The Commonwealth pays employees on a semi-monthly basis with a scheduled pay day on the 15th and 30th of each month. The two monthly pay periods are from the 1st to the 15th of the month and the 16th through the last day of the month. Pay check distribution is delayed by one pay period to allow for system processing. For example work performed during the 1st to the 15th day of the month is paid to the employee on the 30th of the month. Accordingly the cost accounting charges for labor costs posting in eMARS to operating accounts and highway projects are also delayed by approximately one pay period.
A good rule of measure is that the cost accounting charges for the pay period ending on the 15th of the month will post to eMARS by the 25th and those for the pay period ending on the last day of the month will post to eMARS by the 10th of the following month.

x close panel
Detailed Project Expenditure Report
Total E-MARS Expenditures for 1683601D = $321,634.75
Click here for Labor Costs Information
Year Month PBU Charge District Object Phase Program Code County Date ACT Activity Name Trans ID Reference # Vendor Name Expenditure Line Description
2025 6 FD52 06 E143 D 1683601D 059 12/19/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2500130923 PON22400002789 H W Lochner Inc $92,737.81 Kenton Co. 6-80203
2025 6 FD52 06 E143 D 1683601D 059 12/19/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2500130923 PON22400002789 H W Lochner Inc $5,662.19 Kenton Co. 6-80203
2025 3 FD52 06 E143 D 1683601D 059 9/17/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2500051909 PON22400002789 H W Lochner Inc $131,500.00 Kenton Co. 6-80203
2025 3 FD52 06 E143 D 1683601D 059 9/17/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2500057463 PON22400002789 H W Lochner Inc $41,581.89 Kenton Co. 6-80203
2025 3 FD52 06 E143 D 1683601D 059 9/17/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2500057463 PON22400002789 H W Lochner Inc $4,718.11 Kenton Co. 6-80203
2025 3 FD52 06 E111 D 1683601D 059 9/9/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091O1062425002918 $55.23 000001089729-3562506204
2025 3 FD52 06 E121 D 1683601D 059 9/9/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091O1062425002918 $4.00 000001089729-3562506204
2025 3 FD52 06 E122 D 1683601D 059 9/9/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091O1062425002918 $26.92 000001089729-3562506204
2025 3 FD52 06 E123 D 1683601D 059 9/9/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091O1062425002918 $11.64 000001089729-3562506204
2024 12 FD52 06 E111 D 1683601D 059 6/10/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR061O1062415906230 $19.46 000001089729-3562506204
2024 12 FD52 06 E111 D 1683601D 059 6/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061O1062415906230 $3.94 000001089729-3562506204
2024 12 FD52 06 E121 D 1683601D 059 6/10/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR061O1062415906230 $1.42 000001089729-3562506204
2024 12 FD52 06 E121 D 1683601D 059 6/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061O1062415906230 $0.30 000001089729-3562506204
2024 12 FD52 06 E122 D 1683601D 059 6/10/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR061O1062415906230 $13.01 000001089729-3562506204
2024 12 FD52 06 E122 D 1683601D 059 6/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061O1062415906230 $2.60 000001089729-3562506204
2024 12 FD52 06 E123 D 1683601D 059 6/10/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR061O1062415906230 $4.27 000001089729-3562506204
2024 12 FD52 06 E123 D 1683601D 059 6/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061O1062415906230 $0.85 000001089729-3562506204
2024 12 FD52 06 E143 D 1683601D 059 6/3/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400248955 PON22400002789 H W Lochner Inc $30,399.69 Kenton Co. 6-80203
2024 12 FD52 06 E143 D 1683601D 059 6/3/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400248955 PON22400002789 H W Lochner Inc $600.31 Kenton Co. 6-80203
2024 11 FD52 06 E143 D 1683601D 059 5/29/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400245936 PON22400002789 H W Lochner Inc $6,300.00 Kenton Co. 6-80203
2024 11 FD52 06 E111 D 1683601D 059 5/23/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052O1062414305015 $42.89 000001089729-3562506204
