Authorized to Date = $25,933,750.00
Route County Requested Amount Auth# and Mod Level Authorization Date Remarks Facility Name
NEW CONNECTOR RD CAMPBELL $0.00 76970 - 15 6/16/2025 THIS MODIFICATION CORRECTS PREVIOUS FD52 STP FUNDS WITH STATE MATCHING FUNDS TO FD52 1100 'NON-PARTICIPATING' FUNDS FOR DESIGN. (01D - $170,000 & 03D - $15,000)  
NEW CONNECTOR RD CAMPBELL $185,000.00 76970 - 14 6/2/2025 THIS MODIFICATION PROVIDES ADDITIONAL FD52 STP FUNDS WITH STATE MATCHING FUNDS TO COVER CURRENT DESIGN EXPENDITURES.  
NEW CONNECTOR RD CAMPBELL $350,000.00 76970 - 13 4/3/2025 THIS MODIFICATION PROVIDES ADDITIONAL FD52 STP FUNDS WITH STATE MATCHING FUNDS FOR DESIGN.  
NEW CONNECTOR RD CAMPBELL $6,214,000.00 76970 - 12 4/20/2023 THIS AUTHORIZATION PROVIDES ADDITIONAL RIGHT OF WAY FUNDS FOR THE PROJECT. (26 PARCELS, 11 RESIDENTIAL RELOCATIONS, 1 MISC. RELOCATION)  
NEW CONNECTOR RD CAMPBELL $250,000.00 76970 - 11 4/14/2023 THIS MODIFICATION PROVIDES ADDITIONAL DESIGN FUNDS FOR ENVIONMENTAL REASSESSMENT, RIGHT OF WAY REVSIONS, AND PLAN REVIEW FOR 6-8105.07  
NEW CONNECTOR RD CAMPBELL $210,000.00 76970 - 10 6/8/2017 THIS MOD. PROVIDES ADDITIONAL CONSTRUCTION FUNDS TO COVER CHANGE ORDER #1 ($186,899.25), ROADWAY LIGHTING AT TWO ROUND-ABOUTS PLUS ENGINEERING.  
NEW CONNECTOR RD CAMPBELL $25,000.00 76970 - 9 1/19/2017 THIS MODIFICATION PROVIDES ADDITIONAL DESIGN FUNDS TO COVER UTILITY ENGINEERING SERVICES AGREEMENT EXECUTION. LC  
NEW CONNECTOR RD CAMPBELL $2,419,600.00 76970 - 8 1/4/2016 THIS MODIFICATION ADJUSTS PREVIOUSLY AUTHORIZED CONSTRUCTION FUNDS TO COVER THE LOW BID PLUS 10% FOR ENGINEERING.  
NEW CONNECTOR RD CAMPBELL $250,000.00 76970 - 7 12/4/2015 THIS MODIFICATION PROVIDES ADDITIONAL DESIGN FUNDS FOR THE PROJECT. LC  
NEW CONNECTOR RD CAMPBELL $9,280,000.00 76970 - 6 11/16/2015 THIS AUTHORIZATION PROVIDES CONSTRUCTION FUNDS BASED ON THE CURRENT ESTIMATE PRIOR TO THE PROJECT BEING LET.  
NEW CONNECTOR RD CAMPBELL $1,650,000.00 76970 - 5 2/11/2015 THIS MODIFICATION PROVIDES ADDITIONAL RIGHT-OF-WAY FUNDS FOR SECTION 2. (4 PARCELS) (JOHNS HILL RD TO THREE MILE RD THROUGH NKU CAMPUS) OF THE PROJECT. TJ  
NEW CONNECTOR RD CAMPBELL $1,809,000.00 76970 - 4 7/3/2014 THIS AUTHORIZATION PROVIDES INITIAL UTILITY FUNDS (6 ADJUSTMENTS)FOR SECTION 2 (JOHNS HILL RD TO THREE MILE RD THROUGH NKU CAMPUS) OF THE PROJECT. THIS MODIFICATION PROVIDES ADDITIONAL DESIGN FUNDS TO COVER FINAL DESIGN WORK.  
NEW CONNECTOR RD CAMPBELL $1,000,000.00 76970 - 3 4/10/2013 THIS AUTHORIZATION PROVIDES INITIAL RIGHT OF WAY FUNDS (4 PARCELS)FOR THE PROJECT. FUNDING FOR THE R/W PHASE OF THIS PROJECT IS PART OF THE “ADVANCE ACQUISITION OF R/W” PROGRAM TEMPORARILY USING STATE FUNDS, AND THE R/W PHASE WILL BE PROGRAMMED FOR REIMBURSEMENT OF FEDERAL FUNDING UPON COMPLETION OF THE PROJECT ENVIRONMENTAL DOCUMENT. TJ.  
NEW CONNECTOR RD CAMPBELL $400,000.00 76970 - 2 12/1/2011 THIS MOD. PROVIDES DESIGN FUNDS FOR ADDITIONAL CONSULTANT SERVICES NECESSARY FOR FINAL PLANS AND STATE FORCE GEOTECHNICAL ACTIVITIES AND PROJECT MANAGEMENT.  
NEW CONNECTOR RD CAMPBELL $400,000.00 76970 - 1 12/15/2006 THIS MODIFICATION PROVIDES SAFETEA-LU 'HPP' FUNDING ALLOCATED FOR THIS PROJECT FOR DESIGN OF TRANSPORTATION IMPROVEMENTS TO THE AA - I-275 CONNECTOR. TOLL CREDITS WILL BE USED IN LIEU OF THE STATE MATCHING FUNDS. BA  
NEW CONNECTOR RD CAMPBELL $1,491,150.00 76970 - 0 9/10/2004 THIS AUTHORIZATION PROVIDES FEDERAL "SECTION 115" FUNDS ALLOCATED FOR THIS THIS PROJECT. NO STATE MATCHING FUNDS ARE REQUIRED.