The Commonwealth pays employees on a semi-monthly basis with a scheduled pay day on the 15th and 30th of each month. The two monthly pay periods are from the 1st to the 15th of the month and the 16th through the last day of the month. Pay check distribution is delayed by one pay period to allow for system processing. For example work performed during the 1st to the 15th day of the month is paid to the employee on the 30th of the month. Accordingly the cost accounting charges for labor costs posting in eMARS to operating accounts and highway projects are also delayed by approximately one pay period.
A good rule of measure is that the cost accounting charges for the pay period ending on the 15th of the month will post to eMARS by the 25th and those for the pay period ending on the last day of the month will post to eMARS by the 10th of the following month.

x close panel
Detailed Project Expenditure Report
Total E-MARS Expenditures for 7966403D = $753,732.45
Click here for Labor Costs Information
Year Month PBU Charge District Object Phase Program Code County Date ACT Activity Name Trans ID Reference # Vendor Name Expenditure Line Description
2024 9 FD04 04 E111 D 7966403D 090 3/11/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR031O1062406810081 $322.79 000001086253-3562504200
2024 9 FD04 04 E111 D 7966403D 090 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810081 $13.33 000001086253-3562504200
2024 9 FD04 04 E121 D 7966403D 090 3/11/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR031O1062406810081 $24.36 000001086253-3562504200
2024 9 FD04 04 E121 D 7966403D 090 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810081 $1.00 000001086253-3562504200
2024 9 FD04 04 E122 D 7966403D 090 3/11/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR031O1062406810081 $213.51 000001086253-3562504200
2024 9 FD04 04 E122 D 7966403D 090 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810081 $8.82 000001086253-3562504200
2024 9 FD04 04 E123 D 7966403D 090 3/11/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR031O1062406810081 $49.62 000001086253-3562504200
2024 9 FD04 04 E123 D 7966403D 090 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810081 $2.03 000001086253-3562504200
2024 9 FD04 04 E143 D 7966403D 090 3/1/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400176215 PON22300002042 HDR ENGINEERING INC $54,000.00 Nelson-Bullitt County 4-8307.2
2024 8 FD04 00 E121 D 7966403D 090 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408937 $3.78 000001090632-3562500061
2024 8 FD04 00 E122 D 7966403D 090 2/26/2024 0060 ENV STUDIES-ARCHAEOLOGY CA-XR022O1062405408937 $329.63 000001090632-3562500061
2024 8 FD04 00 E122 D 7966403D 090 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408937 $32.97 000001090632-3562500061
2024 8 FD04 00 E123 D 7966403D 090 2/26/2024 0060 ENV STUDIES-ARCHAEOLOGY CA-XR022O1062405408937 $80.77 000001090632-3562500061
2024 8 FD04 00 E123 D 7966403D 090 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408937 $7.98 000001090632-3562500061
2024 8 FD04 00 E124 D 7966403D 090 2/26/2024 0060 ENV STUDIES-ARCHAEOLOGY CA-XR022O1062405408937 $0.18 000001090632-3562500061
2024 8 FD04 00 E124 D 7966403D 090 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408937 $0.02 000001090632-3562500061
2024 8 FD04 00 E111 D 7966403D 090 2/26/2024 0060 ENV STUDIES-ARCHAEOLOGY CA-XR022O1062405408937 $498.15 000001090632-3562500061
2024 8 FD04 00 E111 D 7966403D 090 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408937 $49.82 000001090632-3562500061
2024 8 FD04 04 E111 D 7966403D 090 2/26/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR022O1062405408906 $1,417.79 000001086253-3562504200
2024 8 FD04 04 E111 D 7966403D 090 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408906 $168.18 000001086253-3562504200
2024 8 FD04 04 E121 D 7966403D 090 2/26/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR022O1062405408906 $107.00 000001086253-3562504200
2024 8 FD04 04 E121 D 7966403D 090 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408906 $12.70 000001086253-3562504200
2024 8 FD04 04 E122 D 7966403D 090 2/26/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR022O1062405408906 $938.16 000001086253-3562504200
2024 8 FD04 04 E122 D 7966403D 090 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408906 $111.28 000001086253-3562504200
2024 8 FD04 04 E123 D 7966403D 090 2/26/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR022O1062405408906 $218.20 000001086253-3562504200
