The Commonwealth pays employees on a semi-monthly basis with a scheduled pay day on the 15th and 30th of each month. The two monthly pay periods are from the 1st to the 15th of the month and the 16th through the last day of the month. Pay check distribution is delayed by one pay period to allow for system processing. For example work performed during the 1st to the 15th day of the month is paid to the employee on the 30th of the month. Accordingly the cost accounting charges for labor costs posting in eMARS to operating accounts and highway projects are also delayed by approximately one pay period.
A good rule of measure is that the cost accounting charges for the pay period ending on the 15th of the month will post to eMARS by the 25th and those for the pay period ending on the last day of the month will post to eMARS by the 10th of the following month.

x close panel
Detailed Project Expenditure Report
Total E-MARS Expenditures for 1377701D = $9,191,783.14
Click here for Labor Costs Information
Year Month PBU Charge District Object Phase Program Code County Date ACT Activity Name Trans ID Reference # Vendor Name Expenditure Line Description
2025 6 FD52 00 E111 D 1377701D 056 12/2/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR112O1062432608770 $2,761.67 000001081429-3562500610
2025 6 FD52 00 E111 D 1377701D 056 12/2/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608770 $647.08 000001081429-3562500610
2025 6 FD52 00 E121 D 1377701D 056 12/2/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR112O1062432608770 $202.42 000001081429-3562500610
2025 6 FD52 00 E121 D 1377701D 056 12/2/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608770 $47.42 000001081429-3562500610
2025 6 FD52 00 E122 D 1377701D 056 12/2/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR112O1062432608770 $1,346.26 000001081429-3562500610
2025 6 FD52 00 E122 D 1377701D 056 12/2/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608770 $315.45 000001081429-3562500610
2025 6 FD52 00 E123 D 1377701D 056 12/2/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR112O1062432608770 $382.26 000001081429-3562500610
2025 6 FD52 00 E123 D 1377701D 056 12/2/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608770 $89.25 000001081429-3562500610
2025 6 FD52 00 E124 D 1377701D 056 12/2/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR112O1062432608770 $0.62 000001081429-3562500610
2025 6 FD52 00 E124 D 1377701D 056 12/2/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608770 $0.15 000001081429-3562500610
2025 5 FD52 00 E111 D 1377701D 056 11/25/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR112O1062432608791 $2,021.95 000001089166-3562500610
2025 5 FD52 00 E111 D 1377701D 056 11/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608791 $524.61 000001089166-3562500610
2025 5 FD52 00 E121 D 1377701D 056 11/25/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR112O1062432608791 $146.49 000001089166-3562500610
2025 5 FD52 00 E121 D 1377701D 056 11/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608791 $38.00 000001089166-3562500610
2025 5 FD52 00 E122 D 1377701D 056 11/25/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR112O1062432608791 $985.77 000001089166-3562500610
2025 5 FD52 00 E122 D 1377701D 056 11/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608791 $255.75 000001089166-3562500610
2025 5 FD52 00 E123 D 1377701D 056 11/25/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR112O1062432608791 $364.03 000001089166-3562500610
2025 5 FD52 00 E123 D 1377701D 056 11/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608791 $93.73 000001089166-3562500610
2025 5 FD52 00 E124 D 1377701D 056 11/25/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR112O1062432608791 $0.43 000001089166-3562500610
2025 5 FD52 00 E124 D 1377701D 056 11/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608791 $0.11 000001089166-3562500610
2025 5 FD52 00 E111 D 1377701D 056 11/25/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112O1062432608818 $418.91 000001093320-3562500636
2025 5 FD52 00 E111 D 1377701D 056 11/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608818 $227.06 000001093320-3562500636
2025 5 FD52 00 E121 D 1377701D 056 11/25/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112O1062432608818 $30.37 000001093320-3562500636
2025 5 FD52 00 E121 D 1377701D 056 11/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608818 $16.46 000001093320-3562500636
2025 5 FD52 00 E122 D 1377701D 056 11/25/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112O1062432608818 $204.15 000001093320-3562500636
2025 5 FD52 00 E122 D 1377701D 056 11/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608818 $110.70 000001093320-3562500636
2025 5 FD52 00 E123 D 1377701D 056 11/25/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112O1062432608818 $92.45 000001093320-3562500636
2025 5 FD52 00 E123 D 1377701D 056 11/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608818 $49.66 000001093320-3562500636
2025 5 FD52 00 E124 D 1377701D 056 11/25/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112O1062432608818 $0.11 000001093320-3562500636
2025 5 FD52 00 E124 D 1377701D 056 11/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112O1062432608818 $0.06 000001093320-3562500636
2025 5 FD52 10 E797 D 1377701D 056 11/20/2024 3550 RAILROAD CONTRACTS PRC-2500107540 DO2400018030 CSX TRANSPORTATION INC $1,182.00
2025 5 FD52 00 E111 D 1377701D 056 11/18/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR111O1062431307579 $770.06 000001089166-3562500610
2025 5 FD52 00 E111 D 1377701D 056 11/18/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307579 $88.24 000001089166-3562500610
2025 5 FD52 00 E121 D 1377701D 056 11/18/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR111O1062431307579 $54.30 000001089166-3562500610
2025 5 FD52 00 E121 D 1377701D 056 11/18/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307579 $6.22 000001089166-3562500610
2025 5 FD52 00 E122 D 1377701D 056 11/18/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR111O1062431307579 $375.45 000001089166-3562500610
2025 5 FD52 00 E122 D 1377701D 056 11/18/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307579 $43.02 000001089166-3562500610
2025 5 FD52 00 E123 D 1377701D 056 11/18/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR111O1062431307579 $138.53 000001089166-3562500610
2025 5 FD52 00 E123 D 1377701D 056 11/18/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307579 $15.77 000001089166-3562500610
2025 5 FD52 05 E797 D 1377701D 056 11/15/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092239002P007K CTXCONST0922390020002K Kiewit Infrastructure South Co. $404,949.64
2025 5 FD52 00 E111 D 1377701D 056 11/12/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR111O1062431307556 $135.20 000001079749-3562500636
2025 5 FD52 00 E111 D 1377701D 056 11/12/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR111O1062431307588 $296.40 000001091103-3562500480
2025 5 FD52 00 E111 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307556 $2.26 000001079749-3562500636
2025 5 FD52 00 E111 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307588 $59.28 000001091103-3562500480
2025 5 FD52 00 E121 D 1377701D 056 11/12/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR111O1062431307556 $10.14 000001079749-3562500636
2025 5 FD52 00 E121 D 1377701D 056 11/12/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR111O1062431307588 $22.26 000001091103-3562500480
2025 5 FD52 00 E121 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307556 $0.17 000001079749-3562500636
2025 5 FD52 00 E121 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307588 $4.45 000001091103-3562500480
2025 5 FD52 00 E122 D 1377701D 056 11/12/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR111O1062431307556 $65.91 000001079749-3562500636
2025 5 FD52 00 E122 D 1377701D 056 11/12/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR111O1062431307588 $144.49 000001091103-3562500480
2025 5 FD52 00 E122 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307556 $1.10 000001079749-3562500636
2025 5 FD52 00 E122 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307588 $28.90 000001091103-3562500480
2025 5 FD52 00 E123 D 1377701D 056 11/12/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR111O1062431307556 $14.79 000001079749-3562500636
2025 5 FD52 00 E123 D 1377701D 056 11/12/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR111O1062431307588 $41.42 000001091103-3562500480
2025 5 FD52 00 E123 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307556 $0.24 000001079749-3562500636
2025 5 FD52 00 E123 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307588 $8.18 000001091103-3562500480
2025 5 FD52 00 E111 D 1377701D 056 11/12/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111O1062431307604 $895.71 000001093320-3562500636
2025 5 FD52 00 E111 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307604 $93.41 000001093320-3562500636
2025 5 FD52 00 E121 D 1377701D 056 11/12/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111O1062431307604 $63.74 000001093320-3562500636
2025 5 FD52 00 E121 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307604 $6.64 000001093320-3562500636
2025 5 FD52 00 E122 D 1377701D 056 11/12/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111O1062431307604 $436.66 000001093320-3562500636
2025 5 FD52 00 E122 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307604 $45.54 000001093320-3562500636
2025 5 FD52 00 E123 D 1377701D 056 11/12/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111O1062431307604 $197.21 000001093320-3562500636
2025 5 FD52 00 E123 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307604 $20.43 000001093320-3562500636
2025 5 FD52 00 E111 D 1377701D 056 11/12/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111O1062431307559 $3,055.64 000001081429-3562500610
2025 5 FD52 00 E111 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307559 $71.80 000001081429-3562500610
2025 5 FD52 00 E121 D 1377701D 056 11/12/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111O1062431307559 $219.83 000001081429-3562500610
2025 5 FD52 00 E121 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307559 $5.16 000001081429-3562500610
2025 5 FD52 00 E122 D 1377701D 056 11/12/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111O1062431307559 $1,489.43 000001081429-3562500610
2025 5 FD52 00 E122 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307559 $35.00 000001081429-3562500610
2025 5 FD52 00 E123 D 1377701D 056 11/12/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111O1062431307559 $421.38 000001081429-3562500610
2025 5 FD52 00 E123 D 1377701D 056 11/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111O1062431307559 $10.86 000001081429-3562500610
2025 4 FD52 00 E143 D 1377701D 056 10/30/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2500090461 PON22200004678 STANTEC CONSULTING SERVICES INC $59,041.40 Jefferson Co. 5-20061
2025 4 FD52 05 E143 D 1377701D 056 10/30/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2500088718 PON22200002246 AECOM TECHNICAL SERVICES, INC. $808,847.51 Jefferson Co. 5-20061
2025 4 FD52 10 E797 D 1377701D 056 10/29/2024 3550 RAILROAD CONTRACTS PRC-2500091898 DO2400018030 CSX TRANSPORTATION INC $1,373.25
2025 4 FD52 00 E111 D 1377701D 056 10/24/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR102O1062429706348 $854.40 000001089166-3562500610
2025 4 FD52 00 E111 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706348 $49.55 000001089166-3562500610
2025 4 FD52 00 E121 D 1377701D 056 10/24/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR102O1062429706348 $61.89 000001089166-3562500610
2025 4 FD52 00 E121 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706348 $3.59 000001089166-3562500610
2025 4 FD52 00 E122 D 1377701D 056 10/24/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR102O1062429706348 $416.53 000001089166-3562500610
2025 4 FD52 00 E122 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706348 $24.15 000001089166-3562500610
2025 4 FD52 00 E111 D 1377701D 056 10/24/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR102O1062429706327 $3,660.65 000001081429-3562500610
2025 4 FD52 00 E123 D 1377701D 056 10/24/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR102O1062429706348 $153.61 000001089166-3562500610
2025 4 FD52 00 E111 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706327 $405.36 000001081429-3562500610
2025 4 FD52 00 E123 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706348 $8.85 000001089166-3562500610
2025 4 FD52 00 E121 D 1377701D 056 10/24/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR102O1062429706327 $268.23 000001081429-3562500610
2025 4 FD52 00 E124 D 1377701D 056 10/24/2024 1640 BRIDGE-REVIEW OF PLANS CA-XR102O1062429706348 $0.17 000001089166-3562500610
2025 4 FD52 00 E121 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706327 $29.63 000001081429-3562500610
2025 4 FD52 00 E124 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706348 $0.01 000001089166-3562500610
2025 4 FD52 00 E122 D 1377701D 056 10/24/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR102O1062429706327 $1,784.47 000001081429-3562500610
2025 4 FD52 00 E122 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706327 $197.62 000001081429-3562500610
2025 4 FD52 00 E123 D 1377701D 056 10/24/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR102O1062429706327 $526.63 000001081429-3562500610
2025 4 FD52 00 E123 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706327 $60.05 000001081429-3562500610
2025 4 FD52 00 E124 D 1377701D 056 10/24/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR102O1062429706327 $0.78 000001081429-3562500610
2025 4 FD52 00 E124 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706327 $0.08 000001081429-3562500610
2025 4 FD52 00 E111 D 1377701D 056 10/24/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102O1062429706376 $395.51 000001093320-3562500636
2025 4 FD52 00 E111 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706376 $284.30 000001093320-3562500636
2025 4 FD52 00 E121 D 1377701D 056 10/24/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102O1062429706376 $28.69 000001093320-3562500636
2025 4 FD52 00 E121 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706376 $20.62 000001093320-3562500636
2025 4 FD52 00 E122 D 1377701D 056 10/24/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102O1062429706376 $192.81 000001093320-3562500636
2025 4 FD52 00 E122 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706376 $138.59 000001093320-3562500636
2025 4 FD52 00 E123 D 1377701D 056 10/24/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102O1062429706376 $87.40 000001093320-3562500636
2025 4 FD52 00 E123 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706376 $62.18 000001093320-3562500636
2025 4 FD52 00 E124 D 1377701D 056 10/24/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102O1062429706376 $0.10 000001093320-3562500636
2025 4 FD52 00 E124 D 1377701D 056 10/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102O1062429706376 $0.07 000001093320-3562500636
2025 4 FD52 00 E111 D 1377701D 056 10/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101O1062428205206 $3,255.23 000001081429-3562500610
2025 4 FD52 00 E123 D 1377701D 056 10/9/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR101O1062428205232 $45.66 000001091103-3562500480
2025 4 FD52 00 E111 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205206 $96.72 000001081429-3562500610
2025 4 FD52 00 E123 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205232 $25.46 000001091103-3562500480
2025 4 FD52 00 E121 D 1377701D 056 10/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101O1062428205206 $233.28 000001081429-3562500610
2025 4 FD52 00 E121 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205206 $6.91 000001081429-3562500610
2025 4 FD52 00 E122 D 1377701D 056 10/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101O1062428205206 $1,587.14 000001081429-3562500610
2025 4 FD52 00 E122 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205206 $47.15 000001081429-3562500610
2025 4 FD52 00 E123 D 1377701D 056 10/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101O1062428205206 $485.36 000001081429-3562500610
2025 4 FD52 00 E123 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205206 $15.65 000001081429-3562500610
2025 4 FD52 00 E111 D 1377701D 056 10/9/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR101O1062428205232 $323.59 000001091103-3562500480
2025 4 FD52 00 E111 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205232 $184.52 000001091103-3562500480
2025 4 FD52 00 E121 D 1377701D 056 10/9/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR101O1062428205232 $24.28 000001091103-3562500480
2025 4 FD52 00 E111 D 1377701D 056 10/9/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101O1062428205248 $162.81 000001093320-3562500636
2025 4 FD52 00 E111 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205248 $79.56 000001093320-3562500636
2025 4 FD52 00 E121 D 1377701D 056 10/9/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101O1062428205248 $11.59 000001093320-3562500636
2025 4 FD52 00 E121 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205248 $5.67 000001093320-3562500636
2025 4 FD52 00 E121 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205232 $13.86 000001091103-3562500480
2025 4 FD52 00 E122 D 1377701D 056 10/9/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101O1062428205248 $79.39 000001093320-3562500636
2025 4 FD52 00 E122 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205248 $38.79 000001093320-3562500636
2025 4 FD52 00 E123 D 1377701D 056 10/9/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101O1062428205248 $35.94 000001093320-3562500636
2025 4 FD52 00 E123 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205248 $17.40 000001093320-3562500636
2025 4 FD52 00 E122 D 1377701D 056 10/9/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR101O1062428205232 $158.43 000001091103-3562500480
2025 4 FD52 00 E122 D 1377701D 056 10/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101O1062428205232 $89.96 000001091103-3562500480
2025 3 FD52 00 E143 D 1377701D 056 9/30/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2500068704 PON22200004696 STANTEC CONSULTING SERVICES INC $149,602.12 Letter Agreement 3 & 3X Jefferson Co.
