PROJECT AUTHORIZATION |
PACKET ID: PMT-D3K9 |
CONTRACT ID |
EMARS PROGRAM CODE |
AUTHORIZATION NO: |
|
1624801D |
16248 |
0 |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID |
PROJECT ID NUMBER |
FEDERAL PROJECT NUMBER |
6 YR PLAN ITEM NUMBER |
6 YR PLAN ITEM PARENT NUMBER |
|
006 006 0 008-010 |
|
09-80250 |
|
PROJECT TYPE |
PROJECT LENGTH |
NUMBER OF BRIDGES |
SYSTEMS |
|
0.8000 MI |
|
|
PROJECT PHASE
&
RESPONSIBILITY |
PLANNING |
DESIGN |
RIGHT OF WAY |
UTILITIES |
|
|
|
|
CONSTRUCTION |
TITLE DEEDED TO: |
MAINTENANCE |
OTHER |
|
|
|
|
FUNDING & TIME
ACCOUNTABILITY |
PARTICIPATING AGENCIES |
FEDERAL |
|
STATE |
DOH |
LOCAL |
|
OTHER |
|
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER |
PHASE |
FUND |
PROGRAM |
FEDERAL FISCAL YEAR |
STATE FISCAL YEAR
|
FEDERAL APPR
CODE |
CURRENT FUNDING REQUEST |
9-80250 |
D |
1100 |
FD04 |
|
2023 |
|
$500,000.00 |
CURRENT FUNDING REQUEST TOTAL: $500,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE |
TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING |
$0.00 |
DESIGN |
$500,000.00 |
UTILITIES |
$0.00 |
R/W |
$0.00 |
CONSTRUCTION |
$0.00 |
NON-HIGHWAYS |
$0.00 |
|
Total: $500,000.00 |
THIS AUTHORIZATION PROVIDES $500,000 FD04 FUNDS FOR PE & ENVIRONMENTAL (PARTIAL DESIGN AUTHORIZATION). |
|
Project Approval Recommended By:
James Ballinger 3/3/2023 |
Signed and Approved by:
Jim Gray 3/6/2023 |
ITEM NO. |
COUNTY |
DIST |
FACILITY NAME
|
ROUTE |
LENGTH |
09-80250.00 |
BATH
|
9 |
US-60 |
US 60 |
0.8000 MI |
REALIGN ROADWAY ON US 60 NEAR OWINGSVILLE BEGINNING IN THE VICINITY OF ROSE BUSH LN AND ENDING AT WELLS ROAD NEAR I 64 EXIT 123 (2022CCN) |