC ENGINEERING - BRIDGES NOT REQUIRED 07/15/1998 07/15/1998
ROAD PLANS TO CENTRAL OFFICE REVIEW PRINTS SENT TO C.O. 08/15/2014 08/15/2014
TRAFFIC PLANS - TRAFFIC CONTROL SCHEDULED COMPLETION DATE 02/01/2012 02/01/2012
TRAFFIC PLANS - SIGNALS SCHEDULED COMPLETION DATE 02/01/2012 02/01/2012
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE NOT REQUIRED 07/15/1998 07/15/1998
 
Project Manager: KYTC\CARL.JENKINS       Item #: 5-972.00
Project Description: US 42 SAFETY IMPROVEMENTS FROM HARRODS CREEK BRIDGE TO RIVER ROAD.(10CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
Local Government CE LVL 1 11/3/2023 DEA 11/3/2023 3/7/2025
CE RE 4/6/2006 7/30/2008 9/7/2010 9/7/2012

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\CARL.JENKINS       Item #: 5-972.00
Project Description: US 42 SAFETY IMPROVEMENTS FROM HARRODS CREEK BRIDGE TO RIVER ROAD.(10CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 5-972.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\CARL.JENKINS       Item #: 5-972.00
Project Description: US 42 SAFETY IMPROVEMENTS FROM HARRODS CREEK BRIDGE TO RIVER ROAD.(10CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\CARL.JENKINS       Item #: 5-972.00
Project Description: US 42 SAFETY IMPROVEMENTS FROM HARRODS CREEK BRIDGE TO RIVER ROAD.(10CCR)
Phase Vendor
D WOOLPERT
D HALL HARMON ENGINEERS INC