2025 3 FD52 00 E111 D 1377701D 056 9/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092O1062426804074 $3,675.73 000001081429-3562500610
2025 3 FD52 00 E111 D 1377701D 056 9/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092O1062426804074 $584.39 000001081429-3562500610
2025 3 FD52 00 E121 D 1377701D 056 9/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092O1062426804074 $270.93 000001081429-3562500610
2025 3 FD52 00 E121 D 1377701D 056 9/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092O1062426804074 $42.86 000001081429-3562500610
2025 3 FD52 00 E122 D 1377701D 056 9/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092O1062426804074 $1,791.81 000001081429-3562500610
2025 3 FD52 00 E122 D 1377701D 056 9/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092O1062426804074 $284.89 000001081429-3562500610
2025 3 FD52 00 E123 D 1377701D 056 9/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092O1062426804074 $501.09 000001081429-3562500610
2025 3 FD52 00 E123 D 1377701D 056 9/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092O1062426804074 $87.11 000001081429-3562500610
2025 3 FD52 00 E124 D 1377701D 056 9/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092O1062426804074 $0.89 000001081429-3562500610
2025 3 FD52 00 E124 D 1377701D 056 9/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092O1062426804074 $0.13 000001081429-3562500610
2025 3 FD52 00 E111 D 1377701D 056 9/25/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092O1062426804124 $102.30 000001093320-3562500636
2025 3 FD52 00 E111 D 1377701D 056 9/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092O1062426804124 $62.96 000001093320-3562500636
2025 3 FD52 00 E121 D 1377701D 056 9/25/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092O1062426804124 $7.43 000001093320-3562500636
2025 3 FD52 00 E121 D 1377701D 056 9/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092O1062426804124 $4.57 000001093320-3562500636
2025 3 FD52 00 E122 D 1377701D 056 9/25/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092O1062426804124 $49.90 000001093320-3562500636
2025 3 FD52 00 E122 D 1377701D 056 9/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092O1062426804124 $30.70 000001093320-3562500636
2025 3 FD52 00 E123 D 1377701D 056 9/25/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092O1062426804124 $22.61 000001093320-3562500636
2025 3 FD52 00 E123 D 1377701D 056 9/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092O1062426804124 $13.77 000001093320-3562500636
2025 3 FD52 00 E124 D 1377701D 056 9/25/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092O1062426804124 $0.03 000001093320-3562500636
2025 3 FD52 00 E124 D 1377701D 056 9/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092O1062426804124 $0.01 000001093320-3562500636
2025 3 FD52 00 E111 D 1377701D 056 9/17/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR091O1062425002930 $614.84 000001092045-3562500061
2025 3 FD52 00 E111 D 1377701D 056 9/17/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002930 $61.48 000001092045-3562500061
2025 3 FD52 00 E121 D 1377701D 056 9/17/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR091O1062425002930 $43.62 000001092045-3562500061
2025 3 FD52 00 E121 D 1377701D 056 9/17/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002930 $4.37 000001092045-3562500061
2025 3 FD52 00 E122 D 1377701D 056 9/17/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR091O1062425002930 $299.73 000001092045-3562500061
2025 3 FD52 00 E122 D 1377701D 056 9/17/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002930 $29.97 000001092045-3562500061
2025 3 FD52 00 E123 D 1377701D 056 9/17/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR091O1062425002930 $153.67 000001092045-3562500061
2025 3 FD52 00 E123 D 1377701D 056 9/17/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002930 $15.26 000001092045-3562500061
2025 3 FD52 00 E111 D 1377701D 056 9/13/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091O1062425002897 $3,616.21 000001081429-3562500610
2025 3 FD52 00 E111 D 1377701D 056 9/13/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002897 $159.20 000001081429-3562500610
2025 3 FD52 00 E121 D 1377701D 056 9/13/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091O1062425002897 $257.78 000001081429-3562500610
2025 3 FD52 00 E121 D 1377701D 056 9/13/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002897 $11.23 000001081429-3562500610
2025 3 FD52 00 E122 D 1377701D 056 9/13/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091O1062425002897 $1,762.95 000001081429-3562500610
2025 3 FD52 00 E122 D 1377701D 056 9/13/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002897 $77.61 000001081429-3562500610
2025 3 FD52 00 E123 D 1377701D 056 9/13/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091O1062425002897 $565.09 000001081429-3562500610
2025 3 FD52 00 E123 D 1377701D 056 9/13/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002897 $26.91 000001081429-3562500610
2025 3 FD52 00 E229 D 1377701D 056 9/11/2024 5021 GEOTECH INVEST STRUCTURE (DESI IET-XE13A162524254014340 $55.08
2025 3 FD52 00 E122 D 1377701D 056 9/9/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091O1062425002944 $158.78 000001093320-3562500636
2025 3 FD52 00 E122 D 1377701D 056 9/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002944 $7.49 000001093320-3562500636
2025 3 FD52 00 E123 D 1377701D 056 9/9/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091O1062425002944 $71.69 000001093320-3562500636
2025 3 FD52 00 E123 D 1377701D 056 9/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002944 $3.36 000001093320-3562500636
2025 3 FD52 00 E111 D 1377701D 056 9/9/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091O1062425002944 $325.66 000001093320-3562500636
2025 3 FD52 00 E111 D 1377701D 056 9/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002944 $15.36 000001093320-3562500636
2025 3 FD52 00 E121 D 1377701D 056 9/9/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091O1062425002944 $23.17 000001093320-3562500636
2025 3 FD52 00 E121 D 1377701D 056 9/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091O1062425002944 $1.10 000001093320-3562500636
2025 3 FD52 00 E111 D 1377701D 056 9/4/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082O1062423601652 $255.79 000001093320-3562500636
2025 3 FD52 00 E111 D 1377701D 056 9/4/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082O1062423601652 $35.36 000001093320-3562500636
2025 3 FD52 00 E121 D 1377701D 056 9/4/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082O1062423601652 $18.56 000001093320-3562500636
2025 3 FD52 00 E121 D 1377701D 056 9/4/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082O1062423601652 $2.56 000001093320-3562500636
2025 3 FD52 00 E122 D 1377701D 056 9/4/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082O1062423601652 $124.76 000001093320-3562500636
2025 3 FD52 00 E122 D 1377701D 056 9/4/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082O1062423601652 $17.24 000001093320-3562500636
2025 3 FD52 00 E123 D 1377701D 056 9/4/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082O1062423601652 $56.36 000001093320-3562500636
2025 3 FD52 00 E123 D 1377701D 056 9/4/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082O1062423601652 $7.73 000001093320-3562500636
2025 3 FD52 00 E124 D 1377701D 056 9/4/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082O1062423601652 $0.07 000001093320-3562500636
2025 3 FD52 00 E124 D 1377701D 056 9/4/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082O1062423601652 $0.01 000001093320-3562500636
2025 2 FD52 05 E143 D 1377701D 056 8/30/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2500043818 PON22200004678 STANTEC CONSULTING SERVICES INC $127,815.88 Jefferson Co. 5-20061
2025 2 FD52 00 E229 D 1377701D 056 8/27/2024 5021 GEOTECH INVEST STRUCTURE (DESI IET-XE13A162524238013400 $62.10
2025 2 FD52 00 E111 D 1377701D 056 8/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR082O1062423601589 $4,140.08 000001081429-3562500610
2025 2 FD52 00 E111 D 1377701D 056 8/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082O1062423601589 $17.74 000001081429-3562500610
2025 2 FD52 00 E121 D 1377701D 056 8/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR082O1062423601589 $302.24 000001081429-3562500610
2025 2 FD52 00 E121 D 1377701D 056 8/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082O1062423601589 $1.34 000001081429-3562500610
2025 2 FD52 00 E122 D 1377701D 056 8/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR082O1062423601589 $2,018.29 000001081429-3562500610
2025 2 FD52 00 E122 D 1377701D 056 8/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082O1062423601589 $8.65 000001081429-3562500610
2025 2 FD52 00 E123 D 1377701D 056 8/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR082O1062423601589 $691.68 000001081429-3562500610
2025 2 FD52 00 E123 D 1377701D 056 8/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082O1062423601589 $3.13 000001081429-3562500610
2025 2 FD52 00 E124 D 1377701D 056 8/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR082O1062423601589 $1.00 000001081429-3562500610
2025 2 FD52 00 E124 D 1377701D 056 8/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082O1062423601589 $0.01 000001081429-3562500610
2025 2 FD52 05 E143 D 1377701D 056 8/15/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2500032534 PON22200002246 AECOM TECHNICAL SERVICES, INC. $1,488,864.04 Jefferson Co. 5-20061
2025 2 FD52 05 E143 D 1377701D 056 8/15/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2500032534 PON22200002246 AECOM TECHNICAL SERVICES, INC. $15,000.00 Jefferson Co. 5-20061
2025 2 FD52 00 E229 D 1377701D 056 8/13/2024 5021 GEOTECH INVEST STRUCTURE (DESI IET-XE13A162524223012920 $30.78
2025 2 FD52 00 E111 D 1377701D 056 8/12/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081O1062422200371 $5,253.98 000001081429-3562500610
2025 2 FD52 00 E111 D 1377701D 056 8/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081O1062422200371 $180.21 000001081429-3562500610
2025 2 FD52 00 E121 D 1377701D 056 8/12/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081O1062422200371 $374.80 000001081429-3562500610
2025 2 FD52 00 E121 D 1377701D 056 8/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081O1062422200371 $13.07 000001081429-3562500610
2025 2 FD52 00 E122 D 1377701D 056 8/12/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081O1062422200371 $2,561.29 000001081429-3562500610
2025 2 FD52 00 E122 D 1377701D 056 8/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081O1062422200371 $87.86 000001081429-3562500610
2025 2 FD52 00 E123 D 1377701D 056 8/12/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081O1062422200371 $818.29 000001081429-3562500610
2025 2 FD52 00 E123 D 1377701D 056 8/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081O1062422200371 $26.30 000001081429-3562500610
2025 2 FD52 00 E111 D 1377701D 056 8/12/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081O1062422200437 $127.91 000001093320-3562500636
2025 2 FD52 00 E111 D 1377701D 056 8/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081O1062422200437 $18.34 000001093320-3562500636
2025 2 FD52 00 E121 D 1377701D 056 8/12/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081O1062422200437 $9.11 000001093320-3562500636
2025 2 FD52 00 E121 D 1377701D 056 8/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081O1062422200437 $1.30 000001093320-3562500636
2025 2 FD52 00 E122 D 1377701D 056 8/12/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081O1062422200437 $62.38 000001093320-3562500636
2025 2 FD52 00 E122 D 1377701D 056 8/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081O1062422200437 $8.94 000001093320-3562500636
2025 2 FD52 00 E123 D 1377701D 056 8/12/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081O1062422200437 $28.18 000001093320-3562500636
2025 2 FD52 00 E123 D 1377701D 056 8/12/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081O1062422200437 $4.02 000001093320-3562500636
2025 2 FD52 05 E797 D 1377701D 056 8/9/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092239002P006K CTXCONST0922390020002K Kiewit Infrastructure South Co. $665,860.78
2025 1 FD52 00 E111 D 1377701D 056 7/31/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072O1062420509738 $3,447.71 000001081429-3562500610
2025 1 FD52 00 E124 D 1377701D 056 7/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072O1062420509738 $0.19 000001081429-3562500610
2025 1 FD52 00 E111 D 1377701D 056 7/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072O1062420509738 $808.37 000001081429-3562500610