2024 11 FD52 06 E111 D 1683601D 059 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414305015 $4.29 000001089729-3562506204
2024 11 FD52 06 E121 D 1683601D 059 5/23/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052O1062414305015 $3.12 000001089729-3562506204
2024 11 FD52 06 E121 D 1683601D 059 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414305015 $0.31 000001089729-3562506204
2024 11 FD52 06 E122 D 1683601D 059 5/23/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052O1062414305015 $28.38 000001089729-3562506204
2024 11 FD52 06 E122 D 1683601D 059 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414305015 $2.84 000001089729-3562506204
2024 11 FD52 06 E123 D 1683601D 059 5/23/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052O1062414305015 $9.32 000001089729-3562506204
2024 11 FD52 06 E123 D 1683601D 059 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414305015 $0.93 000001089729-3562506204
2024 11 FD52 06 E124 D 1683601D 059 5/23/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052O1062414305015 $0.01 000001089729-3562506204
2024 9 FD52 06 E121 D 1683601D 059 3/15/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031O1062406810100 $8.53 000001089729-3562506204
2024 9 FD52 06 E122 D 1683601D 059 3/15/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031O1062406810100 $78.05 000001089729-3562506204
2024 9 FD52 06 E123 D 1683601D 059 3/15/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031O1062406810100 $25.61 000001089729-3562506204
2024 9 FD52 06 E111 D 1683601D 059 3/11/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031O1062406810099 $117.96 000001089729-3562506204
2024 8 FD52 06 E111 D 1683601D 059 2/26/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR022O1062405408929 $42.89 000001089729-3562506204
2024 8 FD52 06 E121 D 1683601D 059 2/26/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR022O1062405408929 $3.12 000001089729-3562506204
2024 8 FD52 06 E122 D 1683601D 059 2/26/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR022O1062405408929 $28.38 000001089729-3562506204
2024 8 FD52 06 E123 D 1683601D 059 2/26/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR022O1062405408929 $9.31 000001089729-3562506204
2024 8 FD52 06 E124 D 1683601D 059 2/26/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR022O1062405408929 $0.01 000001089729-3562506204
2024 8 FD52 00 E111 D 1683601D 059 2/16/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021O1062403907697 $60.64 000001090295-3562500636
2024 8 FD52 00 E111 D 1683601D 059 2/16/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907697 $21.48 000001090295-3562500636
2024 8 FD52 00 E121 D 1683601D 059 2/16/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021O1062403907697 $4.31 000001090295-3562500636
2024 8 FD52 00 E121 D 1683601D 059 2/16/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907697 $1.53 000001090295-3562500636
2024 8 FD52 00 E122 D 1683601D 059 2/16/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021O1062403907697 $40.22 000001090295-3562500636
2024 8 FD52 00 E122 D 1683601D 059 2/16/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907697 $14.21 000001090295-3562500636
2024 8 FD52 00 E123 D 1683601D 059 2/16/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021O1062403907697 $14.11 000001090295-3562500636
2024 8 FD52 00 E123 D 1683601D 059 2/16/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907697 $4.95 000001090295-3562500636
2024 8 FD52 06 E111 D 1683601D 059 2/9/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021O1062403907693 $528.96 000001089729-3562506204
2024 8 FD52 06 E111 D 1683601D 059 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907693 $40.25 000001089729-3562506204
2024 8 FD52 06 E121 D 1683601D 059 2/9/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021O1062403907693 $37.72 000001089729-3562506204
2024 8 FD52 06 E121 D 1683601D 059 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907693 $2.80 000001089729-3562506204
2024 8 FD52 06 E122 D 1683601D 059 2/9/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021O1062403907693 $349.97 000001089729-3562506204
2024 8 FD52 06 E122 D 1683601D 059 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907693 $26.63 000001089729-3562506204