2024 8 FD04 04 E123 D 7966403D 090 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408906 $25.59 000001086253-3562504200
2024 8 FD04 00 E121 D 7966403D 090 2/26/2024 0060 ENV STUDIES-ARCHAEOLOGY CA-XR022O1062405408937 $37.73 000001090632-3562500061
2024 8 FD04 04 E124 D 7966403D 090 2/26/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR022O1062405408906 $0.44 000001086253-3562504200
2024 8 FD04 04 E124 D 7966403D 090 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408906 $0.05 000001086253-3562504200
2024 8 FD04 04 E111 D 7966403D 090 2/9/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR021O1062403907672 $528.70 000001086253-3562504200
2024 8 FD04 04 E111 D 7966403D 090 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907672 $22.95 000001086253-3562504200
2024 8 FD04 04 E121 D 7966403D 090 2/9/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR021O1062403907672 $39.91 000001086253-3562504200
2024 8 FD04 04 E121 D 7966403D 090 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907672 $1.73 000001086253-3562504200
2024 8 FD04 04 E122 D 7966403D 090 2/9/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR021O1062403907672 $349.68 000001086253-3562504200
2024 8 FD04 04 E122 D 7966403D 090 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907672 $15.18 000001086253-3562504200
2024 8 FD04 04 E123 D 7966403D 090 2/9/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR021O1062403907672 $81.28 000001086253-3562504200
2024 8 FD04 04 E123 D 7966403D 090 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907672 $3.49 000001086253-3562504200
2024 8 FD04 04 E143 D 7966403D 090 2/7/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400157970 PON22300002042 HDR ENGINEERING INC $39,160.00 Nelson-Bullitt County 4-8307.2
2024 7 FD04 04 E111 D 7966403D 090 1/24/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR012O1062402306598 $547.62 000001086253-3562504200
2024 7 FD04 04 E111 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306598 $131.80 000001086253-3562504200
2024 7 FD04 04 E121 D 7966403D 090 1/24/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR012O1062402306598 $41.32 000001086253-3562504200
2024 7 FD04 04 E121 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306598 $9.95 000001086253-3562504200
2024 7 FD04 04 E122 D 7966403D 090 1/24/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR012O1062402306598 $362.32 000001086253-3562504200
2024 7 FD04 04 E122 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306598 $87.21 000001086253-3562504200
2024 7 FD04 04 E123 D 7966403D 090 1/24/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR012O1062402306598 $84.37 000001086253-3562504200
2024 7 FD04 04 E123 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306598 $20.05 000001086253-3562504200
2024 7 FD04 04 E124 D 7966403D 090 1/24/2024 0640 ENV STUDIES-GEN-CONSULT CA-XR012O1062402306598 $0.17 000001086253-3562504200
2024 7 FD04 04 E124 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306598 $0.04 000001086253-3562504200
2024 7 FD04 00 E111 D 7966403D 090 1/24/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306597 $568.22 000001086197-3562500630
2024 7 FD04 00 E111 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306597 $200.99 000001086197-3562500630
2024 7 FD04 00 E121 D 7966403D 090 1/24/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306597 $41.06 000001086197-3562500630
2024 7 FD04 00 E121 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306597 $14.52 000001086197-3562500630
2024 7 FD04 00 E122 D 7966403D 090 1/24/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306597 $376.03 000001086197-3562500636
2024 7 FD04 00 E122 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306597 $133.01 000001086197-3562500630
2024 7 FD04 00 E123 D 7966403D 090 1/24/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306597 $133.39 000001086197-3562500630
2024 7 FD04 00 E123 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306597 $46.82 000001086197-3562500630
2024 7 FD04 00 E124 D 7966403D 090 1/24/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306597 $0.16 000001086197-3562500636
2024 7 FD04 00 E124 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306597 $0.06 000001086197-3562500636
2024 7 FD04 00 E111 D 7966403D 120 1/24/2024 0070 ENV STUDIES-HIST/CULTURAL CA-XR012O1062402306646 $695.45 000001090742-3562500061
2024 7 FD04 00 E111 D 7966403D 120 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306646 $154.55 000001090742-3562500061