2025 1 FD52 00 E121 D 1377701D 056 7/31/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072O1062420509738 $253.18 000001081429-3562500610
2025 1 FD52 00 E121 D 1377701D 056 7/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072O1062420509738 $60.26 000001081429-3562500610
2025 1 FD52 00 E122 D 1377701D 056 7/31/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072O1062420509738 $1,680.77 000001081429-3562500610
2025 1 FD52 00 E122 D 1377701D 056 7/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072O1062420509738 $394.07 000001081429-3562500610
2025 1 FD52 00 E123 D 1377701D 056 7/31/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072O1062420509738 $465.82 000001081429-3562500610
2025 1 FD52 00 E123 D 1377701D 056 7/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072O1062420509738 $73.78 000001081429-3562500610
2025 1 FD52 00 E124 D 1377701D 056 7/31/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072O1062420509738 $0.80 000001081429-3562500610
2025 1 FD52 10 E797 D 1377701D 056 7/29/2024 3550 RAILROAD CONTRACTS PRC-2500020418 DO2400018030 CSX TRANSPORTATION INC $3,384.65
2025 1 FD52 00 E229 D 1377701D 056 7/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI IET-XE13A162524207010080 $35.64
2025 1 FD52 05 E143 D 1377701D 056 7/22/2024 0310 PROJECT DEVELOPMENT PRC-2500014863 PON22200002099 WSP USA INC $342,501.85 Letter Agreement 1X, 1XX & 1XXX
2025 1 FD52 00 E111 D 1377701D 056 7/11/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071O1062419208627 $2,537.86 000001081429-3562500610
2025 1 FD52 00 E111 D 1377701D 056 7/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071O1062419208627 $1,551.15 000001081429-3562500610
2025 1 FD52 00 E121 D 1377701D 056 7/11/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071O1062419208627 $180.29 000001081429-3562500610
2025 1 FD52 00 E121 D 1377701D 056 7/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071O1062419208627 $108.18 000001081429-3562500610
2025 1 FD52 00 E122 D 1377701D 056 7/11/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071O1062419208627 $1,679.42 000001081429-3562500610
2025 1 FD52 00 E122 D 1377701D 056 7/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071O1062419208627 $1,026.41 000001081429-3562500610
2025 1 FD52 00 E123 D 1377701D 056 7/11/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071O1062419208627 $400.03 000001081429-3562500610
2025 1 FD52 00 E123 D 1377701D 056 7/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071O1062419208627 $300.14 000001081429-3562500610
2025 1 FD52 10 E797 D 1377701D 056 7/10/2024 3550 RAILROAD CONTRACTS PRC-2500006697 DO2400018030 CSX TRANSPORTATION INC $2,135.25 2P/5-20061 DO 24*18030
2024 12 FD52 00 E111 D 1377701D 056 6/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR062O1062417607379 $991.02 000001081429-3562500610
2024 12 FD52 00 E111 D 1377701D 056 6/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062O1062417607379 $13.21 000001081429-3562500610
2024 12 FD52 00 E121 D 1377701D 056 6/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR062O1062417607379 $73.80 000001081429-3562500610
2024 12 FD52 00 E121 D 1377701D 056 6/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062O1062417607379 $0.99 000001081429-3562500610
2024 12 FD52 00 E122 D 1377701D 056 6/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR062O1062417607379 $655.67 000001081429-3562500610
2024 12 FD52 00 E122 D 1377701D 056 6/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062O1062417607379 $8.74 000001081429-3562500610
2024 12 FD52 00 E123 D 1377701D 056 6/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR062O1062417607379 $88.76 000001081429-3562500610
2024 12 FD52 00 E123 D 1377701D 056 6/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062O1062417607379 $1.17 000001081429-3562500610
2024 12 FD52 00 E124 D 1377701D 056 6/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR062O1062417607379 $0.20 000001081429-3562500610
2024 12 FD52 10 E797 D 1377701D 056 6/21/2024 3550 RAILROAD CONTRACTS PRC-2400263599 DO2400018030 CSX TRANSPORTATION INC $2,155.00
2024 12 FD52 05 E797 D 1377701D 056 6/20/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092239002P005K CTXCONST0922390020002K Kiewit Infrastructure South Co. $619,341.87
2024 12 FD52 05 E143 D 1377701D 056 6/13/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400257405 PON22300001539 Stanton Constructability Services, LLC $110,365.90 Letter Agreement 2
2024 12 FD52 00 E111 D 1377701D 056 6/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR061O1062415906200 $1,614.76 000001081429-3562500610
2024 12 FD52 00 E111 D 1377701D 056 6/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061O1062415906200 $331.89 000001081429-3562500610
2024 12 FD52 00 E121 D 1377701D 056 6/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR061O1062415906200 $114.07 000001081429-3562500610
2024 12 FD52 00 E121 D 1377701D 056 6/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061O1062415906200 $23.47 000001081429-3562500610
2024 12 FD52 00 E122 D 1377701D 056 6/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR061O1062415906200 $1,068.64 000001081429-3562500610
2024 12 FD52 00 E122 D 1377701D 056 6/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061O1062415906200 $219.61 000001081429-3562500610
2024 12 FD52 00 E123 D 1377701D 056 6/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR061O1062415906200 $270.49 000001081429-3562500610
2024 12 FD52 00 E123 D 1377701D 056 6/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061O1062415906200 $54.92 000001081429-3562500610
2024 11 FD52 00 E111 D 1377701D 056 5/23/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR052O1062414304982 $4,036.96 000001081429-3562500610
2024 11 FD52 00 E111 D 1377701D 056 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414304982 $10.81 000001081429-3562500610
2024 11 FD52 00 E121 D 1377701D 056 5/23/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR052O1062414304982 $291.79 000001081429-3562500610
2024 11 FD52 00 E121 D 1377701D 056 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414304982 $0.81 000001081429-3562500610
2024 11 FD52 00 E122 D 1377701D 056 5/23/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR052O1062414304982 $2,671.18 000001081429-3562500610
2024 11 FD52 00 E122 D 1377701D 056 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414304982 $7.15 000001081429-3562500610
2024 11 FD52 00 E123 D 1377701D 056 5/23/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR052O1062414304982 $751.31 000001081429-3562500610
2024 11 FD52 00 E123 D 1377701D 056 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414304982 $0.96 000001081429-3562500610
2024 11 FD52 00 E124 D 1377701D 056 5/23/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR052O1062414304982 $0.97 000001081429-3562500610
2024 11 FD52 00 E111 D 1377701D 056 5/23/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052O1062414304978 $167.01 000001079749-3562500636
2024 11 FD52 00 E111 D 1377701D 056 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414304978 $43.44 000001079749-3562500636
2024 11 FD52 00 E121 D 1377701D 056 5/23/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052O1062414304978 $12.70 000001079749-3562500636
2024 11 FD52 00 E121 D 1377701D 056 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414304978 $3.30 000001079749-3562500636
2024 11 FD52 00 E122 D 1377701D 056 5/23/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052O1062414304978 $110.54 000001079749-3562500636
2024 11 FD52 00 E122 D 1377701D 056 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414304978 $28.75 000001079749-3562500636
2024 11 FD52 00 E123 D 1377701D 056 5/23/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052O1062414304978 $18.88 000001079749-3562500636
2024 11 FD52 00 E123 D 1377701D 056 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414304978 $4.84 000001079749-3562500636
2024 11 FD52 00 E124 D 1377701D 056 5/23/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052O1062414304978 $0.04 000001079749-3562500636
2024 11 FD52 00 E124 D 1377701D 056 5/23/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052O1062414304978 $0.01 000001079749-3562500636
2024 11 FD52 00 E111 D 1377701D 056 5/23/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR052O1062414305027 $313.93 000001091103-3562500480
2024 11 FD52 00 E121 D 1377701D 056 5/23/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR052O1062414305027 $23.57 000001091103-3562500480
2024 11 FD52 00 E122 D 1377701D 056 5/23/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR052O1062414305027 $207.72 000001091103-3562500480
2024 11 FD52 00 E123 D 1377701D 056 5/23/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR052O1062414305027 $45.09 000001091103-3562500480
2024 11 FD52 00 E124 D 1377701D 056 5/23/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR052O1062414305027 $0.09 000001091103-3562500480
2024 10 FD52 00 E111 D 1377701D 056 4/30/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042O1062411502734 $2,978.28 000001081429-3562500610
2024 10 FD52 00 E111 D 1377701D 056 4/30/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502734 $424.21 000001081429-3562500610
2024 10 FD52 00 E121 D 1377701D 056 4/30/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042O1062411502734 $215.22 000001081429-3562500610
2024 10 FD52 00 E121 D 1377701D 056 4/30/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502734 $30.36 000001081429-3562500610
2024 10 FD52 00 E122 D 1377701D 056 4/30/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042O1062411502734 $1,970.72 000001081429-3562500610
2024 10 FD52 00 E122 D 1377701D 056 4/30/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502734 $280.70 000001081429-3562500610
2024 10 FD52 00 E123 D 1377701D 056 4/30/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042O1062411502734 $543.35 000001081429-3562500610
2024 10 FD52 00 E123 D 1377701D 056 4/30/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502734 $88.00 000001081429-3562500610
2024 10 FD52 00 E124 D 1377701D 056 4/30/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042O1062411502734 $0.74 000001081429-3562500610
2024 10 FD52 00 E124 D 1377701D 056 4/30/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502734 $0.11 000001081429-3562500610
2024 10 FD52 00 E122 D 1377701D 056 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502731 $21.35 000001079749-3562500636
2024 10 FD52 00 E123 D 1377701D 056 4/26/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042O1062411502731 $46.11 000001079749-3562500636
2024 10 FD52 00 E123 D 1377701D 056 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502731 $7.43 000001079749-3562500636
2024 10 FD52 00 E124 D 1377701D 056 4/26/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042O1062411502731 $0.05 000001079749-3562500636
2024 10 FD52 00 E124 D 1377701D 056 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502731 $0.01 000001079749-3562500636
2024 10 FD52 00 E111 D 1377701D 056 4/26/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042O1062411502731 $198.95 000001079749-3562500636
2024 10 FD52 00 E111 D 1377701D 056 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502731 $32.27 000001079749-3562500636
2024 10 FD52 00 E121 D 1377701D 056 4/26/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042O1062411502731 $14.39 000001079749-3562500636
2024 10 FD52 00 E121 D 1377701D 056 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502731 $2.33 000001079749-3562500636
2024 10 FD52 00 E122 D 1377701D 056 4/26/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042O1062411502731 $131.61 000001079749-3562500636
2024 10 FD52 05 E143 D 1377701D 056 4/22/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400209897 PON22200002246 AECOM TECHNICAL SERVICES, INC. $719,672.90 Jefferson Co. 5-20061
2024 10 FD52 05 E143 D 1377701D 056 4/22/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400209650 PON22300001539 Stanton Constructability Services, LLC $18,941.66 Letter Agreement 2
2024 10 FD52 05 E143 D 1377701D 056 4/22/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400209765 PON22300001539 Stanton Constructability Services, LLC $69,379.37 Letter Agreement 2
2024 10 FD52 05 E143 D 1377701D 056 4/22/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400209897 PON22200002246 AECOM TECHNICAL SERVICES, INC. $15,000.00 Jefferson Co. 5-20061
2024 10 FD52 05 E143 D 1377701D 056 4/22/2024 0310 PROJECT DEVELOPMENT JV2E-2400006360 WSP USA INC ($847,031.00) Reversing changes from JV2E 2400006103
2024 10 FD52 05 E143 D 1377701D 121 4/22/2024 1550 DESIGN CONTRACTS-CONSULTANT JV2E-2400006360 WSP USA INC ($847,031.00) Moving charge from 1377701D to 1678001D
