PROJECT AUTHORIZATION PACKET ID: PMT-3A7R
CONTRACT ID EMARS PROGRAM CODE AUTHORIZATION NO:
1209901R      12099 10
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized.
PROJECT ID PROJECT ID NUMBER FEDERAL PROJECT NUMBER 6 YR PLAN ITEM NUMBER 6 YR PLAN ITEM PARENT NUMBER


8149003

06-01086 6-.-
PROJECT TYPE PROJECT LENGTH NUMBER OF BRIDGES SYSTEMS
MINOR BRIDGE REHAB 0.2520 MI
PROJECT PHASE
&
RESPONSIBILITY
PLANNING DESIGN RIGHT OF WAY UTILITIES
CONSTRUCTION TITLE DEEDED TO: MAINTENANCE OTHER
FUNDING & TIME
ACCOUNTABILITY
PARTICIPATING AGENCIES
FEDERAL STATE LOCAL OTHER
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER PHASE FUND PROGRAM FEDERAL FISCAL YEAR STATE FISCAL YEAR
FEDERAL APPR
CODE
CURRENT FUNDING REQUEST
6-1086 R 1100 FD04 2025 $2,855,000.00
CURRENT FUNDING REQUEST TOTAL: $2,855,000.00
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES
PHASE TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST)
PLANNING $0.00
DESIGN $10,444,000.00
UTILITIES $0.00
R/W $3,705,000.00
CONSTRUCTION $0.00
NON-HIGHWAYS $0.00
  Total: $14,149,000.00
REMARKS: THIS MODIFICATION PROVIDES ADDITIONAL RIGHT OF WAY FUNDS FOR THE PROJECT. (2 PARCELS FOR EARLY ACQUISITION). FUNDING FOR THE R/W PHASE OF THIS PROJECT IS PART OF THE “ADVANCE ACQUISITION OF R/W” PROGRAM TEMPORARILY USING STATE FUNDS, AND THE R/W PHASE WILL BE PROGRAMMED FOR REIMBURSEMENT OF FEDERAL FUNDING UPON COMPLETION OF THE PROJECT ENVIRONMENTAL DOCUMENT.
 
Project Approval Recommended By:
James Ballinger   9/13/2024
Signed and Approved by:
Jim Gray   9/16/2024
AUTHORIZATION LOCATION
ITEM NO. COUNTY DIST FACILITY NAME
ROUTE LENGTH SCOPE
06-01086.00 KENTON


6 W 4TH ST W 3RD ST INDUSTRIAL R KY 8 0.2520 MI ADDRESS DEFICIENCIES OF BRIDGE OVER LICKING RIVER ON WEST 4TH STREET (KY 8) IN COVINGTON/NEWPORT AT KENTON/CAMPBELL CO LN. (059B00037N) *CAMPBELL CO MPS ARE 0.0-0.19 (2020CCR)