2024 7 FD04 00 E121 D 7966403D 120 1/24/2024 0070 ENV STUDIES-HIST/CULTURAL CA-XR012O1062402306646 $53.21 000001090742-3562500061
2024 7 FD04 00 E121 D 7966403D 120 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306646 $11.82 000001090742-3562500061
2024 7 FD04 00 E122 D 7966403D 120 1/24/2024 0070 ENV STUDIES-HIST/CULTURAL CA-XR012O1062402306646 $460.17 000001090742-3562500061
2024 7 FD04 00 E122 D 7966403D 120 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306646 $102.27 000001090742-3562500061
2024 7 FD04 00 E111 D 7966403D 090 1/24/2024 0060 ENV STUDIES-ARCHAEOLOGY CA-XR012O1062402306638 $248.88 000001090632-3562500061
2024 7 FD04 00 E111 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306638 $93.66 000001090632-3562500061
2024 7 FD04 00 E121 D 7966403D 090 1/24/2024 0060 ENV STUDIES-ARCHAEOLOGY CA-XR012O1062402306638 $18.87 000001090632-3562500061
2024 7 FD04 00 E121 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306638 $7.10 000001090632-3562500061
2024 7 FD04 00 E122 D 7966403D 090 1/24/2024 0060 ENV STUDIES-ARCHAEOLOGY CA-XR012O1062402306638 $164.81 000001090632-3562500061
2024 7 FD04 00 E122 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306638 $61.98 000001090632-3562500061
2024 7 FD04 00 E123 D 7966403D 090 1/24/2024 0060 ENV STUDIES-ARCHAEOLOGY CA-XR012O1062402306638 $40.52 000001090632-3562500061
2024 7 FD04 00 E123 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306638 $15.00 000001090632-3562500061
2024 7 FD04 00 E124 D 7966403D 090 1/24/2024 0060 ENV STUDIES-ARCHAEOLOGY CA-XR012O1062402306638 $0.09 000001090632-3562500061
2024 7 FD04 00 E124 D 7966403D 090 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306638 $0.03 000001090632-3562500061
2024 7 FD04 04 E143 D 7966403D 090 1/12/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400138880 PON22300002042 HDR ENGINEERING INC $97,000.00 Nelson-Bullitt County 4-8307.2
2024 7 FD04 00 E111 D 7966403D 090 1/8/2024 0010 ENV STUDIES-UST/HZM CA-XR011O1062400505749 $1,411.97 000001090450-3562500061
2024 7 FD04 00 E111 D 7966403D 090 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505749 $714.28 000001090450-3562500061
2024 7 FD04 00 E121 D 7966403D 090 1/8/2024 0010 ENV STUDIES-UST/HZM CA-XR011O1062400505749 $102.11 000001090450-3562500061
2024 7 FD04 00 E121 D 7966403D 090 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505749 $51.74 000001090450-3562500061
2024 7 FD04 00 E122 D 7966403D 090 1/8/2024 0010 ENV STUDIES-UST/HZM CA-XR011O1062400505749 $934.45 000001090450-3562500061
2024 7 FD04 00 E122 D 7966403D 090 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505749 $472.63 000001090450-3562500061
2024 7 FD04 00 E123 D 7966403D 090 1/8/2024 0010 ENV STUDIES-UST/HZM CA-XR011O1062400505749 $268.25 000001090450-3562500061
2024 7 FD04 00 E123 D 7966403D 090 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505749 $131.47 000001090450-3562500061
2024 7 FD04 00 E111 D 7966403D 121 1/4/2024 0010 ENV STUDIES-UST/HZM CA-XR122N1062335504658 $100.85 000001090232-3562500061
2024 7 FD04 00 E111 D 7966403D 121 1/4/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504658 $16.11 000001090232-3562500061
2024 7 FD04 00 E121 D 7966403D 121 1/4/2024 0010 ENV STUDIES-UST/HZM CA-XR122N1062335504658 $7.50 000001090232-3562500061
2024 7 FD04 00 E121 D 7966403D 121 1/4/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504658 $1.20 000001090232-3562500061
2024 7 FD04 00 E122 D 7966403D 121 1/4/2024 0010 ENV STUDIES-UST/HZM CA-XR122N1062335504658 $66.63 000001090232-3562500061
2024 7 FD04 00 E122 D 7966403D 121 1/4/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504658 $10.66 000001090232-3562500061
2024 7 FD04 00 E123 D 7966403D 121 1/4/2024 0010 ENV STUDIES-UST/HZM CA-XR122N1062335504658 $14.43 000001090232-3562500061
2024 7 FD04 00 E123 D 7966403D 121 1/4/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504658 $2.28 000001090232-3562500061
2024 7 FD04 00 E124 D 7966403D 121 1/4/2024 0010 ENV STUDIES-UST/HZM CA-XR122N1062335504658 $0.03 000001090232-3562500061
2024 6 FD04 04 E111 D 7966403D 090 12/22/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR122N1062335504623 $293.27 000001086253-3562504200
2024 6 FD04 04 E111 D 7966403D 090 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504623 $48.89 000001086253-3562504200
2024 6 FD04 04 E121 D 7966403D 090 12/22/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR122N1062335504623 $22.14 000001086253-3562504200
