Highway Plan Phase Info
Phase Funding FY Amount
Design STP 2023 $1,000,000.00
Right of way STP 2024 $1,501,000.00
Utility Relocation STP 2025 $748,800.00
Construction STP 2026 $6,899,200.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D STP $0.00 2023 AUTHORIZED 7/6/2022 $800,000.00
R STP $1,501,000.00 2024 ESTIMATED $0.00
U STP $748,800.00 2025 ESTIMATED $0.00
C STP $6,899,200.00 2026 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 15275 1527501D $800,000.00 $0.00 $0.00 $0.00 $800,000.00
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: Construct a two lane roadway from KY 3297 to the intersection of US 60 and KY 1 to mitigate congestion along Carol Malone Boulevard. (Phase III of proposed bypass project.) (2022CCN)
Location:
Route 1 Carter County PF-9999 from MP to MP
Route 2 22 County US - from MP 23.8 to MP 24.760
Item #: 9-80202.00
Project Manager: KYTC\MICHAEL.READ
Road Engineer:
Type of Work: NEW ROUTE(O)
Concerns:
Bridge Engineer:
Bridge Structure Number: 022B00063N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 63
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\MICHAEL.READ       Item #: 9-80202.00
Project Description: Construct a two lane roadway from KY 3297 to the intersection of US 60 and KY 1 to mitigate congestion along Carol Malone Boulevard. (Phase III of proposed bypass project.) (2022CCN)

This Project has no Milesones defined.
Project Manager: KYTC\MICHAEL.READ       Item #: 9-80202.00
Project Description: Construct a two lane roadway from KY 3297 to the intersection of US 60 and KY 1 to mitigate congestion along Carol Malone Boulevard. (Phase III of proposed bypass project.) (2022CCN)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
Preliminary 5/31/2022

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\MICHAEL.READ       Item #: 9-80202.00
Project Description: Construct a two lane roadway from KY 3297 to the intersection of US 60 and KY 1 to mitigate congestion along Carol Malone Boulevard. (Phase III of proposed bypass project.) (2022CCN)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 9-80202.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\MICHAEL.READ       Item #: 9-80202.00
Project Description: Construct a two lane roadway from KY 3297 to the intersection of US 60 and KY 1 to mitigate congestion along Carol Malone Boulevard. (Phase III of proposed bypass project.) (2022CCN)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\MICHAEL.READ       Item #: 9-80202.00
Project Description: Construct a two lane roadway from KY 3297 to the intersection of US 60 and KY 1 to mitigate congestion along Carol Malone Boulevard. (Phase III of proposed bypass project.) (2022CCN)
This Project has no Vendors Assigned.