PROJECT AUTHORIZATION | PACKET ID: PMT-93EY |
CONTRACT ID | EMARS PROGRAM CODE | AUTHORIZATION NO: | |
6780812R | 67808 | 31 | |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID | PROJECT ID NUMBER | FEDERAL PROJECT NUMBER | 6 YR PLAN ITEM NUMBER | 6 YR PLAN ITEM PARENT NUMBER |
100 046 1 000-0 |
NHPP 4611 009 |
08-00059 |
PROJECT TYPE | PROJECT LENGTH | NUMBER OF BRIDGES | SYSTEMS |
NEW ROUTE | MI |
PROJECT PHASE & RESPONSIBILITY |
PLANNING | DESIGN | RIGHT OF WAY | UTILITIES |
CONSTRUCTION | TITLE DEEDED TO: | MAINTENANCE | OTHER | |
FUNDING & TIME ACCOUNTABILITY |
PARTICIPATING AGENCIES | |||||||
FEDERAL | STATE | DOH | LOCAL | OTHER |
ITEM NUMBER | PHASE | FUND | PROGRAM | FEDERAL FISCAL YEAR | STATE FISCAL YEAR |
||
FEDERAL APPR CODE |
CURRENT FUNDING REQUEST | ||||||
8-59.25 | R | 1100 | FD52 | 2020 | $3,000,000.00 | ||
CURRENT FUNDING REQUEST TOTAL: $3,000,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE | TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING | $0.00 |
DESIGN | $29,591,359.00 |
UTILITIES | $11,395,928.00 |
R/W | $39,129,700.00 |
CONSTRUCTION | $60,915,888.00 |
NON-HIGHWAYS | $0.00 |
Total: $141,032,875.00 |
REMARKS: | THIS AUTHORIZATION PROVIDES ADDITIONAL $3,000,000 STATE FUNDS TO PROGRAM CODE 6780812R TO COVER EXPENSES FOR CELL TOWER, LIFT STATION, FIBER OPTIC HUT, PURCHASING AN ADDITIONAL HOME NOT SHOWN ON ORIGINAL R/W PLANS. STATE FUNDS WERE RELEASED FROM 8-136 PROGRAM CODE 7796602R, 8-108 PROGRAM CODE 6980501R, AND 8-108 PROGRAM CODE 6980501U TO HELP OFFSET THIS COST. |
Project Approval Recommended By: John Moore 2/28/2020 |
Signed and Approved by: Andy Barber 3/4/2020 |
AUTHORIZATION LOCATION | ||||||
ITEM NO. | COUNTY | DIST | FACILITY NAME |
ROUTE | LENGTH | SCOPE |
08-00059.25 | PULASKI
|
8 | KY-80 HAL ROGERS PKWY,KY-80 HA | MI | IMPROVE KY-461 FROM KY-80 TO BUCK CREEK BRIDGE, INCLUDING INTERCHANGE AT KY-80. (18CCR) |