Project Description: RECONSTRUCT US 42 AND WIDEN FROM 2 LANES TO 3 LANES (3RD LANE WILL BE A CENTER TURN LANE) FROM JEFFERSON/OLDHAM COUNTY LINE TO RIDGEMOOR DRIVE. PROJECT WILL INCLUDE THE CONSIDERATION OF IMPROVEMENTS TO THE HAYFIELD WAY INTERSECTION. (2004BOPC) Location: Route 1 Oldham County US-42 from MP 0 to MP 0.942 Route 2 County - from MP to MP Item #: 5-441.01 Project Manager: KYTC\JAMES.MAYNARD Road Engineer: Type of Work: RECONSTRUCTION(O) Concerns:
Bridge Engineer: Bridge Structure Number: Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report Bridge Suff. Rate: NBI Rating: Posting: |
Project Manager: KYTC\JAMES.MAYNARD Item #: 5-441.01 Project Description: RECONSTRUCT US 42 AND WIDEN FROM 2 LANES TO 3 LANES (3RD LANE WILL BE A CENTER TURN LANE) FROM JEFFERSON/OLDHAM COUNTY LINE TO RIDGEMOOR DRIVE. PROJECT WILL INCLUDE THE CONSIDERATION OF IMPROVEMENTS TO THE HAYFIELD WAY INTERSECTION. (2004BOPC) |
Milestones
|
Project Manager: KYTC\JAMES.MAYNARD Item #: 5-441.01 Project Description: RECONSTRUCT US 42 AND WIDEN FROM 2 LANES TO 3 LANES (3RD LANE WILL BE A CENTER TURN LANE) FROM JEFFERSON/OLDHAM COUNTY LINE TO RIDGEMOOR DRIVE. PROJECT WILL INCLUDE THE CONSIDERATION OF IMPROVEMENTS TO THE HAYFIELD WAY INTERSECTION. (2004BOPC) Authoritative Source for Environmental Data: EATS |
Requestor | Request Type | Request Date | Assigned Name | Assigned Date | Scheduled Completion Date |
Actual Completion Date | Expiration Date |
District Office | CE LVL 1 RE | 8/16/2012 | District | 8/16/2012 | 8/24/2012 | 8/17/2012 | 8/17/2014 |
District Office | CE LVL 1 | 3/24/2006 | District | 3/24/2006 | 3/31/2010 | 3/17/2010 | 3/17/2012 |
Permit Sequence Number | Applied Date | Received Date | Permit Number | Permit Status | Mitigation Type | Unit | Estimated Date | Estimated Amnt (Unit) | Estimated Dollar Amnt | Actual Amnt (Unit) | Actual Dollar Amnt | Completion Date | Bank Name | Mitigation Remarks | Permit Remarks |
28636 | General | NOT APPLICABLE | 0 | 0 | $0.00 | 0 | $0.00 |
Permit Sequence Number | Applied Date | Received Date | Permit Number | Permit Status | Mitigation Type | Unit | Estimated Date | Estimated Amnt (Unit) | Estimated Dollar Amnt | Actual Amnt (Unit) | Actual Dollar Amnt | Completion Date | Bank Name | Mitigation Remarks | Permit Remarks |
3910 | NotApplicable | NOT APPLICABLE | 0 | 0 | $0.00 | 0 | $0.00 |
Permit Sequence Number | Applied Date | Received Date | Permit Number | Permit Status | Mitigation Type | Unit | Estimated Date | Estimated Amnt (Unit) | Estimated Dollar Amnt | Actual Amnt (Unit) | Actual Dollar Amnt | Completion Date | Bank Name | Mitigation Remarks | Permit Remarks |
525 | Required | NOT APPLICABLE | 0 | 0 | $0.00 | 0 | $0.00 |
Permit Sequence Number | Applied Date | Received Date | Permit Number | Permit Status | Mitigation Type | Unit | Estimated Date | Estimated Amnt (Unit) | Estimated Dollar Amnt | Actual Amnt (Unit) | Actual Dollar Amnt | Completion Date | Bank Name | Mitigation Remarks | Permit Remarks |