2024 10 FD52 00 E229 D 1377701D 056 4/17/2024 5021 GEOTECH INVEST STRUCTURE (DESI IET-XE13A162524101017380 $28.89
2024 10 FD52 00 E111 D 1377701D 056 4/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR041O1062410001621 $3,762.03 000001081429-3562500610
2024 10 FD52 00 E111 D 1377701D 056 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001621 $509.01 000001081429-3562500610
2024 10 FD52 00 E121 D 1377701D 056 4/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR041O1062410001621 $263.47 000001081429-3562500610
2024 10 FD52 00 E121 D 1377701D 056 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001621 $36.09 000001081429-3562500610
2024 10 FD52 00 E122 D 1377701D 056 4/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR041O1062410001621 $2,489.69 000001081429-3562500610
2024 10 FD52 00 E122 D 1377701D 056 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001621 $336.82 000001081429-3562500610
2024 10 FD52 00 E123 D 1377701D 056 4/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR041O1062410001621 $671.62 000001081429-3562500610
2024 10 FD52 00 E123 D 1377701D 056 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001621 $91.17 000001081429-3562500610
2024 10 FD52 05 E143 D 1377701D 056 4/4/2024 0310 PROJECT DEVELOPMENT JV2E-2400006103 WSP USA INC $847,031.00 Correcting funding information from one program to another
2024 9 FD52 00 E111 D 1377701D 056 3/25/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032O1062408200398 $154.74 000001079749-3562500636
2024 9 FD52 00 E111 D 1377701D 056 3/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032O1062408200398 $1.77 000001079749-3562500636
2024 9 FD52 00 E121 D 1377701D 056 3/25/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032O1062408200398 $11.19 000001079749-3562500636
2024 9 FD52 00 E121 D 1377701D 056 3/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032O1062408200398 $0.12 000001079749-3562500636
2024 9 FD52 00 E122 D 1377701D 056 3/25/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032O1062408200398 $102.37 000001079749-3562500636
2024 9 FD52 00 E122 D 1377701D 056 3/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032O1062408200398 $1.17 000001079749-3562500636
2024 9 FD52 00 E111 D 1377701D 056 3/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR032O1062408200402 $929.80 000001081429-3562500610
2024 9 FD52 00 E123 D 1377701D 056 3/25/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032O1062408200398 $35.84 000001079749-3562500636
2024 9 FD52 00 E111 D 1377701D 056 3/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032O1062408200402 $43.57 000001081429-3562500610
2024 9 FD52 00 E123 D 1377701D 056 3/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032O1062408200398 $0.41 000001079749-3562500636
2024 9 FD52 00 E121 D 1377701D 056 3/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR032O1062408200402 $68.33 000001081429-3562500610
2024 9 FD52 00 E124 D 1377701D 056 3/25/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032O1062408200398 $0.04 000001079749-3562500636
2024 9 FD52 00 E121 D 1377701D 056 3/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032O1062408200402 $3.11 000001081429-3562500610
2024 9 FD52 00 E122 D 1377701D 056 3/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR032O1062408200402 $615.25 000001081429-3562500610
2024 9 FD52 00 E122 D 1377701D 056 3/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032O1062408200402 $28.83 000001081429-3562500610
2024 9 FD52 00 E123 D 1377701D 056 3/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR032O1062408200402 $120.55 000001081429-3562500610
2024 9 FD52 00 E123 D 1377701D 056 3/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032O1062408200402 $9.26 000001081429-3562500610
2024 9 FD52 00 E124 D 1377701D 056 3/25/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR032O1062408200402 $0.20 000001081429-3562500610
2024 9 FD52 00 E124 D 1377701D 056 3/25/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032O1062408200402 $0.01 000001081429-3562500610
2024 9 FD52 00 E111 D 1377701D 056 3/11/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031O1062406810065 $174.06 000001079749-3562500636
2024 9 FD52 00 E111 D 1377701D 056 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810065 $16.53 000001079749-3562500636
2024 9 FD52 00 E121 D 1377701D 056 3/11/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031O1062406810065 $12.55 000001079749-3562500636
2024 9 FD52 00 E121 D 1377701D 056 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810065 $1.17 000001079749-3562500636
2024 9 FD52 00 E122 D 1377701D 056 3/11/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031O1062406810065 $115.18 000001079749-3562500636
2024 9 FD52 00 E122 D 1377701D 056 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810065 $10.94 000001079749-3562500636
2024 9 FD52 00 E123 D 1377701D 056 3/11/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031O1062406810065 $34.10 000001079749-3562500636
2024 9 FD52 00 E123 D 1377701D 056 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810065 $3.80 000001079749-3562500636
2024 9 FD52 00 E111 D 1377701D 056 3/11/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031O1062406810068 $3,250.92 000001081429-3562500610
2024 9 FD52 00 E111 D 1377701D 056 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810068 $232.61 000001081429-3562500610
2024 9 FD52 00 E121 D 1377701D 056 3/11/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031O1062406810068 $232.66 000001081429-3562500610
2024 9 FD52 00 E121 D 1377701D 056 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810068 $16.73 000001081429-3562500610
2024 9 FD52 00 E122 D 1377701D 056 3/11/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031O1062406810068 $2,150.88 000001081429-3562500610
2024 9 FD52 00 E122 D 1377701D 056 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810068 $153.91 000001081429-3562500610
2024 9 FD52 00 E123 D 1377701D 056 3/11/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031O1062406810068 $496.48 000001081429-3562500610
2024 9 FD52 00 E123 D 1377701D 056 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810068 $28.50 000001081429-3562500610
2024 8 FD52 00 E111 D 1377701D 056 2/29/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR022O1062405408949 $188.36 000001091103-3562500480
2024 8 FD52 00 E121 D 1377701D 056 2/29/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR022O1062405408949 $14.14 000001091103-3562500480
2024 8 FD52 00 E122 D 1377701D 056 2/29/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR022O1062405408949 $124.64 000001091103-3562500480
2024 8 FD52 00 E123 D 1377701D 056 2/29/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR022O1062405408949 $27.06 000001091103-3562500480
2024 8 FD52 00 E124 D 1377701D 056 2/29/2024 3030 INSPECTION&SUPER-RAILROAD CA-XR022O1062405408949 $0.05 000001091103-3562500480
2024 8 FD52 05 E797 D 1377701D 056 2/28/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092239002P004K CTXCONST0922390020001K Kiewit Infrastructure South Co. $162,119.71
2024 8 FD52 00 E111 D 1377701D 056 2/26/2024 1620 BRIDGE DESIGN & PLANS CA-XR022O1062405408942 $3,107.01 000001091003-3562500610
2024 8 FD52 00 E121 D 1377701D 056 2/26/2024 1620 BRIDGE DESIGN & PLANS CA-XR022O1062405408942 $236.09 000001091003-3562500610
2024 8 FD52 00 E122 D 1377701D 056 2/26/2024 1620 BRIDGE DESIGN & PLANS CA-XR022O1062405408942 $2,055.90 000001091003-3562500610
2024 8 FD52 00 E123 D 1377701D 056 2/26/2024 1620 BRIDGE DESIGN & PLANS CA-XR022O1062405408942 $491.50 000001091003-3562500610
2024 8 FD52 00 E111 D 1377701D 056 2/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR022O1062405408890 $3,125.85 000001081429-3562500610
2024 8 FD52 00 E124 D 1377701D 056 2/26/2024 1620 BRIDGE DESIGN & PLANS CA-XR022O1062405408942 $1.09 000001091003-3562500610
2024 8 FD52 00 E111 D 1377701D 056 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408890 $498.54 000001081429-3562500610
2024 8 FD52 00 E121 D 1377701D 056 2/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR022O1062405408890 $228.73 000001081429-3562500610
2024 8 FD52 00 E121 D 1377701D 056 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408890 $37.09 000001081429-3562500610
2024 8 FD52 00 E122 D 1377701D 056 2/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR022O1062405408890 $2,068.46 000001081429-3562500610
2024 8 FD52 00 E122 D 1377701D 056 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408890 $329.89 000001081429-3562500610
2024 8 FD52 00 E123 D 1377701D 056 2/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR022O1062405408890 $458.36 000001081429-3562500610
2024 8 FD52 00 E123 D 1377701D 056 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408890 $45.77 000001081429-3562500610
2024 8 FD52 00 E124 D 1377701D 056 2/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR022O1062405408890 $0.85 000001081429-3562500610
2024 8 FD52 00 E124 D 1377701D 056 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408890 $0.11 000001081429-3562500610
2024 8 FD52 05 E143 D 1377701D 056 2/21/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400167918 PON22200002246 AECOM TECHNICAL SERVICES, INC. $126,941.38 Jefferson Co. 5-20061
2024 8 FD52 05 E143 D 1377701D 056 2/21/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400167918 PON22200002246 AECOM TECHNICAL SERVICES, INC. $15,000.00 Jefferson Co. 5-20061
2024 8 FD52 05 E143 D 1377701D 056 2/16/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400165557 PON22300001539 Stanton Constructability Services, LLC $9,773.96 Letter Agreement 2
2024 8 FD52 05 E797 D 1377701D 056 2/14/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092239002P003K CTXCONST0922390020001K Kiewit Infrastructure South Co. $168,441.83
2024 8 FD52 00 E121 D 1377701D 056 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907715 $7.86 000001091003-3562500610
2024 8 FD52 00 E122 D 1377701D 056 2/9/2024 1620 BRIDGE DESIGN & PLANS CA-XR021O1062403907715 $761.94 000001091003-3562500610
2024 8 FD52 00 E122 D 1377701D 056 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907715 $69.42 000001091003-3562500610
2024 8 FD52 00 E123 D 1377701D 056 2/9/2024 1620 BRIDGE DESIGN & PLANS CA-XR021O1062403907715 $124.11 000001091003-3562500610
2024 8 FD52 00 E123 D 1377701D 056 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907715 $11.18 000001091003-3562500610
2024 8 FD52 00 E111 D 1377701D 056 2/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021O1062403907659 $2,451.03 000001081429-3562500610
2024 8 FD52 00 E111 D 1377701D 056 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907659 $83.46 000001081429-3562500610
2024 8 FD52 00 E121 D 1377701D 056 2/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021O1062403907659 $176.19 000001081429-3562500610
2024 8 FD52 00 E121 D 1377701D 056 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907659 $6.11 000001081429-3562500610
2024 8 FD52 00 E122 D 1377701D 056 2/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021O1062403907659 $1,621.59 000001081429-3562500610
2024 8 FD52 00 E122 D 1377701D 056 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907659 $55.23 000001081429-3562500610
2024 8 FD52 00 E123 D 1377701D 056 2/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021O1062403907659 $294.11 000001081429-3562500610
2024 8 FD52 00 E123 D 1377701D 056 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907659 $8.14 000001081429-3562500610
2024 8 FD52 00 E111 D 1377701D 056 2/9/2024 1620 BRIDGE DESIGN & PLANS CA-XR021O1062403907715 $1,151.48 000001091003-3562500610
2024 8 FD52 00 E111 D 1377701D 056 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907715 $104.91 000001091003-3562500610
2024 8 FD52 00 E121 D 1377701D 056 2/9/2024 1620 BRIDGE DESIGN & PLANS CA-XR021O1062403907715 $86.31 000001091003-3562500610
2024 8 FD52 05 E143 D 1377701D 056 2/7/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400157761 PON22200002246 AECOM TECHNICAL SERVICES, INC. $393,232.92 Jefferson Co. 5-20061
2024 8 FD52 05 E143 D 1377701D 056 2/7/2024 0310 PROJECT DEVELOPMENT PRC-2400157768 PON22200002099 WSP USA INC $576,521.00 Letter Agreement 1X
2024 8 FD52 05 E143 D 1377701D 056 2/7/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400157761 PON22200002246 AECOM TECHNICAL SERVICES, INC. $15,000.00 Jefferson Co. 5-20061
2024 8 FD52 05 E143 D 1377701D 056 2/5/2024 0310 PROJECT DEVELOPMENT PRC-2400155074 PON22200002099 WSP USA INC $1,304.49 Letter Agreement 2
2024 8 FD52 05 E143 D 1377701D 056 2/2/2024 0310 PROJECT DEVELOPMENT PRC-2400153875 PON22200002099 WSP USA INC $593,621.70 Letter Agreement 6
