Highway Plan Phase Info
Phase Funding FY Amount
Right of way SPP 2026 $3,500,000.00
Utility Relocation SPP 2028 $750,000.00
Construction SPP 2029 $10,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D SPP $0.00 2026 AUTHORIZED 3/6/2023 $500,000.00
R SPP $1,650,000.00 2027 ESTIMATED $0.00
U SPP $1,200,000.00 2027 ESTIMATED $0.00
C SPP $10,000,000.00 2029 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 16248 1624801D $500,000.00 $0.00 $527,499.78 $0.00 $11,409.23
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: REALIGN ROADWAY ON US 60 NEAR OWINGSVILLE BEGINNING IN THE VICINITY OF ROSE BUSH LN AND ENDING AT WELLS ROAD NEAR I 64 EXIT 123 (2022CCN) (2024CCR)
Location:
Route 1 Bath County US-60 from MP 8.4 to MP 9.2
Route 2 County - from MP to MP
Item #: 9-80250.00
Project Manager: KYTC\MICHAEL.READ
Road Engineer:
Type of Work: REALIGNMENT
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\MICHAEL.READ       Item #: 9-80250.00
Project Description: REALIGN ROADWAY ON US 60 NEAR OWINGSVILLE BEGINNING IN THE VICINITY OF ROSE BUSH LN AND ENDING AT WELLS ROAD NEAR I 64 EXIT 123 (2022CCN) (2024CCR)

Milestones
Milestones Status Status Date Scheduled
Final Design 04/30/2024
Preliminary Engineering 04/30/2024
RR Engineering Agreement 04/30/2024
Structure Plans 04/30/2024
Planning Funding 04/30/2024
Environmental Approval 04/30/2024
FHWA Scope Verification Meeting 04/30/2024
Utility Agreement 04/30/2024
Final Design Notice to Proceed 04/30/2024
Pavement Design 04/30/2024
Additional Design Funding 04/30/2024
RR Real Estate 04/30/2024
Right of Way Consultant Notice to Proceed 04/30/2024
Funding for Preliminary Engineering 04/30/2024
Traffic Management Plan 04/30/2024
ROW Clearance 04/30/2024
Traffic Lighting Plans 04/30/2024
Planning Study and Reports 04/30/2024
Design Executive Summary 04/30/2024
Additional Design Funding 04/30/2024
Railroad Clearance 04/30/2024
Joint Inspection Meeting 04/30/2024
Drainage Inspection 04/30/2024
Advertisement 04/30/2024
Planning 04/30/2024
Check Prints 04/30/2024
Letting 04/30/2024
Preliminary Engineering Notice to Proceed 04/30/2024
Right of Way Acquisition 04/30/2024
Final Plans Submittal 04/30/2024
Roadway Plans 04/30/2024
Traffic Control Electrical Device Plans 04/30/2024
Right of Way Plans 04/30/2024
Signing Plans 04/30/2024
Utility Clearance 04/30/2024
Right of Way Inspection 04/30/2024
PS&E 04/30/2024
Geotechnical - Roadway Design Investigation 04/30/2024
Highway Drainage Design 04/30/2024
Alternative Selection 04/30/2024
Traffic Signals Plans 04/30/2024
 
Project Manager: KYTC\MICHAEL.READ       Item #: 9-80250.00
Project Description: REALIGN ROADWAY ON US 60 NEAR OWINGSVILLE BEGINNING IN THE VICINITY OF ROSE BUSH LN AND ENDING AT WELLS ROAD NEAR I 64 EXIT 123 (2022CCN) (2024CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
CE LVL 2 11/8/2023 6/1/2025

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\MICHAEL.READ       Item #: 9-80250.00
Project Description: REALIGN ROADWAY ON US 60 NEAR OWINGSVILLE BEGINNING IN THE VICINITY OF ROSE BUSH LN AND ENDING AT WELLS ROAD NEAR I 64 EXIT 123 (2022CCN) (2024CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 9-80250.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\MICHAEL.READ       Item #: 9-80250.00
Project Description: REALIGN ROADWAY ON US 60 NEAR OWINGSVILLE BEGINNING IN THE VICINITY OF ROSE BUSH LN AND ENDING AT WELLS ROAD NEAR I 64 EXIT 123 (2022CCN) (2024CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\MICHAEL.READ       Item #: 9-80250.00
Project Description: REALIGN ROADWAY ON US 60 NEAR OWINGSVILLE BEGINNING IN THE VICINITY OF ROSE BUSH LN AND ENDING AT WELLS ROAD NEAR I 64 EXIT 123 (2022CCN) (2024CCR)
This Project has no Vendors Assigned.