Highway Plan Phase Info
Phase Funding FY Amount
Design STP 2019 $1,500,000.00
Right of way STP 2022 $4,000,000.00
Utility Relocation STP 2023 $750,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D STP $1,500,000.00 2019 NOT REQUIRED $0.00
R STP $5,000,000.00 2022 ESTIMATED $0.00
U STP $750,000.00 2023 ESTIMATED $0.00
C STP $15,000,000.00 2025 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
R/W Clearance:
Utility Clearance:
Some critical dates have not been assigned. (Letting Date not Established)

Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-236 TO I-275. (18CCR)(DESIGN CONDUCTED UNDER ITEM 3 6-444)
Location:
Route 1 BOONE County KY-3076 from MP 0 to MP 1.05
Route 2 County - from MP to MP
Item #: 6-445.00
Project Manager: KYTC\MIKE.BEZOLD
Road Engineer: consultant
Type of Work: MAJOR WIDENING(O)

Concerns:

Bridge Engineer:
Bridge Structure Number:
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-445.00
Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-236 TO I-275. (18CCR)(DESIGN CONDUCTED UNDER ITEM 3 6-444)
Milestones
Milestones Status Status Date Scheduled
PRELIMINARY LINE AND GRADE REQUIRED 02/28/2019 04/01/2020
DRAINAGE INSPECTION REQUIRED 02/28/2019
JOINT INSPECTION REQUIRED 02/28/2019 06/01/2021
GEOTEC ENGINEERING - ROADWAY REQUIRED 02/28/2019
GEOTEC ENGINEERING - BRIDGES UNKNOWN 07/10/2018
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 07/10/2018
RIGHT OF WAY PLANS TO CENTRAL OFFICE REQUIRED 02/28/2019 08/01/2021
ROAD PLANS TO CENTRAL OFFICE REQUIRED 02/28/2019 08/01/2024
TRAFFIC PLANS - SIGNING UNKNOWN 07/10/2018
TRAFFIC PLANS - LIGHTING UNKNOWN 07/10/2018
TRAFFIC PLANS - SIGNALS UNKNOWN 07/10/2018
TRAFFIC PLANS - TRAFFIC CONTROL REQUIRED 02/28/2019
 

Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-445.00
Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-236 TO I-275. (18CCR)(DESIGN CONDUCTED UNDER ITEM 3 6-444)

Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
PRELIMINARY 2/4/2019

No IND Permit Data Available

No NW Permit Data Available

No WQC Permit Data Available

No KPD Permit Data Available

No TVA Permit Data Available

Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-445.00
Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-236 TO I-275. (18CCR)(DESIGN CONDUCTED UNDER ITEM 3 6-444)

This Project has no Right Of Way Data available.

Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-445.00
Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-236 TO I-275. (18CCR)(DESIGN CONDUCTED UNDER ITEM 3 6-444)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-445.00
Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-236 TO I-275. (18CCR)(DESIGN CONDUCTED UNDER ITEM 3 6-444)
This Project has no Vendors Assigned.