Highway Plan Phase Info
Phase Funding FY Amount
Design NH 2024 $5,000,000.00
Right of way NH 2026 $100,000.00
Utility Relocation NH 2027 $450,000.00
Construction NH 2027 $105,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D NH $7,000,000.00 2024 ESTIMATED 5/28/2024 $4,500,000.00
R NH $1,000,000.00 2025 ESTIMATED 5/28/2024 $10,030,000.00
U NH $0.00 2026 AUTHORIZED 5/28/2024 $2,580,000.00
C NH $86,500,000.00 2027 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
U 67808 6780803U $3,065,713.00 $3,065,713.00 $1,214,373.00 $0.00 $1,859,196.17
D 67808 6780810D $4,500,000.00 $0.00 $54,841.69 $1,410,960.31 $3,034,198.00
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: SOMERSET NORTHERN BYPASS (I-66) SECTION 3; FROM WEST OF THE BRIDGE OVER US-27 AND THE SOUTHERN RR, E TO KY-39 N OF BROYLES RD. (INCLUDES I-CHNG AT KY-39). (CONST SEQ. 3) (2002BOP)(04KYD)(05KYD) (2024CCN)
Location:
Route 1 Pulaski County PF-9999 from MP to MP
Route 2 100 County KY - from MP 18.846 to MP 19.93380
Item #: 8-59.50
Project Manager: KYTC\JOSEPH.GOSSAGE
Road Engineer: JDQ
Type of Work: NEW ROUTE(O)
Concerns:
RAILROAD INVOLVEMENT
Bridge Engineer: T.H.E. ENGINEERS, INC
Bridge Structure Number: 100B00063N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating: N/A
Posting: NO
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-59.50
Project Description: SOMERSET NORTHERN BYPASS (I-66) SECTION 3; FROM WEST OF THE BRIDGE OVER US-27 AND THE SOUTHERN RR, E TO KY-39 N OF BROYLES RD. (INCLUDES I-CHNG AT KY-39). (CONST SEQ. 3) (2002BOP)(04KYD)(05KYD) (2024CCN)

Milestones
Milestones Status Status Date Scheduled
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE ADV FOLDER REVIEWED SENT TO DIST 04/01/2004 04/01/2004
TRAFFIC PLANS - SIGNALS UNKNOWN 09/25/2001 09/25/2001
ADVANCE SITUATION TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 03/01/2003 03/01/2003
TRAFFIC PLANS - LIGHTING REQUIRED 04/21/2003 04/21/2003
GEOTEC ENGINEERING - ROADWAY GEOTEC ENGINEERING REPORT COMPLETED 02/03/2004 02/03/2004
RIGHT OF WAY PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 09/01/2013 09/01/2013
GEOTEC ENGINEERING - BRIDGES ADVANCE SITUATION REPORT COMPLETED 03/16/2004 03/16/2004
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 09/25/2001 09/25/2001
PRELIMINARY LINE AND GRADE INSPECTION HELD 11/08/2002 11/08/2002
DRAINAGE INSPECTION INSPECTION HELD 06/30/2003 06/30/2003
RIGHT OF WAY PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 09/01/2013 09/01/2013
ROAD PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 12/01/2013 12/01/2013
ROAD PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 12/01/2013 12/01/2013
ADVANCE SITUATION TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 03/01/2003 03/01/2003
JOINT INSPECTION INSPECTION HELD 06/30/2003 06/30/2003
TRAFFIC PLANS - SIGNING REQUIRED 12/05/2002 12/05/2002
 
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-59.50
Project Description: SOMERSET NORTHERN BYPASS (I-66) SECTION 3; FROM WEST OF THE BRIDGE OVER US-27 AND THE SOUTHERN RR, E TO KY-39 N OF BROYLES RD. (INCLUDES I-CHNG AT KY-39). (CONST SEQ. 3) (2002BOP)(04KYD)(05KYD) (2024CCN)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
Environmental Analysis FONSI RE 11/20/2006 Johnson, Depp & Quisenberry 11/20/2006 9/1/2007 6/18/2007 6/18/2008
FONSI RE 8/31/2005 DEA 9/12/2005 2/15/2007 1/1/4000
FONSI 9/1/2003 5/30/2004 6/14/2004 6/14/2005
FONSI 11/12/2002 HMB Professional Engineers, LLC 4/30/2004 6/14/2004 6/14/2005

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-59.50
Project Description: SOMERSET NORTHERN BYPASS (I-66) SECTION 3; FROM WEST OF THE BRIDGE OVER US-27 AND THE SOUTHERN RR, E TO KY-39 N OF BROYLES RD. (INCLUDES I-CHNG AT KY-39). (CONST SEQ. 3) (2002BOP)(04KYD)(05KYD) (2024CCN)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 8-59.50
Authorized Amount for R/W Phase: 10030000
RIGHT OF WAY STATUS REPORT (RWMS)
RWMS Parcel Input Summary
Total Parcels 121
Parcels Cleared 14
Offers Made 19
Deeds Recorded 15
Suits Submitted to CO 2
Right of Entry
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-59.50
Project Description: SOMERSET NORTHERN BYPASS (I-66) SECTION 3; FROM WEST OF THE BRIDGE OVER US-27 AND THE SOUTHERN RR, E TO KY-39 N OF BROYLES RD. (INCLUDES I-CHNG AT KY-39). (CONST SEQ. 3) (2002BOP)(04KYD)(05KYD) (2024CCN)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
Windstream Holdings II, LLC Communication
Eubank Water Water
The Cincinnati, New Orleans and Texas Pacific Railway Company Railroad
Kentucky Communications Network Authority Communication
Spectrum Mid-America LLC Communication
City of Somerset Natural Gas
Kentucky Utilities Electric Distrib
South Eastern Water Association, Inc. Water
AT&T Corp Telephone
East Kentucky Power Cooperative, Inc. Electric
South Kentucky RECC Electric
City of Science Hill Water
Agreements
Utility Company Agreement Status Agreement Amnt Document Type Estimate Approval Date Plans Approval Date Working Days Estimated Completion Date Work Status
AT&T Corp - Telephone Executed 33393.05 KRS 179 Engineering Services Agreement 10/30/2015
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-59.50
Project Description: SOMERSET NORTHERN BYPASS (I-66) SECTION 3; FROM WEST OF THE BRIDGE OVER US-27 AND THE SOUTHERN RR, E TO KY-39 N OF BROYLES RD. (INCLUDES I-CHNG AT KY-39). (CONST SEQ. 3) (2002BOP)(04KYD)(05KYD) (2024CCN)
Phase Vendor
U KENTUCKY UTILITIES CO
D HAWORTH MEYER BOLEYN INC
U EAST KENTUCKY POWER COOPERATIVE
R WADE ENGINEERING
U SOUTH KY RURAL ELECTRIC CORP
U CITY OF EUBANK
R BROOK PING
R ROBERT R KNIGHT
R JOHN D LYONS
U CINCINNATI NEW ORLEANS AND
R TOOMS & DUNAWAY PLLC
U NEWWAVE COMMUNICATIONS
U SOUTHEASTERN WATER ASSOCIATION
U AT&T
R STRAND ASSOCIATES INC.