2024 8 FD52 05 E143 D 1377701D 056 2/2/2024 0310 PROJECT DEVELOPMENT PRC-2400153882 PON22200002099 WSP USA INC $253,409.30 Letter Agreement 6
2024 7 FD52 05 E143 D 1377701D 056 1/25/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400148172 PON22300001539 Stanton Constructability Services, LLC $8,062.32 Letter Agreement 2
2024 7 FD52 05 E143 D 1377701D 056 1/24/2024 0310 PROJECT DEVELOPMENT PRC-2400145484 PON22200002099 WSP USA INC $8,224.93 Letter Agreement 2
2024 7 FD52 00 E111 D 1377701D 056 1/24/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012O1062402306580 $267.10 000001081429-3562500610
2024 7 FD52 00 E111 D 1377701D 056 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306580 $59.37 000001081429-3562500610
2024 7 FD52 00 E121 D 1377701D 056 1/24/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012O1062402306580 $18.39 000001081429-3562500610
2024 7 FD52 00 E121 D 1377701D 056 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306580 $4.08 000001081429-3562500610
2024 7 FD52 00 E122 D 1377701D 056 1/24/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012O1062402306580 $176.42 000001081429-3562500610
2024 7 FD52 00 E122 D 1377701D 056 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306580 $39.29 000001081429-3562500610
2024 7 FD52 00 E123 D 1377701D 056 1/24/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012O1062402306580 $46.05 000001081429-3562500610
2024 7 FD52 00 E123 D 1377701D 056 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306580 $10.18 000001081429-3562500610
2024 7 FD52 00 E124 D 1377701D 056 1/24/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012O1062402306580 $0.06 000001081429-3562500610
2024 7 FD52 00 E124 D 1377701D 056 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306580 $0.01 000001081429-3562500610
2024 7 FD52 05 E143 D 1377701D 056 1/16/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400139935 PON22200002246 AECOM TECHNICAL SERVICES, INC. $15,561.37 Jefferson Co. 5-20061
2024 7 FD52 05 E143 D 1377701D 056 1/16/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400139935 PON22200002246 AECOM TECHNICAL SERVICES, INC. $15,000.00 Jefferson Co. 5-20061
2024 7 FD52 05 E797 D 1377701D 056 1/10/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092239002P002K CTXCONST0922390020001K Kiewit Infrastructure South Co. $101,303.31
2024 7 FD52 05 E143 D 1377701D 056 1/8/2024 0310 PROJECT DEVELOPMENT PRC-2400133068 PON22200002099 WSP USA INC $15,074.56 Letter Agreement 2
2024 7 FD52 05 E143 D 1377701D 056 1/2/2024 0310 PROJECT DEVELOPMENT PRC-2400128809 PON22200002099 WSP USA INC $299,894.00 Letter Agreement 1X
2024 6 FD52 00 E111 D 1377701D 056 12/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR121N1062334203611 $71.52 000001079749-3562500636
2024 6 FD52 00 E111 D 1377701D 056 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203611 $18.62 000001079749-3562500636
2024 6 FD52 00 E121 D 1377701D 056 12/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR121N1062334203611 $5.37 000001079749-3562500636
2024 6 FD52 00 E121 D 1377701D 056 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203611 $1.40 000001079749-3562500636
2024 6 FD52 00 E122 D 1377701D 056 12/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR121N1062334203611 $47.38 000001079749-3562500636
2024 6 FD52 00 E122 D 1377701D 056 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203611 $12.32 000001079749-3562500636
2024 6 FD52 00 E123 D 1377701D 056 12/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR121N1062334203611 $7.03 000001079749-3562500636
2024 6 FD52 00 E123 D 1377701D 056 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203611 $1.80 000001079749-3562500636
2024 6 FD52 05 E797 D 1377701D 056 12/6/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092239002P001K CTXCONST0922390020001K Kiewit Infrastructure South Co. $64,762.61
2024 5 FD52 05 E143 D 1377701D 056 11/20/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400100804 PON22200002246 AECOM TECHNICAL SERVICES, INC. $35,000.00 Jefferson Co. 5-20061
2024 5 FD52 05 E143 D 1377701D 056 11/20/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400100804 PON22200002246 AECOM TECHNICAL SERVICES, INC. $15,000.00 Jefferson Co. 5-20061
2024 5 FD52 05 E143 D 1377701D 056 11/9/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400094416 PON22200002246 AECOM TECHNICAL SERVICES, INC. $20,000.00 Jefferson Co. 5-20061
2024 5 FD52 00 E111 D 1377701D 056 11/9/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR111N1062331201511 $1,535.31 000001089166-3562500610
2024 5 FD52 00 E121 D 1377701D 056 11/9/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR111N1062331201511 $114.60 000001089166-3562500610
2024 5 FD52 00 E122 D 1377701D 056 11/9/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR111N1062331201511 $1,015.92 000001089166-3562500610
2024 5 FD52 05 E143 D 1377701D 056 11/9/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400094416 PON22200002246 AECOM TECHNICAL SERVICES, INC. $15,000.00 Jefferson Co. 5-20061
2024 5 FD52 00 E123 D 1377701D 056 11/9/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR111N1062331201511 $143.37 000001089166-3562500610
2024 4 FD52 05 E143 D 1377701D 056 10/26/2023 0310 PROJECT DEVELOPMENT PRC-2400019669 PON22200002099 WSP USA INC $21,669.87 Letter Agreement 2
2024 4 FD52 05 E143 D 1377701D 056 10/26/2023 0310 PROJECT DEVELOPMENT PRC-2400083465 PON22200002099 WSP USA INC $23,996.05 Letter Agreement 2
2024 4 FD52 05 E143 D 1377701D 056 10/26/2023 0310 PROJECT DEVELOPMENT PRC-2400083486 PON22200002099 WSP USA INC $21,221.83 Letter Agreement 2
2024 4 FD52 00 E111 D 1377701D 056 10/24/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR102N1062329600452 $460.60 000001089166-3562500610
2024 4 FD52 00 E111 D 1377701D 056 10/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102N1062329600452 $3.07 000001089166-3562500610
2024 4 FD52 00 E121 D 1377701D 056 10/24/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR102N1062329600452 $34.91 000001089166-3562500610
2024 4 FD52 00 E121 D 1377701D 056 10/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102N1062329600452 $0.23 000001089166-3562500610
2024 4 FD52 00 E122 D 1377701D 056 10/24/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR102N1062329600452 $304.78 000001089166-3562500610
2024 4 FD52 00 E122 D 1377701D 056 10/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102N1062329600452 $2.03 000001089166-3562500610
2024 4 FD52 00 E123 D 1377701D 056 10/24/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR102N1062329600452 $43.01 000001089166-3562500610
2024 4 FD52 00 E123 D 1377701D 056 10/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102N1062329600452 $0.28 000001089166-3562500610
2024 4 FD52 00 E124 D 1377701D 056 10/24/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR102N1062329600452 $0.10 000001089166-3562500610
2024 4 FD52 00 E111 D 1377701D 056 10/9/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR101N1062328009724 $921.19 000001089166-3562500610
2024 4 FD52 00 E121 D 1377701D 056 10/9/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR101N1062328009724 $68.76 000001089166-3562500610
2024 4 FD52 00 E122 D 1377701D 056 10/9/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR101N1062328009724 $609.55 000001089166-3562500610
2024 4 FD52 00 E123 D 1377701D 056 10/9/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR101N1062328009724 $86.02 000001089166-3562500610
2024 3 FD52 00 E122 D 1377701D 056 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208403 $90.34 000001079749-3562500636
2024 3 FD52 00 E123 D 1377701D 056 9/29/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062327208403 $11.84 000001079749-3562500636
2024 3 FD52 00 E123 D 1377701D 056 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208403 $13.18 000001079749-3562500636
2024 3 FD52 00 E124 D 1377701D 056 9/29/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062327208403 $0.03 000001079749-3562500636
2024 3 FD52 00 E124 D 1377701D 056 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208403 $0.03 000001079749-3562500636
2024 3 FD52 00 E111 D 1377701D 056 9/29/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062327208457 $1,244.28 000001089166-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208457 $124.43 000001089166-3562500610
2024 3 FD52 00 E121 D 1377701D 056 9/29/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062327208457 $90.49 000001089166-3562500610
2024 3 FD52 00 E121 D 1377701D 056 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208457 $9.05 000001089166-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/29/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062327208403 $119.25 000001079749-3562500636
2024 3 FD52 00 E122 D 1377701D 056 9/29/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062327208457 $823.34 000001089166-3562500610
2024 3 FD52 00 E122 D 1377701D 056 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208457 $82.33 000001089166-3562500610
2024 3 FD52 00 E123 D 1377701D 056 9/29/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062327208457 $191.81 000001089166-3562500610
2024 3 FD52 00 E123 D 1377701D 056 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208457 $19.03 000001089166-3562500610
2024 3 FD52 00 E124 D 1377701D 056 9/29/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062327208457 $0.27 000001089166-3562500610
2024 3 FD52 00 E124 D 1377701D 056 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208457 $0.03 000001089166-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208403 $136.52 000001079749-3562500636
2024 3 FD52 00 E121 D 1377701D 056 9/29/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062327208403 $9.07 000001079749-3562500636
2024 3 FD52 00 E121 D 1377701D 056 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208403 $10.38 000001079749-3562500636
2024 3 FD52 00 E122 D 1377701D 056 9/29/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062327208403 $78.96 000001079749-3562500636
2024 3 FD52 00 E122 D 1377701D 056 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507052 ($90.34) 000001079749-3562500636
2024 3 FD52 00 E123 D 1377701D 056 9/28/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062326507052 ($11.84) 000001079749-3562500636
2024 3 FD52 00 E123 D 1377701D 056 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507052 ($13.18) 000001079749-3562500636
2024 3 FD52 00 E124 D 1377701D 056 9/28/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062326507052 ($0.03) 000001079749-3562500636
2024 3 FD52 00 E124 D 1377701D 056 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507052 ($0.03) 000001079749-3562500636
2024 3 FD52 00 E111 D 1377701D 056 9/28/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062326507106 ($1,244.28) 000001089166-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507106 ($124.43) 000001089166-3562500610
2024 3 FD52 00 E121 D 1377701D 056 9/28/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062326507106 ($90.49) 000001089166-3562500610
2024 3 FD52 00 E121 D 1377701D 056 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507106 ($9.05) 000001089166-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/28/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062326507052 ($119.25) 000001079749-3562500636
2024 3 FD52 00 E122 D 1377701D 056 9/28/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062326507106 ($823.34) 000001089166-3562500610
2024 3 FD52 00 E122 D 1377701D 056 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507106 ($82.33) 000001089166-3562500610
2024 3 FD52 00 E123 D 1377701D 056 9/28/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062326507106 ($191.81) 000001089166-3562500610
2024 3 FD52 00 E123 D 1377701D 056 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507106 ($19.03) 000001089166-3562500610
2024 3 FD52 00 E124 D 1377701D 056 9/28/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062326507106 ($0.27) 000001089166-3562500610
2024 3 FD52 00 E124 D 1377701D 056 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507106 ($0.03) 000001089166-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507052 ($136.52) 000001079749-3562500636
2024 3 FD52 00 E121 D 1377701D 056 9/28/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062326507052 ($9.07) 000001079749-3562500636
2024 3 FD52 00 E121 D 1377701D 056 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507052 ($10.38) 000001079749-3562500636
2024 3 FD52 00 E122 D 1377701D 056 9/28/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062326507052 ($78.96) 000001079749-3562500636
2024 3 FD52 00 E122 D 1377701D 056 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507052 $90.34 000001079749-3562500636
