NEW CONNECTOR RD |
CAMPBELL |
$0.00 |
76970 - 15 |
6/16/2025 |
THIS MODIFICATION CORRECTS PREVIOUS FD52 STP FUNDS WITH STATE MATCHING FUNDS TO FD52 1100 'NON-PARTICIPATING' FUNDS FOR DESIGN. (01D - $170,000 & 03D - $15,000) |
|
NEW CONNECTOR RD |
CAMPBELL |
$185,000.00 |
76970 - 14 |
6/2/2025 |
THIS MODIFICATION PROVIDES ADDITIONAL FD52 STP FUNDS WITH STATE MATCHING FUNDS TO COVER CURRENT DESIGN EXPENDITURES. |
|
NEW CONNECTOR RD |
CAMPBELL |
$350,000.00 |
76970 - 13 |
4/3/2025 |
THIS MODIFICATION PROVIDES ADDITIONAL FD52 STP FUNDS WITH STATE MATCHING FUNDS FOR DESIGN. |
|
NEW CONNECTOR RD |
CAMPBELL |
$6,214,000.00 |
76970 - 12 |
4/20/2023 |
THIS AUTHORIZATION PROVIDES ADDITIONAL RIGHT OF WAY FUNDS FOR THE PROJECT. (26 PARCELS, 11 RESIDENTIAL RELOCATIONS, 1 MISC. RELOCATION) |
|
NEW CONNECTOR RD |
CAMPBELL |
$250,000.00 |
76970 - 11 |
4/14/2023 |
THIS MODIFICATION PROVIDES ADDITIONAL DESIGN FUNDS FOR ENVIONMENTAL REASSESSMENT, RIGHT OF WAY REVSIONS, AND PLAN REVIEW FOR 6-8105.07 |
|
NEW CONNECTOR RD |
CAMPBELL |
$210,000.00 |
76970 - 10 |
6/8/2017 |
THIS MOD. PROVIDES ADDITIONAL CONSTRUCTION FUNDS TO COVER CHANGE ORDER #1 ($186,899.25), ROADWAY LIGHTING AT TWO ROUND-ABOUTS PLUS ENGINEERING. |
|
NEW CONNECTOR RD |
CAMPBELL |
$25,000.00 |
76970 - 9 |
1/19/2017 |
THIS MODIFICATION PROVIDES ADDITIONAL DESIGN FUNDS TO COVER UTILITY ENGINEERING SERVICES AGREEMENT EXECUTION. LC |
|
NEW CONNECTOR RD |
CAMPBELL |
$2,419,600.00 |
76970 - 8 |
1/4/2016 |
THIS MODIFICATION ADJUSTS PREVIOUSLY AUTHORIZED CONSTRUCTION FUNDS TO COVER THE LOW BID PLUS 10% FOR ENGINEERING. |
|
NEW CONNECTOR RD |
CAMPBELL |
$250,000.00 |
76970 - 7 |
12/4/2015 |
THIS MODIFICATION PROVIDES ADDITIONAL DESIGN FUNDS FOR THE PROJECT. LC |
|
NEW CONNECTOR RD |
CAMPBELL |
$9,280,000.00 |
76970 - 6 |
11/16/2015 |
THIS AUTHORIZATION PROVIDES CONSTRUCTION FUNDS BASED ON THE CURRENT ESTIMATE PRIOR TO THE PROJECT BEING LET. |
|
NEW CONNECTOR RD |
CAMPBELL |
$1,650,000.00 |
76970 - 5 |
2/11/2015 |
THIS MODIFICATION PROVIDES ADDITIONAL RIGHT-OF-WAY FUNDS FOR SECTION 2. (4 PARCELS) (JOHNS HILL RD TO THREE MILE RD THROUGH NKU CAMPUS) OF THE PROJECT. TJ |
|
NEW CONNECTOR RD |
CAMPBELL |
$1,809,000.00 |
76970 - 4 |
7/3/2014 |
THIS AUTHORIZATION PROVIDES INITIAL UTILITY FUNDS (6 ADJUSTMENTS)FOR SECTION 2 (JOHNS HILL RD TO THREE MILE RD THROUGH NKU CAMPUS) OF THE PROJECT. THIS MODIFICATION PROVIDES ADDITIONAL DESIGN FUNDS TO COVER FINAL DESIGN WORK. |
|
NEW CONNECTOR RD |
CAMPBELL |
$1,000,000.00 |
76970 - 3 |
4/10/2013 |
THIS AUTHORIZATION PROVIDES INITIAL RIGHT OF WAY FUNDS (4 PARCELS)FOR THE PROJECT. FUNDING FOR THE R/W PHASE OF THIS PROJECT IS PART OF THE “ADVANCE ACQUISITION OF R/W” PROGRAM TEMPORARILY USING STATE FUNDS, AND THE R/W PHASE WILL BE PROGRAMMED FOR REIMBURSEMENT OF FEDERAL FUNDING UPON COMPLETION OF THE PROJECT ENVIRONMENTAL DOCUMENT. TJ. |
|
NEW CONNECTOR RD |
CAMPBELL |
$400,000.00 |
76970 - 2 |
12/1/2011 |
THIS MOD. PROVIDES DESIGN FUNDS FOR ADDITIONAL CONSULTANT SERVICES NECESSARY FOR FINAL PLANS AND STATE FORCE GEOTECHNICAL ACTIVITIES AND PROJECT MANAGEMENT. |
|
NEW CONNECTOR RD |
CAMPBELL |
$400,000.00 |
76970 - 1 |
12/15/2006 |
THIS MODIFICATION PROVIDES SAFETEA-LU 'HPP' FUNDING ALLOCATED FOR THIS PROJECT FOR DESIGN OF TRANSPORTATION IMPROVEMENTS TO THE AA - I-275 CONNECTOR. TOLL CREDITS WILL BE USED IN LIEU OF THE STATE MATCHING FUNDS. BA |
|
NEW CONNECTOR RD |
CAMPBELL |
$1,491,150.00 |
76970 - 0 |
9/10/2004 |
THIS AUTHORIZATION PROVIDES FEDERAL "SECTION 115" FUNDS ALLOCATED FOR THIS THIS PROJECT. NO STATE MATCHING FUNDS ARE REQUIRED. |
|