2024 6 FD04 04 E121 D 7966403D 090 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504623 $3.69 000001086253-3562504200
2024 6 FD04 04 E122 D 7966403D 090 12/22/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR122N1062335504623 $194.10 000001086253-3562504200
2024 6 FD04 04 E122 D 7966403D 090 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504623 $32.34 000001086253-3562504200
2024 6 FD04 04 E123 D 7966403D 090 12/22/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR122N1062335504623 $39.18 000001086253-3562504200
2024 6 FD04 04 E123 D 7966403D 090 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504623 $6.44 000001086253-3562504200
2024 6 FD04 04 E124 D 7966403D 090 12/22/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR122N1062335504623 $0.09 000001086253-3562504200
2024 6 FD04 04 E124 D 7966403D 090 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504623 $0.02 000001086253-3562504200
2024 6 FD04 00 E111 D 7966403D 090 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504622 $130.49 000001086197-3562500630
2024 6 FD04 00 E111 D 7966403D 090 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504622 $22.18 000001086197-3562500630
2024 6 FD04 00 E121 D 7966403D 090 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504622 $9.43 000001086197-3562500630
2024 6 FD04 00 E121 D 7966403D 090 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504622 $1.61 000001086197-3562500630
2024 6 FD04 00 E122 D 7966403D 090 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504622 $86.35 000001086197-3562500630
2024 6 FD04 00 E122 D 7966403D 090 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504622 $14.68 000001086197-3562500630
2024 6 FD04 00 E123 D 7966403D 090 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504622 $25.59 000001086197-3562500630
2024 6 FD04 00 E123 D 7966403D 090 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504622 $4.31 000001086197-3562500630
2024 6 FD04 00 E124 D 7966403D 090 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504622 $0.04 000001086197-3562500630
2024 6 FD04 04 E143 D 7966403D 090 12/12/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400117485 PON22300002042 HDR ENGINEERING INC $78,500.00 Nelson-Bullitt County 4-8307.2
2024 5 FD04 04 E122 D 7966403D 090 11/22/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR112N1062332502527 $478.78 000001086253-3562504200
2024 5 FD04 04 E122 D 7966403D 090 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502527 $77.39 000001086253-3562504200
2024 5 FD04 04 E123 D 7966403D 090 11/22/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR112N1062332502527 $96.63 000001086253-3562504200
2024 5 FD04 04 E123 D 7966403D 090 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502527 $15.41 000001086253-3562504200
2024 5 FD04 04 E124 D 7966403D 090 11/22/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR112N1062332502527 $0.22 000001086253-3562504200
2024 5 FD04 04 E124 D 7966403D 090 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502527 $0.03 000001086253-3562504200
2024 5 FD04 04 E111 D 7966403D 090 11/22/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR112N1062332502526 $723.64 000001086253-3562504200
2024 5 FD04 04 E111 D 7966403D 090 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502526 $116.95 000001086253-3562504200
2024 5 FD04 04 E121 D 7966403D 090 11/22/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR112N1062332502526 $54.61 000001086253-3562504200
2024 5 FD04 04 E121 D 7966403D 090 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502526 $8.83 000001086253-3562504200
2024 5 FD04 04 E143 D 7966403D 090 11/15/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400097086 PON22300002042 HDR ENGINEERING INC $74,636.00 Nelson-Bullitt County 4-8307.2
2024 5 FD04 04 E111 D 7966403D 090 11/9/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR111N1062331201490 $269.02 000001086253-3562504200
2024 5 FD04 04 E111 D 7966403D 090 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201490 $37.29 000001086253-3562504200
2024 5 FD04 04 E121 D 7966403D 090 11/9/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR111N1062331201490 $20.30 000001086253-3562504200
2024 5 FD04 04 E121 D 7966403D 090 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201490 $2.82 000001086253-3562504200
2024 5 FD04 04 E122 D 7966403D 090 11/9/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR111N1062331201490 $177.93 000001086253-3562504200
2024 5 FD04 04 E122 D 7966403D 090 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201490 $24.68 000001086253-3562504200