2024 8 FD52 06 E123 D 1683601D 059 2/9/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR021O1062403907693 $102.30 000001089729-3562506204
2024 8 FD52 06 E123 D 1683601D 059 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907693 $6.08 000001089729-3562506204
2024 7 FD52 00 E111 D 1683601D 059 1/31/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR012O1062402306639 $401.69 000001090637-3562500061
2024 7 FD52 00 E111 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306639 $137.42 000001090637-3562500061
2024 7 FD52 00 E121 D 1683601D 059 1/31/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR012O1062402306639 $29.17 000001090637-3562500061
2024 7 FD52 00 E121 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306639 $9.98 000001090637-3562500061
2024 7 FD52 00 E122 D 1683601D 059 1/31/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR012O1062402306639 $265.87 000001090637-3562500061
2024 7 FD52 00 E122 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306639 $90.93 000001090637-3562500061
2024 7 FD52 00 E123 D 1683601D 059 1/31/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR012O1062402306639 $93.37 000001090637-3562500061
2024 7 FD52 00 E123 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306639 $31.65 000001090637-3562500061
2024 7 FD52 00 E124 D 1683601D 059 1/31/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR012O1062402306639 $0.12 000001090637-3562500061
2024 7 FD52 00 E124 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306639 $0.04 000001090637-3562500061
2024 7 FD52 06 E111 D 1683601D 059 1/31/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306623 $895.51 000001089729-3562506204
2024 7 FD52 06 E111 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306623 $217.30 000001089729-3562506204
2024 7 FD52 06 E121 D 1683601D 059 1/31/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306623 $66.39 000001089729-3562506200
2024 7 FD52 06 E121 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306623 $16.09 000001089729-3562506204
2024 7 FD52 06 E122 D 1683601D 059 1/31/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306623 $592.55 000001089729-3562506204
2024 7 FD52 06 E122 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306623 $143.80 000001089729-3562506204
2024 7 FD52 06 E123 D 1683601D 059 1/31/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306623 $144.61 000001089729-3562506204
2024 7 FD52 06 E123 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306623 $35.11 000001089729-3562506204
2024 7 FD52 06 E124 D 1683601D 059 1/31/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306623 $0.21 000001089729-3562506204
2024 7 FD52 06 E124 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306623 $0.05 000001089729-3562506200
2024 7 FD52 00 E111 D 1683601D 059 1/31/2024 0070 ENV STUDIES-HIST/CULTURAL CA-XR012O1062402306639 $260.53 000001090639-3562500061
2024 7 FD52 00 E111 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306639 $192.03 000001090639-3562500061
2024 7 FD52 00 E121 D 1683601D 059 1/31/2024 0070 ENV STUDIES-HIST/CULTURAL CA-XR012O1062402306639 $19.46 000001090639-3562500061
2024 7 FD52 00 E121 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306639 $14.35 000001090639-3562500061
2024 7 FD52 00 E122 D 1683601D 059 1/31/2024 0070 ENV STUDIES-HIST/CULTURAL CA-XR012O1062402306639 $172.33 000001090639-3562500061
2024 7 FD52 00 E122 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306639 $127.07 000001090639-3562500061
2024 7 FD52 00 E123 D 1683601D 059 1/31/2024 0070 ENV STUDIES-HIST/CULTURAL CA-XR012O1062402306639 $40.69 000001090639-3562500061
2024 7 FD52 00 E123 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306639 $29.40 000001090639-3562500061
2024 7 FD52 00 E124 D 1683601D 059 1/31/2024 0070 ENV STUDIES-HIST/CULTURAL CA-XR012O1062402306639 $0.09 000001090639-3562500061
2024 7 FD52 00 E124 D 1683601D 059 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306639 $0.07 000001090639-3562500061
2024 7 FD52 00 E111 D 1683601D 059 1/24/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306630 $243.17 000001090295-3562500636
2024 7 FD52 00 E111 D 1683601D 059 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306630 $63.21 000001090295-3562500636
2024 7 FD52 00 E121 D 1683601D 059 1/24/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306630 $17.58 000001090295-3562500636
