Highway Plan Phase Info
Phase Funding FY Amount
Right of way SPP 2025 $6,300,000.00
Utility Relocation SPP 2026 $2,270,000.00
Construction SPP 2026 $21,280,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D SPP $0.00 2024 AUTHORIZED 7/26/2021 $1,406,000.00
R SPP $6,000,000.00 2025 ESTIMATED $0.00
U SPP $2,100,000.00 2026 ESTIMATED $0.00
C SPP $19,000,000.00 2027 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 13534 1353401D $1,406,000.00 $0.00 $886,252.10 $164,233.36 $364,913.85
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: REDUCE CONGESTION AND IMPROVE SAFETY, CAPACITY AND MOBILIITY ALONG KY 90 BETWEEN WAYNE COUNTY LINE AND NEW CUMBERLAND RIVER BRIDGE (2020CCN) (2022CCR) (2024CCR)
Location:
Route 1 Pulaski County KY-90 from MP 0 to MP 3.061
Route 2 County - from MP to MP
Item #: 8-80104.00
Project Manager: KYTC\JOSEPH.GOSSAGE
Road Engineer:
Type of Work: CONGESTION MITIGATION
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-80104.00
Project Description: REDUCE CONGESTION AND IMPROVE SAFETY, CAPACITY AND MOBILIITY ALONG KY 90 BETWEEN WAYNE COUNTY LINE AND NEW CUMBERLAND RIVER BRIDGE (2020CCN) (2022CCR) (2024CCR)

This Project has no Milesones defined.
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-80104.00
Project Description: REDUCE CONGESTION AND IMPROVE SAFETY, CAPACITY AND MOBILIITY ALONG KY 90 BETWEEN WAYNE COUNTY LINE AND NEW CUMBERLAND RIVER BRIDGE (2020CCN) (2022CCR) (2024CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
District Office CE LVL 1 11/14/2022 Lochner H. W., Inc. 11/21/2022 9/5/2023

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-80104.00
Project Description: REDUCE CONGESTION AND IMPROVE SAFETY, CAPACITY AND MOBILIITY ALONG KY 90 BETWEEN WAYNE COUNTY LINE AND NEW CUMBERLAND RIVER BRIDGE (2020CCN) (2022CCR) (2024CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 8-80104.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-80104.00
Project Description: REDUCE CONGESTION AND IMPROVE SAFETY, CAPACITY AND MOBILIITY ALONG KY 90 BETWEEN WAYNE COUNTY LINE AND NEW CUMBERLAND RIVER BRIDGE (2020CCN) (2022CCR) (2024CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-80104.00
Project Description: REDUCE CONGESTION AND IMPROVE SAFETY, CAPACITY AND MOBILIITY ALONG KY 90 BETWEEN WAYNE COUNTY LINE AND NEW CUMBERLAND RIVER BRIDGE (2020CCN) (2022CCR) (2024CCR)
This Project has no Vendors Assigned.