2024 5 FD04 04 E123 D 7966403D 090 11/9/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR111N1062331201490 $35.90 000001086253-3562504200
2024 5 FD04 04 E123 D 7966403D 090 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201490 $4.91 000001086253-3562504200
2024 4 FD04 04 E143 D 7966403D 090 10/10/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400070712 PON22300002042 HDR ENGINEERING INC $26,500.00 Nelson-Bullitt County 4-8307.2
2024 4 FD04 04 E111 D 7966403D 090 10/9/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR101N1062328009704 $282.91 000001086253-3562504200
2024 4 FD04 04 E111 D 7966403D 090 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009704 $18.11 000001086253-3562504200
2024 4 FD04 04 E121 D 7966403D 090 10/9/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR101N1062328009704 $21.32 000001086253-3562504200
2024 4 FD04 04 E121 D 7966403D 090 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009704 $1.37 000001086253-3562504200
2024 4 FD04 04 E122 D 7966403D 090 10/9/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR101N1062328009704 $186.97 000001086253-3562504200
2024 4 FD04 04 E122 D 7966403D 090 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009704 $11.99 000001086253-3562504200
2024 4 FD04 04 E123 D 7966403D 090 10/9/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR101N1062328009704 $42.98 000001086253-3562504200
2024 4 FD04 04 E123 D 7966403D 090 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009704 $2.72 000001086253-3562504200
2024 3 FD04 00 E122 D 7966403D 090 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106105 $1.34 000001086197-3562500636
2024 3 FD04 00 E123 D 7966403D 090 9/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091N1062325106105 $11.72 000001086197-3562500636
2024 3 FD04 00 E123 D 7966403D 090 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106105 $0.39 000001086197-3562500636
2024 3 FD04 00 E111 D 7966403D 090 9/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091N1062325106104 $60.73 000001086197-3562500636
2024 3 FD04 00 E111 D 7966403D 090 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106104 $2.03 000001086197-3562500636
2024 3 FD04 00 E121 D 7966403D 090 9/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091N1062325106104 $4.33 000001086197-3562500636
2024 3 FD04 00 E121 D 7966403D 090 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106104 $0.15 000001086197-3562500636
2024 3 FD04 00 E122 D 7966403D 090 9/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091N1062325106104 $40.22 000001086197-3562500636
2024 3 FD04 04 E143 D 7966403D 090 9/7/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400046884 PON22300002042 HDR ENGINEERING INC $51,000.00 Nelson-Bullitt County 4-8307.2
2024 2 FD04 04 E143 D 7966403D 090 8/18/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400025753 PON22300002042 HDR ENGINEERING INC $45,000.00 Nelson-Bullitt County 4-8307.2
2024 1 FD04 04 E143 D 7966403D 090 7/17/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400009913 PON22300002042 HDR ENGINEERING INC $63,000.00 Nelson-Bullitt County 4-8307.2
2024 1 FD04 00 E111 D 7966403D 090 7/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071N1062319101558 $508.14 000001086197-3562500630
2024 1 FD04 00 E111 D 7966403D 090 7/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101558 $12.51 000001086197-3562500630
2024 1 FD04 00 E121 D 7966403D 090 7/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071N1062319101558 $35.49 000001086197-3562500630
2024 1 FD04 00 E121 D 7966403D 090 7/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101558 $0.88 000001086197-3562500630
2024 1 FD04 00 E122 D 7966403D 090 7/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071N1062319101558 $396.29 000001086197-3562500630
2024 1 FD04 00 E122 D 7966403D 090 7/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101558 $9.76 000001086197-3562500630
2024 1 FD04 00 E123 D 7966403D 090 7/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071N1062319101558 $110.76 000001086197-3562500630
2024 1 FD04 00 E123 D 7966403D 090 7/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101558 $2.71 000001086197-3562500630
2023 12 FD04 04 E143 D 7966403D 090 6/23/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300251370 PON22300002042 HDR ENGINEERING INC $67,600.00 Nelson-Bullitt County 4-8307.2
2023 11 FD04 04 E143 D 7966403D 090 5/19/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300224613 PON22300002042 HDR ENGINEERING INC $85,596.00 Nelson-Bullitt County 4-8307.2