2024 7 FD52 00 E121 D 1683601D 059 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306630 $4.56 000001090295-3562500636
2024 7 FD52 00 E122 D 1683601D 059 1/24/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306630 $160.86 000001090295-3562500636
2024 7 FD52 00 E122 D 1683601D 059 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306630 $41.83 000001090295-3562500636
2024 7 FD52 00 E123 D 1683601D 059 1/24/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306630 $56.40 000001090295-3562500636
2024 7 FD52 00 E123 D 1683601D 059 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306630 $14.55 000001090295-3562500636
2024 7 FD52 00 E124 D 1683601D 059 1/24/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012O1062402306630 $0.07 000001090295-3562500636
2024 7 FD52 00 E124 D 1683601D 059 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306630 $0.02 000001090295-3562500636
2024 7 FD52 06 E111 D 1683601D 059 1/8/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR011O1062400505743 $436.45 000001089729-3562506204
2024 7 FD52 06 E111 D 1683601D 059 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505743 $186.85 000001089729-3562506204
2024 7 FD52 06 E121 D 1683601D 059 1/8/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR011O1062400505743 $31.55 000001089729-3562506204
2024 7 FD52 06 E121 D 1683601D 059 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505743 $13.51 000001089729-3562506204
2024 7 FD52 06 E122 D 1683601D 059 1/8/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR011O1062400505743 $288.80 000001089729-3562506204
2024 7 FD52 06 E122 D 1683601D 059 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505743 $123.64 000001089729-3562506204
2024 7 FD52 06 E123 D 1683601D 059 1/8/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR011O1062400505743 $95.06 000001089729-3562506204
2024 7 FD52 06 E123 D 1683601D 059 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505743 $40.31 000001089729-3562506204
2024 6 FD52 00 E111 D 1683601D 059 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504662 $154.61 000001090295-3562500636
2024 6 FD52 00 E111 D 1683601D 059 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504662 $45.53 000001090295-3562500636
2024 6 FD52 00 E121 D 1683601D 059 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504662 $11.19 000001090295-3562500636
2024 6 FD52 00 E121 D 1683601D 059 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504662 $3.30 000001090295-3562500636
2024 6 FD52 00 E122 D 1683601D 059 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504662 $102.37 000001090295-3562500636
2024 6 FD52 00 E122 D 1683601D 059 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504662 $30.12 000001090295-3562500636
2024 6 FD52 00 E123 D 1683601D 059 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504662 $29.88 000001090295-3562500636
2024 6 FD52 00 E123 D 1683601D 059 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504662 $8.71 000001090295-3562500636
2024 6 FD52 00 E124 D 1683601D 059 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504662 $0.04 000001090295-3562500636
2024 5 FD52 06 E111 D 1683601D 059 11/30/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112N1062332502558 $32.17 000001089729-3562506204
2024 5 FD52 06 E111 D 1683601D 059 11/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502558 $18.44 000001089729-3562506204
2024 5 FD52 06 E121 D 1683601D 059 11/30/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112N1062332502558 $2.34 000001089729-3562506204
2024 5 FD52 06 E121 D 1683601D 059 11/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502558 $1.35 000001089729-3562506204
2024 5 FD52 06 E122 D 1683601D 059 11/30/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112N1062332502558 $21.28 000001089729-3562506204
2024 5 FD52 06 E122 D 1683601D 059 11/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502558 $12.20 000001089729-3562506204
2024 5 FD52 06 E123 D 1683601D 059 11/30/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112N1062332502558 $5.84 000001089729-3562506204
2024 5 FD52 06 E123 D 1683601D 059 11/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502558 $3.31 000001089729-3562506204
2024 5 FD52 06 E124 D 1683601D 059 11/30/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112N1062332502558 $0.02 000001089729-3562506204