2024 3 FD52 00 E123 D 1377701D 056 9/25/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062326507052 $11.84 000001079749-3562500636
2024 3 FD52 00 E123 D 1377701D 056 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507052 $13.18 000001079749-3562500636
2024 3 FD52 00 E124 D 1377701D 056 9/25/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062326507052 $0.03 000001079749-3562500636
2024 3 FD52 00 E124 D 1377701D 056 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507052 $0.03 000001079749-3562500636
2024 3 FD52 00 E111 D 1377701D 056 9/25/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062326507106 $1,244.28 000001089166-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507106 $124.43 000001089166-3562500610
2024 3 FD52 00 E121 D 1377701D 056 9/25/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062326507106 $90.49 000001089166-3562500610
2024 3 FD52 00 E121 D 1377701D 056 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507106 $9.05 000001089166-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/25/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062326507052 $119.25 000001079749-3562500636
2024 3 FD52 00 E122 D 1377701D 056 9/25/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062326507106 $823.34 000001089166-3562500610
2024 3 FD52 00 E122 D 1377701D 056 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507106 $82.33 000001089166-3562500610
2024 3 FD52 00 E123 D 1377701D 056 9/25/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062326507106 $191.81 000001089166-3562500610
2024 3 FD52 00 E123 D 1377701D 056 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507106 $19.03 000001089166-3562500610
2024 3 FD52 00 E124 D 1377701D 056 9/25/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR092N1062326507106 $0.27 000001089166-3562500610
2024 3 FD52 00 E124 D 1377701D 056 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507106 $0.03 000001089166-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507052 $136.52 000001079749-3562500636
2024 3 FD52 00 E121 D 1377701D 056 9/25/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062326507052 $9.07 000001079749-3562500636
2024 3 FD52 00 E121 D 1377701D 056 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507052 $10.38 000001079749-3562500636
2024 3 FD52 00 E122 D 1377701D 056 9/25/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092N1062326507052 $78.96 000001079749-3562500636
2024 3 FD52 00 E111 D 1377701D 056 9/19/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR091N1062325106138 $760.46 000001089166-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/19/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106138 $2.03 000001089166-3562500610
2024 3 FD52 00 E121 D 1377701D 056 9/19/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR091N1062325106138 $53.79 000001089166-3562500610
2024 3 FD52 00 E121 D 1377701D 056 9/19/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106138 $0.15 000001089166-3562500610
2024 3 FD52 00 E122 D 1377701D 056 9/19/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR091N1062325106138 $503.15 000001089166-3562500610
2024 3 FD52 00 E122 D 1377701D 056 9/19/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106138 $1.34 000001089166-3562500610
2024 3 FD52 00 E123 D 1377701D 056 9/19/2023 1640 BRIDGE-REVIEW OF PLANS CA-XR091N1062325106138 $117.14 000001089166-3562500610
2024 3 FD52 00 E123 D 1377701D 056 9/19/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106138 $0.31 000001089166-3562500610
2024 3 FD52 05 E143 D 1377701D 056 9/15/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400052369 PON22200002246 AECOM TECHNICAL SERVICES, INC. $59,642.61 Jefferson Co. 5-20061
2024 3 FD52 05 E143 D 1377701D 056 9/15/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400052369 PON22200002246 AECOM TECHNICAL SERVICES, INC. $15,000.00 Jefferson Co. 5-20061
2024 3 FD52 00 E111 D 1377701D 056 9/11/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091N1062325106087 $217.68 000001081429-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106087 $4.35 000001081429-3562500610
2024 3 FD52 00 E121 D 1377701D 056 9/11/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091N1062325106087 $15.09 000001081429-3562500610
2024 3 FD52 00 E121 D 1377701D 056 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106087 $0.30 000001081429-3562500610
2024 3 FD52 00 E122 D 1377701D 056 9/11/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091N1062325106087 $144.04 000001081429-3562500610
2024 3 FD52 00 E122 D 1377701D 056 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106087 $2.88 000001081429-3562500610
2024 3 FD52 00 E123 D 1377701D 056 9/11/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091N1062325106087 $31.24 000001081429-3562500610
2024 3 FD52 00 E123 D 1377701D 056 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106087 $0.62 000001081429-3562500610
2024 3 FD52 00 E111 D 1377701D 056 9/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091N1062325106083 $153.17 000001079749-3562500636
2024 3 FD52 00 E111 D 1377701D 056 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106083 $8.75 000001079749-3562500636
2024 3 FD52 00 E121 D 1377701D 056 9/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091N1062325106083 $11.48 000001079749-3562500636
2024 3 FD52 00 E121 D 1377701D 056 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106083 $0.66 000001079749-3562500636
2024 3 FD52 00 E122 D 1377701D 056 9/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091N1062325106083 $101.33 000001079749-3562500636
2024 3 FD52 00 E122 D 1377701D 056 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106083 $5.79 000001079749-3562500636
2024 3 FD52 00 E123 D 1377701D 056 9/11/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091N1062325106083 $14.98 000001079749-3562500636
2024 3 FD52 00 E123 D 1377701D 056 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106083 $0.85 000001079749-3562500636
2024 2 FD52 00 E111 D 1377701D 056 8/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR082N1062323504934 $790.51 000001081429-3562500610
2024 2 FD52 00 E111 D 1377701D 056 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504934 $21.50 000001081429-3562500610
2024 2 FD52 00 E121 D 1377701D 056 8/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR082N1062323504934 $56.50 000001081429-3562500610
2024 2 FD52 00 E121 D 1377701D 056 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504934 $1.52 000001081429-3562500610
2024 2 FD52 00 E122 D 1377701D 056 8/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR082N1062323504934 $523.03 000001081429-3562500610
2024 2 FD52 00 E122 D 1377701D 056 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504934 $14.22 000001081429-3562500610
2024 2 FD52 00 E123 D 1377701D 056 8/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR082N1062323504934 $93.40 000001081429-3562500610
2024 2 FD52 00 E123 D 1377701D 056 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504934 $2.83 000001081429-3562500610
2024 2 FD52 00 E124 D 1377701D 056 8/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR082N1062323504934 $0.17 000001081429-3562500610
2024 2 FD52 00 E123 D 1377701D 056 8/15/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081N1062322003854 $7.89 000001081429-3562500610
2024 2 FD52 00 E123 D 1377701D 056 8/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003854 $0.59 000001081429-3562500610
2024 2 FD52 00 E111 D 1377701D 056 8/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR081N1062322003886 $284.25 000001088342-3562500061
2024 2 FD52 00 E111 D 1377701D 056 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003886 $236.88 000001088342-3562500061
2024 2 FD52 00 E121 D 1377701D 056 8/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR081N1062322003886 $20.04 000001088342-3562500061
2024 2 FD52 00 E121 D 1377701D 056 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003886 $16.70 000001088342-3562500061
2024 2 FD52 00 E122 D 1377701D 056 8/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR081N1062322003886 $188.09 000001088342-3562500061
2024 2 FD52 00 E122 D 1377701D 056 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003886 $156.74 000001088342-3562500061
2024 2 FD52 00 E123 D 1377701D 056 8/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR081N1062322003886 $64.28 000001088342-3562500061
2024 2 FD52 00 E123 D 1377701D 056 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003886 $52.86 000001088342-3562500061
2024 2 FD52 00 E111 D 1377701D 056 8/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081N1062322003853 $334.13 000001081429-3562500610
2024 2 FD52 00 E111 D 1377701D 056 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003853 $26.25 000001081429-3562500610
2024 2 FD52 00 E121 D 1377701D 056 8/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081N1062322003853 $25.56 000001081429-3562500610
2024 2 FD52 00 E121 D 1377701D 056 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003853 $2.01 000001081429-3562500610
2024 2 FD52 00 E122 D 1377701D 056 8/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081N1062322003853 $221.09 000001081429-3562500610
2024 2 FD52 00 E122 D 1377701D 056 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003853 $17.36 000001081429-3562500610
2024 1 FD52 00 E124 D 1377701D 056 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202672 $0.04 000001081429-3562500610
2024 1 FD52 00 E111 D 1377701D 056 7/28/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR072N1062320202721 $297.79 000001088342-3562500061
2024 1 FD52 00 E111 D 1377701D 056 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202721 $48.44 000001088342-3562500061
2024 1 FD52 00 E121 D 1377701D 056 7/28/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR072N1062320202721 $21.26 000001088342-3562500061
2024 1 FD52 00 E121 D 1377701D 056 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202721 $3.46 000001088342-3562500061
2024 1 FD52 00 E122 D 1377701D 056 7/28/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR072N1062320202721 $197.05 000001088342-3562500061
2024 1 FD52 00 E122 D 1377701D 056 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202721 $32.06 000001088342-3562500061
2024 1 FD52 00 E123 D 1377701D 056 7/28/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR072N1062320202721 $70.36 000001088342-3562500061
2024 1 FD52 00 E123 D 1377701D 056 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202721 $11.35 000001088342-3562500061
2024 1 FD52 00 E124 D 1377701D 056 7/28/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR072N1062320202721 $0.10 000001088342-3562500061
2024 1 FD52 00 E124 D 1377701D 056 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202721 $0.01 000001088342-3562500061
2024 1 FD52 00 E111 D 1377701D 056 7/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072N1062320202671 $845.26 000001081429-3562500610
2024 1 FD52 00 E111 D 1377701D 056 7/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202671 $134.57 000001081429-3562500610
2024 1 FD52 00 E121 D 1377701D 056 7/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072N1062320202671 $62.78 000001081429-3562500610
2024 1 FD52 00 E121 D 1377701D 056 7/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202671 $9.84 000001081429-3562500610
2024 1 FD52 00 E122 D 1377701D 056 7/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072N1062320202671 $559.25 000001081429-3562500610
2024 1 FD52 00 E122 D 1377701D 056 7/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202671 $89.05 000001081429-3562500610
2024 1 FD52 00 E123 D 1377701D 056 7/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072N1062320202671 $55.28 000001081429-3562500610
2024 1 FD52 00 E123 D 1377701D 056 7/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202671 $11.78 000001081429-3562500610
2024 1 FD52 00 E124 D 1377701D 056 7/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072N1062320202671 $0.20 000001081429-3562500610
2024 1 FD52 05 E143 D 1377701D 056 7/18/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400010726 PON22200002246 AECOM TECHNICAL SERVICES, INC. $12,000.00 Jefferson Co. 5-20061
2024 1 FD52 05 E143 D 1377701D 056 7/18/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400010726 PON22200002246 AECOM TECHNICAL SERVICES, INC. $848.00 Jefferson Co. 5-20061
2024 1 FD52 00 E111 D 1377701D 056 7/14/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071N1062319101541 $495.26 000001081429-3562500610
2024 1 FD52 00 E111 D 1377701D 056 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101541 $234.61 000001081429-3562500610
2024 1 FD52 00 E121 D 1377701D 056 7/14/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071N1062319101541 $37.89 000001081429-3562500610