33873 | NotApplicable | NOT APPLICABLE | 0 | 0 | $0.00 | 0 | $0.00 |
Permit Sequence Number | Applied Date | Received Date | Permit Number | Permit Status | Mitigation Type | Unit | Estimated Date | Estimated Amnt (Unit) | Estimated Dollar Amnt | Actual Amnt (Unit) | Actual Dollar Amnt | Completion Date | Bank Name | Mitigation Remarks | Permit Remarks |
41116 | NotApplicable | NOT APPLICABLE | 0 | 0 | $0.00 | 0 | $0.00 |
Project Manager: KYTC\JAMES.MAYNARD Item #: 5-441.01 Project Description: RECONSTRUCT US 42 AND WIDEN FROM 2 LANES TO 3 LANES (3RD LANE WILL BE A CENTER TURN LANE) FROM JEFFERSON/OLDHAM COUNTY LINE TO RIDGEMOOR DRIVE. PROJECT WILL INCLUDE THE CONSIDERATION OF IMPROVEMENTS TO THE HAYFIELD WAY INTERSECTION. (2004BOPC) Authoritative Source for R/W Data: KROWDS View Communicating All Promises (CAP) Report for Item# 5-441.01 |
Authorized Amount for R/W Phase: 3030000 | ||||||||||||||
RIGHT OF WAY STATUS REPORT (KROWDS)
|
Project Manager: KYTC\JAMES.MAYNARD Item #: 5-441.01 Project Description: RECONSTRUCT US 42 AND WIDEN FROM 2 LANES TO 3 LANES (3RD LANE WILL BE A CENTER TURN LANE) FROM JEFFERSON/OLDHAM COUNTY LINE TO RIDGEMOOR DRIVE. PROJECT WILL INCLUDE THE CONSIDERATION OF IMPROVEMENTS TO THE HAYFIELD WAY INTERSECTION. (2004BOPC) Authoritative Source for Utilities and Rail Tracking Data: KURTS |
Utility Companies | |
Utility Name | Facility Name |
Time Warner Communications | CATV |
AT&T - KY | Communication |
Louisville Water Company | Water |
(Level 3 / CenturyLink Communications, LLC) | Communication |
Louisville Gas & Electric | Natural Gas |
Oldham Co. Environmental Authority | Sewer |
Windstream Holdings II, LLC | Communication |
Louisville Gas and Electric Company | Electric |
Agreements | ||||||||
Utility Company | Agreement Status | Agreement Amnt | Document Type | Estimate Approval Date | Plans Approval Date | Working Days | Estimated Completion Date | Work Status |
Louisville Gas and Electric Company - Electric | Approved | 0 | KRS 179 Keep Cost Agreement | 6/9/2025 | 6/9/2025 | 365 | 8/21/2020 | |
Louisville Water Company - Water | Executed | 160472.48 | Project Relocation Delivery Order PRDO | 9/24/2015 | 0 | 3/30/2019 | 85 |
Project Manager: KYTC\JAMES.MAYNARD Item #: 5-441.01 Project Description: RECONSTRUCT US 42 AND WIDEN FROM 2 LANES TO 3 LANES (3RD LANE WILL BE A CENTER TURN LANE) FROM JEFFERSON/OLDHAM COUNTY LINE TO RIDGEMOOR DRIVE. PROJECT WILL INCLUDE THE CONSIDERATION OF IMPROVEMENTS TO THE HAYFIELD WAY INTERSECTION. (2004BOPC) |
Phase | Vendor |
R | Logan & Gaines, PLLC |
R | CHARLES JOSEPH BIRD |
R | J MICHAEL JONES AND ASSOCIATES |
R | FRANKLIN PRICE INC |
U | GRW AERIAL SURVEYS INC |
R | ALLGEIER COMPANY |
R | LEGACY TITLE COMPANY LLC |
R | HAWORTH MEYER BOLEYN INC |
D | HALL HARMON ENGINEERS INC |
R | J MICHAEL JONES |
R | LOGAN & GAINES PLLC |
D | THELEN ASSOCIATES INC |
R | HMB PROFESSIONAL ENGINEERS |
R | MATTHEW L CHAPMAN |
D | AMERICAN ENGINEERS INC |
U | LOUISVILLE WATER CO |