2023 10 FD04 04 E143 D 7966403D 090 4/19/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300197331 PON22300002042 HDR ENGINEERING INC $49,700.00 Nelson-Bullitt County 4-8307.2
2023 9 FD04 00 E111 D 7966403D 121 3/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR031N1062306703679 $294.70 000001086314-3562500061
2023 9 FD04 00 E111 D 7966403D 121 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703679 $66.98 000001086314-3562500061
2023 9 FD04 00 E121 D 7966403D 121 3/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR031N1062306703679 $20.68 000001086314-3562500061
2023 9 FD04 00 E121 D 7966403D 121 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703679 $4.69 000001086314-3562500061
2023 9 FD04 00 E122 D 7966403D 121 3/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR031N1062306703679 $229.64 000001086314-3562500061
2023 9 FD04 00 E122 D 7966403D 121 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703679 $52.25 000001086314-3562500061
2023 9 FD04 00 E123 D 7966403D 121 3/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR031N1062306703679 $66.34 000001086314-3562500061
2023 9 FD04 00 E123 D 7966403D 121 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703679 $14.95 000001086314-3562500061
2023 8 FD04 04 E111 D 7966403D 090 2/15/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR021N1062303901451 $222.52 000001086253-3562504200
2023 8 FD04 04 E111 D 7966403D 090 2/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901451 $55.47 000001086253-3562504200
2023 8 FD04 04 E121 D 7966403D 090 2/15/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR021N1062303901451 $16.74 000001086253-3562504200
2023 8 FD04 04 E121 D 7966403D 090 2/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901451 $4.17 000001086253-3562504200
2023 8 FD04 04 E122 D 7966403D 090 2/15/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR021N1062303901451 $173.51 000001086253-3562504200
2023 8 FD04 04 E122 D 7966403D 090 2/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901451 $43.26 000001086253-3562504200
2023 8 FD04 04 E123 D 7966403D 090 2/15/2023 0640 ENV STUDIES-GEN-CONSULT CA-XR021N1062303901451 $35.95 000001086253-3562504200
2023 8 FD04 04 E123 D 7966403D 090 2/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901451 $8.83 000001086253-3562504200
2023 8 FD04 00 E111 D 7966403D 121 2/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR021N1062303901456 $157.95 000001086314-3562500061
2023 8 FD04 00 E111 D 7966403D 121 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901456 $20.85 000001086314-3562500061
2023 8 FD04 00 E121 D 7966403D 121 2/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR021N1062303901456 $11.08 000001086314-3562500061
2023 8 FD04 00 E121 D 7966403D 121 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901456 $1.46 000001086314-3562500061
2023 8 FD04 00 E122 D 7966403D 121 2/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR021N1062303901456 $123.20 000001086314-3562500061
2023 8 FD04 00 E122 D 7966403D 121 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901456 $16.26 000001086314-3562500061
2023 8 FD04 00 E123 D 7966403D 121 2/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR021N1062303901456 $35.57 000001086314-3562500061
2023 8 FD04 00 E123 D 7966403D 121 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901456 $4.65 000001086314-3562500061
2023 8 FD04 00 E111 D 7966403D 090 2/9/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021N1062303901449 $245.79 000001086197-3562500636
2023 8 FD04 00 E111 D 7966403D 090 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901449 $22.29 000001086197-3562500636
2023 8 FD04 00 E121 D 7966403D 090 2/9/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021N1062303901449 $17.20 000001086197-3562500636
2023 8 FD04 00 E121 D 7966403D 090 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901449 $1.56 000001086197-3562500636
2023 8 FD04 00 E122 D 7966403D 090 2/9/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021N1062303901449 $191.74 000001086197-3562500636
2023 8 FD04 00 E122 D 7966403D 090 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901449 $17.39 000001086197-3562500636
2023 8 FD04 00 E123 D 7966403D 090 2/9/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021N1062303901449 $58.60 000001086197-3562500636
2023 8 FD04 00 E123 D 7966403D 090 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901449 $5.27 000001086197-3562500636