2024 1 FD52 00 E121 D 1377701D 056 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101541 $17.95 000001081429-3562500610
2024 1 FD52 00 E122 D 1377701D 056 7/14/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071N1062319101541 $386.04 000001081429-3562500610
2024 1 FD52 00 E122 D 1377701D 056 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101541 $183.00 000001081429-3562500610
2024 1 FD52 00 E123 D 1377701D 056 7/14/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071N1062319101541 $12.66 000001081429-3562500610
2024 1 FD52 00 E123 D 1377701D 056 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101541 $5.53 000001081429-3562500610
2024 1 FD52 05 E143 D 1377701D 056 7/12/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400006473 PON22200002246 AECOM TECHNICAL SERVICES, INC. $25,000.00 Jefferson Co. 5-20061
2023 12 FD52 00 E111 D 1377701D 056 6/26/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR062N1062317400462 $561.61 000001087335-3562500061
2023 12 FD52 00 E111 D 1377701D 056 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317400462 $6.86 000001087335-3562500061
2023 12 FD52 00 E121 D 1377701D 056 6/26/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR062N1062317400462 $40.50 000001087335-3562500061
2023 12 FD52 00 E121 D 1377701D 056 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317400462 $0.49 000001087335-3562500061
2023 12 FD52 00 E122 D 1377701D 056 6/26/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR062N1062317400462 $438.05 000001087335-3562500061
2023 12 FD52 00 E122 D 1377701D 056 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317400462 $5.35 000001087335-3562500061
2023 12 FD52 00 E123 D 1377701D 056 6/26/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR062N1062317400462 $93.86 000001087335-3562500061
2023 12 FD52 00 E123 D 1377701D 056 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317400462 $1.13 000001087335-3562500061
2023 12 FD52 00 E124 D 1377701D 056 6/26/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR062N1062317400462 $0.22 000001087335-3562500061
2023 12 FD52 00 E122 D 1377701D 056 6/8/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR061N1062315810165 $1,388.68 000001087335-3562500061
2023 12 FD52 00 E122 D 1377701D 056 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810165 $619.05 000001087335-3562500061
2023 12 FD52 00 E123 D 1377701D 056 6/8/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR061N1062315810165 $299.05 000001087335-3562500061
2023 12 FD52 00 E123 D 1377701D 056 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810165 $131.05 000001087335-3562500061
2023 12 FD52 00 E111 D 1377701D 056 6/8/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR061N1062315810165 $1,780.36 000001087335-3562500061
2023 12 FD52 00 E111 D 1377701D 056 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810165 $793.65 000001087335-3562500061
2023 12 FD52 00 E121 D 1377701D 056 6/8/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR061N1062315810165 $128.38 000001087335-3562500061
2023 12 FD52 00 E121 D 1377701D 056 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810165 $57.24 000001087335-3562500061
2023 11 FD52 00 E111 D 1377701D 056 5/24/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR052N1062314309074 $1,715.93 000001087335-3562500061
2023 11 FD52 00 E111 D 1377701D 056 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309074 $433.06 000001087335-3562500061
2023 11 FD52 00 E121 D 1377701D 056 5/24/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR052N1062314309074 $122.26 000001087335-3562500061
2023 11 FD52 00 E121 D 1377701D 056 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309074 $30.79 000001087335-3562500061
2023 11 FD52 00 E122 D 1377701D 056 5/24/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR052N1062314309074 $1,338.49 000001087335-3562500061
2023 11 FD52 00 E122 D 1377701D 056 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309074 $337.79 000001087335-3562500061
2023 11 FD52 00 E123 D 1377701D 056 5/24/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR052N1062314309074 $310.56 000001087335-3562500061
2023 11 FD52 00 E123 D 1377701D 056 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309074 $78.50 000001087335-3562500061
2023 11 FD52 00 E124 D 1377701D 056 5/24/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR052N1062314309074 $0.67 000001087335-3562500061
2023 11 FD52 00 E111 D 1377701D 056 5/24/2023 0060 ENV STUDIES-ARCHAEOLOGY CA-XR052N1062314309083 $272.07 000001087602-3562500061
2023 11 FD52 00 E124 D 1377701D 056 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309074 $0.16 000001087335-3562500061
2023 11 FD52 00 E111 D 1377701D 056 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309083 $10.16 000001087602-3562500061
2023 11 FD52 00 E121 D 1377701D 056 5/24/2023 0060 ENV STUDIES-ARCHAEOLOGY CA-XR052N1062314309083 $20.52 000001087602-3562500061
2023 11 FD52 00 E121 D 1377701D 056 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309083 $0.77 000001087602-3562500061
2023 11 FD52 00 E122 D 1377701D 056 5/24/2023 0060 ENV STUDIES-ARCHAEOLOGY CA-XR052N1062314309083 $212.29 000001087602-3562500061
2023 11 FD52 00 E122 D 1377701D 056 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309083 $7.92 000001087602-3562500061
2023 11 FD52 00 E123 D 1377701D 056 5/24/2023 0060 ENV STUDIES-ARCHAEOLOGY CA-XR052N1062314309083 $39.12 000001087602-3562500061
2023 11 FD52 00 E123 D 1377701D 056 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309083 $1.44 000001087602-3562500061
2023 11 FD52 00 E124 D 1377701D 056 5/24/2023 0060 ENV STUDIES-ARCHAEOLOGY CA-XR052N1062314309083 $0.09 000001087602-3562500061
2023 11 FD52 00 E111 D 1377701D 056 5/9/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR051N1062312808095 $840.84 000001087335-3562500061
2023 11 FD52 00 E121 D 1377701D 056 5/9/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR051N1062312808095 $60.63 000001087335-3562500061
2023 11 FD52 00 E122 D 1377701D 056 5/9/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR051N1062312808095 $655.86 000001087335-3562500061
2023 11 FD52 00 E123 D 1377701D 056 5/9/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR051N1062312808095 $140.50 000001087335-3562500061
2023 11 FD52 05 E143 D 1377701D 056 5/5/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300213427 PON22200002246 AECOM TECHNICAL SERVICES, INC. $41,239.60 Jefferson Co. 5-20061
2023 10 FD52 05 E143 D 1377701D 056 4/5/2023 0310 PROJECT DEVELOPMENT PRC-2300188851 PON22200002099 WSP USA INC $628.34 Letter Agreement 2
2023 9 FD52 05 E143 D 1377701D 056 3/30/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300183702 PON22200002246 AECOM TECHNICAL SERVICES, INC. $76,215.67 Jefferson Co. 5-20061
2023 9 FD52 05 E143 D 1377701D 056 3/30/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300183708 PON22200002246 AECOM TECHNICAL SERVICES, INC. $42,000.00 Jefferson Co. 5-20061
2023 9 FD52 05 E143 D 1377701D 056 3/30/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300183702 PON22200002246 AECOM TECHNICAL SERVICES, INC. $44,995.00 Jefferson Co. 5-20061
2023 9 FD52 05 E143 D 1377701D 056 3/30/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300183708 PON22200002246 AECOM TECHNICAL SERVICES, INC. $49,114.50 Jefferson Co. 5-20061
2023 9 FD52 05 E143 D 1377701D 056 3/30/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300183702 PON22200002246 AECOM TECHNICAL SERVICES, INC. $33,000.00 Jefferson Co. 5-20061
2023 9 FD52 00 E111 D 1377701D 056 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304641 $7.64 000001081429-3562500610
2023 9 FD52 00 E121 D 1377701D 056 3/27/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR032N1062308304641 $14.07 000001081429-3562500610
2023 9 FD52 00 E121 D 1377701D 056 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304641 $0.53 000001081429-3562500610
2023 9 FD52 00 E122 D 1377701D 056 3/27/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR032N1062308304641 $158.86 000001081429-3562500610
2023 9 FD52 00 E122 D 1377701D 056 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304641 $5.96 000001081429-3562500610
2023 9 FD52 00 E123 D 1377701D 056 3/27/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR032N1062308304641 $34.09 000001081429-3562500610
2023 9 FD52 00 E123 D 1377701D 056 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304641 $1.27 000001081429-3562500610
2023 9 FD52 00 E124 D 1377701D 056 3/27/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR032N1062308304641 $0.05 000001081429-3562500610
2023 9 FD52 00 E111 D 1377701D 056 3/27/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR032N1062308304640 $203.74 000001081429-3562500610
2023 9 FD52 00 E111 D 1377701D 056 3/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031N1062306703657 $186.69 000001081429-3562500610
2023 9 FD52 00 E121 D 1377701D 056 3/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031N1062306703657 $13.31 000001081429-3562500610
2023 9 FD52 00 E122 D 1377701D 056 3/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031N1062306703657 $145.62 000001081429-3562500610
2023 9 FD52 00 E123 D 1377701D 056 3/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031N1062306703657 $31.24 000001081429-3562500610
2023 9 FD52 05 E143 D 1377701D 056 3/7/2023 0310 PROJECT DEVELOPMENT PRC-2300163745 PON22200002099 WSP USA INC $4,163.42 Letter Agreement 2
2023 8 FD52 00 E111 D 1377701D 056 2/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021N1062303901415 $206.39 000001081429-3562500610
2023 8 FD52 00 E111 D 1377701D 056 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901415 $206.39 000001081429-3562500610
2023 8 FD52 00 E121 D 1377701D 056 2/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021N1062303901415 $15.79 000001081429-3562500610
2023 8 FD52 00 E121 D 1377701D 056 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901415 $15.80 000001081429-3562500610
2023 8 FD52 00 E122 D 1377701D 056 2/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021N1062303901415 $160.98 000001081429-3562500610
2023 8 FD52 00 E122 D 1377701D 056 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901415 $160.99 000001081429-3562500610
2023 8 FD52 00 E123 D 1377701D 056 2/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021N1062303901415 $5.97 000001081429-3562500610
2023 8 FD52 00 E123 D 1377701D 056 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901415 $5.34 000001081429-3562500610
2023 7 FD52 05 E143 D 1377701D 056 1/27/2023 0310 PROJECT DEVELOPMENT PRC-2300136533 PON22200002099 WSP USA INC $13,705.28 Letter Agreement 2
2023 7 FD52 00 E111 D 1377701D 056 1/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012N1062302300415 $1,057.48 000001081429-3562500610
2023 7 FD52 00 E111 D 1377701D 056 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300415 $146.17 000001081429-3562500610
2023 7 FD52 00 E121 D 1377701D 056 1/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012N1062302300415 $80.08 000001081429-3562500610
2023 7 FD52 00 E121 D 1377701D 056 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300415 $11.09 000001081429-3562500610
2023 7 FD52 00 E122 D 1377701D 056 1/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012N1062302300415 $824.99 000001081429-3562500610
2023 7 FD52 00 E122 D 1377701D 056 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300415 $114.02 000001081429-3562500610
2023 7 FD52 00 E123 D 1377701D 056 1/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012N1062302300415 $44.89 000001081429-3562500610
2023 7 FD52 00 E123 D 1377701D 056 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300415 $5.59 000001081429-3562500610
2023 7 FD52 00 E124 D 1377701D 056 1/24/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012N1062302300415 $0.31 000001081429-3562500610
2023 7 FD52 00 E124 D 1377701D 056 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300415 $0.04 000001081429-3562500610
2023 7 FD52 00 E111 D 1377701D 056 1/12/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR011N1062300610250 $798.12 000001081429-3562500610
2023 7 FD52 00 E111 D 1377701D 056 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610250 $456.44 000001081429-3562500610
2023 7 FD52 00 E121 D 1377701D 056 1/12/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR011N1062300610250 $61.08 000001081429-3562500610
2023 7 FD52 00 E121 D 1377701D 056 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610250 $34.92 000001081429-3562500610
2023 7 FD52 00 E122 D 1377701D 056 1/12/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR011N1062300610250 $622.66 000001081429-3562500610
