Highway Plan Phase Info
Phase Funding FY Amount
Construction STP 2022 $7,100,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D FED $0.00 2020 AUTHORIZED 5/18/2022 $1,500,000.00
R FED $0.00 2021 AUTHORIZED 5/18/2022 $3,250,000.00
U FED $0.00 2021 AUTHORIZED 5/18/2022 $3,265,000.00
C FED $0.00 2022 AWARDED 5/18/2022 $11,504,460.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
C 12374 1237401C $11,504,460.00 $0.00 $7,476,137.85 $3,682,744.39 $385,399.38
D 12374 1237401D $0.00 $0.00 $0.00 $0.00 $0.00
R 12374 1237401R $3,250,000.00 $0.00 $2,054,003.57 $106,800.05 $1,095,025.47
U 12374 1237401U $3,265,000.00 $0.00 $298,465.90 $91,718.58 $2,892,600.77
C 12374 1237403C $0.00 $0.00 $0.00 $0.00 $0.00
R/W Clearance:
Utility Clearance:


Check Prints: 1/13/2022
Final Plans: 3/10/2022
Projects Due to PS&E/ Central Office: 3/14/2022
Projects Due to Construction Procurement: 3/24/2022
Last day to Advertise Federal-Aid Projects
(Notice to Contractors):
4/7/2022
Last Day to Advertise State Funded Projects
(Notice to Contractors):
4/21/2022
Letting Date: 4/28/2022
Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-1017 TO I-275. (18CCR) (2020CCR) (2022CCR)
Location:
Route 1 Boone County KY-3076 from MP 0 to MP 1.05
Route 2 County - from MP to MP
Item #: 6-445.00
Project Manager: KYTC\MIKE.BEZOLD
Road Engineer: consultant
Type of Work: MAJOR WIDENING
Concerns:
Bridge Engineer:
Bridge Structure Number: 008B00066N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 92.9
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-445.00
Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-1017 TO I-275. (18CCR) (2020CCR) (2022CCR)

Milestones
Milestones Status Status Date Scheduled
TRAFFIC PLANS - TRAFFIC CONTROL REQUIRED 02/28/2019 02/28/2019
GEOTEC ENGINEERING - ROADWAY REQUIRED 02/28/2019 02/28/2019
DRAINAGE INSPECTION REQUIRED 02/28/2019 02/28/2019
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
GEOTEC ENGINEERING - BRIDGES UNKNOWN 07/10/2018 07/10/2018
RIGHT OF WAY PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 08/01/2021 08/01/2021
TRAFFIC PLANS - SIGNALS UNKNOWN 07/10/2018 07/10/2018
JOINT INSPECTION SCHEDULED COMPLETION DATE 06/01/2021 06/01/2021
ROAD PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 08/01/2024 08/01/2024
PRELIMINARY LINE AND GRADE SCHEDULED COMPLETION DATE 04/01/2020 04/01/2020
JOINT INSPECTION SCHEDULED COMPLETION DATE 06/01/2021 06/01/2021
ROAD PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 08/01/2024 08/01/2024
TRAFFIC PLANS - LIGHTING UNKNOWN 07/10/2018 07/10/2018
PRELIMINARY LINE AND GRADE SCHEDULED COMPLETION DATE 04/01/2020 04/01/2020
RIGHT OF WAY PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 08/01/2021 08/01/2021
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - SIGNING UNKNOWN 07/10/2018 07/10/2018
 
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-445.00
Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-1017 TO I-275. (18CCR) (2020CCR) (2022CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
CE LVL 2 RE 8/10/2021 8/10/2021 9/1/2021 8/16/2021 8/16/2023
District Office CE LVL 2 7/29/2020 2/1/2021 1/29/2021 1/29/2023
Environmental Analysis CE LVL 3 5/13/2019 Lochner, H.W., Inc. 8/1/2020

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-445.00
Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-1017 TO I-275. (18CCR) (2020CCR) (2022CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 6-445.00
Authorized Amount for R/W Phase: 3250000
This Project has no Right Of Way Data available from RWMS.
RIGHT OF WAY STATUS REPORT (KROWDS)
KROWDS Parcel Input Summary (RW000044)
Total Parcels 16
Parcels Cleared 16
Offers Made 16
Deeds Recorded 12
Suits Submitted to CO 4
Right of Entry 4
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-445.00
Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-1017 TO I-275. (18CCR) (2020CCR) (2022CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
CenturyLink Communications LLC dba Lumen Technologies Group Communication
Cincinnati Bell Telephone Telephone
Boone County Water District Water
Owen Electric Cooperative Electric
Duke Energy Kentucky (Gas) Natural Gas
Charter Communications Holdings, LLC dba Spectrum CATV
Northern Kentucky Water District Water
Agreements
Utility Company Agreement Status Agreement Amnt Document Type Estimate Approval Date Plans Approval Date Working Days Estimated Completion Date Work Status
Boone County Water District - Water Executed 0 HWY Contractor 177 Betterment Agreement 7/13/2023 7/13/2023 0
Boone County Water District - Water Executed 0 HWY Contractor 177 Betterment Agreement 7/13/2023 7/13/2023 0
Boone County Water District - Water Executed 13750 Engineering Services Work by Highway Contractor Agreement 7/13/2023 7/13/2023 0
Charter Communications Holdings, LLC dba Spectrum - CATV Executed 0 No Charge Agreement 30
Cincinnati Bell Telephone - Telephone Executed 0 No Charge Agreement 60
Cincinnati Bell Telephone - Telephone Executed 0 No Charge Agreement 120
Duke Energy Kentucky (Gas) - Natural Gas Executed 0 No Charge Agreement 225
Duke Energy Kentucky (Gas) - Natural Gas Executed 0 No Charge Agreement 30
Duke Energy Kentucky (Gas) - Natural Gas Executed 0 No Charge Agreement 40
Northern Kentucky Water District - Water Executed 29800 Engineering Services Work by Highway Contractor Agreement 3/7/2022 3/7/2022 0
Owen Electric Cooperative - Electric Executed 249707.01 KRS 179 Keep Cost Agreement 7/18/2022 7/18/2022 120
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-445.00
Project Description: IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 (MINEOLA PIKE) FROM KY-1017 TO I-275. (18CCR) (2020CCR) (2022CCR)
Phase Vendor
R H W Lochner Inc
C LYNN BLUE PRINT AND SUPPLY CO
R Fox, Wood & Wood
R FRANKLIN PRICE INC
C KENTUCKY NATURAL LANDS TRUST
C H W Lochner Inc