Route | County | Requested Amount | Auth# and Mod Level | Authorization Date | Remarks | Facility Name |
JOHNSON COUNTY ACCESS ROAD | JOHNSON | $1,200,000.00 | 16049 - 1 | 9/16/2024 | THIS AUTHORIZATION OBLIGATES $750,000 (FD04) FUNDS FOR THE RIGHT OF WAY PHASE AND $450,000 (FD04) FUNDS FOR THE UTILITY PHASE OF THE PROJECT. | |
JOHNSON COUNTY ACCESS ROAD | JOHNSON | $1,500,000.00 | 16049 - 0 | 12/21/2022 | THIS AUTHORIZATION PROVIDES $1,500,000 STATE FD04 FUNDS TO BEGIN DESIGN ACTIVITIES ON THE PROJECT. |