2023 7 FD52 00 E122 D 1377701D 056 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610250 $356.02 000001081429-3562500610
2023 7 FD52 00 E123 D 1377701D 056 1/12/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR011N1062300610250 $22.57 000001081429-3562500610
2023 7 FD52 00 E123 D 1377701D 056 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610250 $11.83 000001081429-3562500610
2023 6 FD52 05 E143 D 1377701D 056 12/22/2022 0310 PROJECT DEVELOPMENT PRC-2300111980 PON22200002099 WSP USA INC $39,572.20 Letter Agreement 2
2023 6 FD52 05 E143 D 1377701D 056 12/22/2022 0310 PROJECT DEVELOPMENT PRC-2300113120 PON22200002099 WSP USA INC $24,823.90 Letter Agreement 2
2023 5 FD52 00 E111 D 1377701D 056 11/7/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111M1062230806156 $145.48 000001081429-3562500610
2023 5 FD52 00 E111 D 1377701D 056 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806156 $7.76 000001081429-3562500610
2023 5 FD52 00 E112 D 1377701D 056 11/7/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111M1062230806156 $1,154.64 000001081429-3562500610
2023 5 FD52 00 E112 D 1377701D 056 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806156 $115.46 000001081429-3562500610
2023 5 FD52 00 E121 D 1377701D 056 11/7/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111M1062230806156 $98.49 000001081429-3562500610
2023 5 FD52 00 E121 D 1377701D 056 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806156 $9.37 000001081429-3562500610
2023 5 FD52 00 E122 D 1377701D 056 11/7/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111M1062230806156 $113.47 000001081429-3562500610
2023 5 FD52 00 E122 D 1377701D 056 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806156 $6.05 000001081429-3562500610
2023 5 FD52 00 E123 D 1377701D 056 11/7/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111M1062230806156 $22.47 000001081429-3562500610
2023 5 FD52 00 E123 D 1377701D 056 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806156 $1.19 000001081429-3562500610
2023 4 FD52 00 E112 D 1377701D 056 10/24/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR102M1062229405048 $1,154.64 000001081429-3562500610
2023 4 FD52 00 E121 D 1377701D 056 10/24/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR102M1062229405048 $88.38 000001081429-3562500610
2023 4 FD52 00 E122 D 1377701D 056 10/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405048 $0.01 000001081429-3562500610
2023 4 FD52 05 E143 D 1377701D 056 10/13/2022 0310 PROJECT DEVELOPMENT PRC-2300063899 PON22200002099 WSP USA INC $67,086.90 Letter Agreement 2
2023 4 FD52 00 E111 D 1377701D 056 10/10/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101M1062228003937 $133.35 000001081429-3562500610
2023 4 FD52 00 E111 D 1377701D 056 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003937 $0.48 000001081429-3562500610
2023 4 FD52 00 E121 D 1377701D 056 10/10/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101M1062228003937 $9.14 000001081429-3562500610
2023 4 FD52 00 E121 D 1377701D 056 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003937 $0.04 000001081429-3562500610
2023 4 FD52 00 E122 D 1377701D 056 10/10/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101M1062228003937 $104.01 000001081429-3562500610
2023 4 FD52 00 E122 D 1377701D 056 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003937 $0.37 000001081429-3562500610
2023 4 FD52 00 E123 D 1377701D 056 10/10/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101M1062228003937 $20.59 000001081429-3562500610
2023 4 FD52 00 E123 D 1377701D 056 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003937 $0.07 000001081429-3562500610
2023 3 FD52 05 E143 D 1377701D 056 9/28/2022 0310 PROJECT DEVELOPMENT PRC-2300055061 PON22200002099 WSP USA INC $190,005.00 Letter Agreement 1
2023 3 FD52 05 E143 D 1377701D 056 9/14/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300046441 PON22200002246 AECOM TECHNICAL SERVICES, INC. $150,000.00 Jefferson Co. 5-20061
2023 3 FD52 05 E143 D 1377701D 056 9/14/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300046472 PON22200002246 AECOM TECHNICAL SERVICES, INC. $80,000.00 Jefferson Co. 5-20061
2023 3 FD52 05 E143 D 1377701D 056 9/14/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300046501 PON22200002246 AECOM TECHNICAL SERVICES, INC. $248,563.88 Jefferson Co. 5-20061
2023 2 FD52 00 E111 D 1377701D 056 8/10/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081M1062222110119 $480.13 000001081429-3562500610
2023 2 FD52 00 E111 D 1377701D 056 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110119 $53.34 000001081429-3562500610
2023 2 FD52 00 E121 D 1377701D 056 8/10/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081M1062222110119 $32.91 000001081429-3562500610
2023 2 FD52 00 E121 D 1377701D 056 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110119 $3.65 000001081429-3562500610
2023 2 FD52 00 E122 D 1377701D 056 8/10/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081M1062222110119 $374.45 000001081429-3562500610
2023 2 FD52 00 E122 D 1377701D 056 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110119 $41.60 000001081429-3562500610
2023 2 FD52 00 E123 D 1377701D 056 8/10/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR081M1062222110119 $74.18 000001081429-3562500610
2023 2 FD52 00 E123 D 1377701D 056 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110119 $8.17 000001081429-3562500610
2023 1 FD52 00 E112 D 1377701D 056 7/12/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071M1062219207878 $288.66 000001081429-3562500610
2023 1 FD52 00 E121 D 1377701D 056 7/12/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071M1062219207878 $22.09 000001081429-3562500610
2022 9 FD52 00 E111 D 1377701D 056 3/9/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031M1062206709471 $659.57 000001081429-3562500610
2022 9 FD52 00 E121 D 1377701D 056 3/9/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031M1062206709471 $48.29 000001081429-3562500610
2022 9 FD52 00 E122 D 1377701D 056 3/9/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031M1062206709471 $553.83 000001081429-3562500610
2022 9 FD52 00 E123 D 1377701D 056 3/9/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR031M1062206709471 $84.83 000001081429-3562500610
2022 8 FD52 00 E111 D 1377701D 056 2/9/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021M1062203907465 $970.74 000001081429-3562500610
2022 8 FD52 00 E111 D 1377701D 056 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907465 $223.21 000001081429-3562500610
2022 8 FD52 00 E121 D 1377701D 056 2/9/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021M1062203907465 $69.39 000001081429-3562500610
2022 8 FD52 00 E121 D 1377701D 056 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907465 $15.60 000001081429-3562500610
2022 8 FD52 00 E122 D 1377701D 056 2/9/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021M1062203907465 $815.02 000001081429-3562500610
2022 8 FD52 00 E122 D 1377701D 056 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907465 $187.43 000001081429-3562500610
2022 8 FD52 00 E123 D 1377701D 056 2/9/2022 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021M1062203907465 $150.18 000001081429-3562500610
2022 8 FD52 00 E123 D 1377701D 056 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907465 $36.90 000001081429-3562500610
2022 7 FD52 00 E111 D 1377701D 056 1/14/2022 0050 ENV STUDIES-TERRESTRIAL ECOL CA-XR011M1062200705559 $1,093.75 000001080861-3562500061
2022 7 FD52 00 E111 D 1377701D 056 1/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705559 $1,093.76 000001080861-3562500061
2022 7 FD52 00 E121 D 1377701D 056 1/14/2022 0050 ENV STUDIES-TERRESTRIAL ECOL CA-XR011M1062200705559 $82.66 000001080861-3562500061
2022 7 FD52 00 E121 D 1377701D 056 1/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705559 $82.65 000001080861-3562500061
2022 7 FD52 00 E122 D 1377701D 056 1/14/2022 0050 ENV STUDIES-TERRESTRIAL ECOL CA-XR011M1062200705559 $918.42 000001080861-3562500061
2022 7 FD52 00 E122 D 1377701D 056 1/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705559 $918.43 000001080861-3562500061
2022 7 FD52 00 E123 D 1377701D 056 1/14/2022 0050 ENV STUDIES-TERRESTRIAL ECOL CA-XR011M1062200705559 $179.31 000001080861-3562500061
2022 7 FD52 00 E123 D 1377701D 056 1/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705559 $174.21 000001080861-3562500061
2022 6 FD52 00 E122 D 1377701D 056 12/22/2021 0092 ENV STUDIES-PERMITTING CA-XR122L1062135504509 $198.56 000001080720-3562500061
2022 6 FD52 00 E122 D 1377701D 056 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504509 $19.86 000001080720-3562500061
2022 6 FD52 00 E123 D 1377701D 056 12/22/2021 0092 ENV STUDIES-PERMITTING CA-XR122L1062135504509 $53.49 000001080720-3562500061
2022 6 FD52 00 E123 D 1377701D 056 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504509 $5.30 000001080720-3562500061
2022 6 FD52 00 E124 D 1377701D 056 12/22/2021 0092 ENV STUDIES-PERMITTING CA-XR122L1062135504509 $0.09 000001080720-3562500061
2022 6 FD52 00 E124 D 1377701D 056 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504509 $0.01 000001080720-3562500061
2022 6 FD52 00 E111 D 1377701D 056 12/22/2021 0050 ENV STUDIES-TERRESTRIAL ECOL CA-XR122L1062135504515 $1,789.78 000001080861-3562500061
2022 6 FD52 00 E111 D 1377701D 056 12/22/2021 0092 ENV STUDIES-PERMITTING CA-XR122L1062135504509 $236.47 000001080720-3562500061
2022 6 FD52 00 E121 D 1377701D 056 12/22/2021 0050 ENV STUDIES-TERRESTRIAL ECOL CA-XR122L1062135504515 $135.28 000001080861-3562500061
2022 6 FD52 00 E111 D 1377701D 056 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504509 $23.65 000001080720-3562500061
2022 6 FD52 00 E122 D 1377701D 056 12/22/2021 0050 ENV STUDIES-TERRESTRIAL ECOL CA-XR122L1062135504515 $1,502.88 000001080861-3562500061
2022 6 FD52 00 E121 D 1377701D 056 12/22/2021 0092 ENV STUDIES-PERMITTING CA-XR122L1062135504509 $16.77 000001080720-3562500061
2022 6 FD52 00 E123 D 1377701D 056 12/22/2021 0050 ENV STUDIES-TERRESTRIAL ECOL CA-XR122L1062135504515 $282.29 000001080861-3562500061
2022 6 FD52 00 E121 D 1377701D 056 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504509 $1.68 000001080720-3562500061
2022 6 FD52 00 E124 D 1377701D 056 12/22/2021 0050 ENV STUDIES-TERRESTRIAL ECOL CA-XR122L1062135504515 $0.82 000001080861-3562500061
2022 6 FD52 00 E111 D 1377701D 056 12/8/2021 0092 ENV STUDIES-PERMITTING CA-XR121L1062134103575 $236.40 000001080720-3562500061
2022 6 FD52 00 E111 D 1377701D 056 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103575 $52.65 000001080720-3562500061
2022 6 FD52 00 E121 D 1377701D 056 12/8/2021 0092 ENV STUDIES-PERMITTING CA-XR121L1062134103575 $16.46 000001080720-3562500061
2022 6 FD52 00 E121 D 1377701D 056 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103575 $3.66 000001080720-3562500061
2022 6 FD52 00 E122 D 1377701D 056 12/8/2021 0092 ENV STUDIES-PERMITTING CA-XR121L1062134103575 $198.57 000001080720-3562500061
2022 6 FD52 00 E122 D 1377701D 056 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103575 $44.21 000001080720-3562500061
2022 6 FD52 00 E123 D 1377701D 056 12/8/2021 0092 ENV STUDIES-PERMITTING CA-XR121L1062134103575 $53.55 000001080720-3562500061
2022 6 FD52 00 E123 D 1377701D 056 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103575 $11.80 000001080720-3562500061
2022 3 FD52 00 E111 D 1377701D 056 9/27/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092L1062126709073 $335.86 000001079749-3562500636
2022 3 FD52 00 E111 D 1377701D 056 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709073 $146.01 000001079749-3562500636
2022 3 FD52 00 E121 D 1377701D 056 9/27/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092L1062126709073 $25.31 000001079749-3562500636
2022 3 FD52 00 E121 D 1377701D 056 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709073 $11.01 000001079749-3562500636
2022 3 FD52 00 E122 D 1377701D 056 9/27/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092L1062126709073 $282.02 000001079749-3562500636
2022 3 FD52 00 E122 D 1377701D 056 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709073 $122.60 000001079749-3562500636
2022 3 FD52 00 E123 D 1377701D 056 9/27/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092L1062126709073 $39.21 000001079749-3562500636
2022 3 FD52 00 E123 D 1377701D 056 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709073 $16.68 000001079749-3562500636
2022 3 FD52 00 E124 D 1377701D 056 9/27/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092L1062126709073 $0.12 000001079749-3562500636
2022 3 FD52 00 E124 D 1377701D 056 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709073 $0.06 000001079749-3562500636