Highway Plan Phase Info
Phase Funding FY Amount
Design NH 2024 $2,000,000.00
Right of way NH 2026 $6,000,000.00
Utility Relocation NH 2027 $5,000,000.00
Construction NH 2028 $10,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D NH $0.00 2024 AUTHORIZED 4/1/2024 $3,200,000.00
R NH $4,560,000.00 2024 ESTIMATED $0.00
U NH $4,080,000.00 2024 ESTIMATED $0.00
C NH $24,840,000.00 2024 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 73566 7356603D $500,000.00 $0.00 $361,391.18 $135,267.81 $3,341.01
D 73566 7356604D $500,000.00 $0.00 $2,354.01 $0.00 $497,860.67
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: IMPROVE US-27 FROM WEST LANCASTER BYPASS TO KY-34. (2006BOPC) (16CCN)(18CCR) (2020CCR)
Location:
Route 1 Garrard County US-27 from MP 5.199 to MP 10.331
Route 2 County - from MP to MP
Item #: 7-196.30
Project Manager: KYTC\ROBIN.SPRAGUE
Road Engineer:
Type of Work: RECONSTRUCTION
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\ROBIN.SPRAGUE       Item #: 7-196.30
Project Description: IMPROVE US-27 FROM WEST LANCASTER BYPASS TO KY-34. (2006BOPC) (16CCN)(18CCR) (2020CCR)

Milestones
Milestones Status Status Date Scheduled
RIGHT OF WAY PLANS TO CENTRAL OFFICE UNKNOWN 12/18/2007 12/18/2007
TRAFFIC PLANS - SIGNING UNKNOWN 12/18/2007 12/18/2007
GEOTEC ENGINEERING - BRIDGES UNKNOWN 12/18/2007 12/18/2007
TRAFFIC PLANS - SIGNALS UNKNOWN 12/18/2007 12/18/2007
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 12/18/2007 12/18/2007
TRAFFIC PLANS - LIGHTING UNKNOWN 12/18/2007 12/18/2007
GEOTEC ENGINEERING - ROADWAY UNKNOWN 12/18/2007 12/18/2007
JOINT INSPECTION UNKNOWN 12/18/2007 12/18/2007
ROAD PLANS TO CENTRAL OFFICE UNKNOWN 12/18/2007 12/18/2007
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 12/18/2007 12/18/2007
DRAINAGE INSPECTION UNKNOWN 12/18/2007 12/18/2007
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 12/18/2007 12/18/2007
PRELIMINARY LINE AND GRADE UNKNOWN 12/18/2007 12/18/2007
 
Project Manager: KYTC\ROBIN.SPRAGUE       Item #: 7-196.30
Project Description: IMPROVE US-27 FROM WEST LANCASTER BYPASS TO KY-34. (2006BOPC) (16CCN)(18CCR) (2020CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
FONSI RE 9/11/2019 9/30/2019 3/11/2019 3/11/2021
FONSI 3/16/2012 11/1/2013 12/2/2013 12/2/2015
EA 4/6/2004 Third Rock Consultants, LLC 12/1/2011 3/15/2012 3/15/2014

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\ROBIN.SPRAGUE       Item #: 7-196.30
Project Description: IMPROVE US-27 FROM WEST LANCASTER BYPASS TO KY-34. (2006BOPC) (16CCN)(18CCR) (2020CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 7-196.30
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\ROBIN.SPRAGUE       Item #: 7-196.30
Project Description: IMPROVE US-27 FROM WEST LANCASTER BYPASS TO KY-34. (2006BOPC) (16CCN)(18CCR) (2020CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\ROBIN.SPRAGUE       Item #: 7-196.30
Project Description: IMPROVE US-27 FROM WEST LANCASTER BYPASS TO KY-34. (2006BOPC) (16CCN)(18CCR) (2020CCR)
Phase Vendor
D STANTEC CONSULTING SERVICES INC