Highway Plan Phase Info
Phase Funding FY Amount
Planning SPP 2024 $1,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
P SPP $1,000,000.00 2023 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: CONDUCT A PLANNING STUDY TO ASSES HOW TO FURTHER MITIGATE ROCKSLIDE DAMAGE ON KY 300 (2022CCN) (2024CCR)
Location:
Route 1 Lincoln County KY-300 from MP 3.75 to MP 3.95
Route 2 County - from MP to MP
Item #: 8-80202.00
Project Manager: KYTC\JOSEPH.GOSSAGE
Road Engineer:
Type of Work: PLANNING-OKI(O)
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-80202.00
Project Description: CONDUCT A PLANNING STUDY TO ASSES HOW TO FURTHER MITIGATE ROCKSLIDE DAMAGE ON KY 300 (2022CCN) (2024CCR)

This Project has no Milesones defined.
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-80202.00
Project Description: CONDUCT A PLANNING STUDY TO ASSES HOW TO FURTHER MITIGATE ROCKSLIDE DAMAGE ON KY 300 (2022CCN) (2024CCR)
Authoritative Source for Environmental Data:  EATS
This Project has no Environmental data.

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-80202.00
Project Description: CONDUCT A PLANNING STUDY TO ASSES HOW TO FURTHER MITIGATE ROCKSLIDE DAMAGE ON KY 300 (2022CCN) (2024CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 8-80202.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-80202.00
Project Description: CONDUCT A PLANNING STUDY TO ASSES HOW TO FURTHER MITIGATE ROCKSLIDE DAMAGE ON KY 300 (2022CCN) (2024CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-80202.00
Project Description: CONDUCT A PLANNING STUDY TO ASSES HOW TO FURTHER MITIGATE ROCKSLIDE DAMAGE ON KY 300 (2022CCN) (2024CCR)
This Project has no Vendors Assigned.