|
PROJECT AUTHORIZATION |
PACKET ID: PMT-VKYW |
CONTRACT ID |
EMARS PROGRAM CODE |
AUTHORIZATION NO: |
|
1746501D |
17465 |
0 |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID |
PROJECT ID NUMBER |
FEDERAL PROJECT NUMBER |
6 YR PLAN ITEM NUMBER |
6 YR PLAN ITEM PARENT NUMBER |
|
056 006 4 017-018 |
0642202
|
05-10057 |
5-.- |
PROJECT TYPE |
PROJECT LENGTH |
NUMBER OF BRIDGES |
SYSTEMS |
|
0.0300 MI |
|
|
PROJECT PHASE
&
RESPONSIBILITY |
PLANNING |
DESIGN |
RIGHT OF WAY |
UTILITIES |
|
DOH/CONSULT |
|
|
CONSTRUCTION |
TITLE DEEDED TO: |
MAINTENANCE |
OTHER |
|
|
|
|
FUNDING & TIME
ACCOUNTABILITY |
PARTICIPATING AGENCIES |
FEDERAL |
FHWA |
STATE |
DOH |
LOCAL |
|
OTHER |
|
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER |
PHASE |
FUND |
PROGRAM |
FEDERAL FISCAL YEAR |
STATE FISCAL YEAR
|
FEDERAL APPR
CODE |
CURRENT FUNDING REQUEST |
5-10057 |
D |
1200 |
FD52 |
2024 |
2024 |
Y001 |
$468,000.00 |
5-10057 |
D |
1100 |
FD52 |
2024 |
2024 |
Y001 |
$52,000.00 |
CURRENT FUNDING REQUEST TOTAL: $520,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE |
TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING |
$0.00 |
DESIGN |
$520,000.00 |
UTILITIES |
$0.00 |
R/W |
$0.00 |
CONSTRUCTION |
$0.00 |
NON-HIGHWAYS |
$0.00 |
|
Total: $520,000.00 |
THIS AUTHORIZATION PROVIDES INITIAL FD52 NHPP FUNDS WITH STATE MATCHING FUNDS FOR PE AND ENVIRONMENTAL. |
|
Project Approval Recommended By:
James Ballinger 11/3/2023 |
Signed and Approved by:
Jim Gray 11/6/2023 |
ITEM NO. |
COUNTY |
DIST |
FACILITY NAME
|
ROUTE |
LENGTH |
05-10057.00 |
JEFFERSON
|
5 |
I-64 |
I 64 |
0.0300 MI |
BRIDGE PROJECT IN JEFFERSON COUNTY ON (056B00039L & 056B00039R) I-64 AT TUCKER STATION RD |