Highway Plan Phase Info
Phase Funding FY Amount
Construction HGC 2025 $3,980,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D NH $0.00 2024 SENTTOFHWA 5/6/2024 $1,500,000.00
R NH $2,666,000.00 2025 ESTIMATED $0.00
U NH $1,598,000.00 2026 ESTIMATED $0.00
C HGC $18,379,000.00 2027 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 17974 1797401D $1,500,000.00 $0.00 $850.85 $1,019,846.00 $479,463.43
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: SAFETY IMPROVEMENTS TO NEW CIRCLE ROAD BETWEEN BOARDWALK AND BRYAN STATION ROAD. - STATE FUNDED COMPONENT OF FEDERAL GRANT RECEIVED IN LATE 2023. (2024CCR)
Location:
Route 1 Fayette County KY-4 from MP 10 to MP 11.4
Route 2 County - from MP to MP
Item #: 7-462.00
Project Manager: KYTC\ROBIN.SPRAGUE
Road Engineer:
Type of Work: SAFETY
Concerns:
Bridge Engineer:
Bridge Structure Number: 034R00600N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\ROBIN.SPRAGUE       Item #: 7-462.00
Project Description: SAFETY IMPROVEMENTS TO NEW CIRCLE ROAD BETWEEN BOARDWALK AND BRYAN STATION ROAD. - STATE FUNDED COMPONENT OF FEDERAL GRANT RECEIVED IN LATE 2023. (2024CCR)

This Project has no Milesones defined.
Project Manager: KYTC\ROBIN.SPRAGUE       Item #: 7-462.00
Project Description: SAFETY IMPROVEMENTS TO NEW CIRCLE ROAD BETWEEN BOARDWALK AND BRYAN STATION ROAD. - STATE FUNDED COMPONENT OF FEDERAL GRANT RECEIVED IN LATE 2023. (2024CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
District Office CE LVL 1 7/1/2024 Palmer Engineering 7/1/2024 7/1/2025

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\ROBIN.SPRAGUE       Item #: 7-462.00
Project Description: SAFETY IMPROVEMENTS TO NEW CIRCLE ROAD BETWEEN BOARDWALK AND BRYAN STATION ROAD. - STATE FUNDED COMPONENT OF FEDERAL GRANT RECEIVED IN LATE 2023. (2024CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 7-462.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\ROBIN.SPRAGUE       Item #: 7-462.00
Project Description: SAFETY IMPROVEMENTS TO NEW CIRCLE ROAD BETWEEN BOARDWALK AND BRYAN STATION ROAD. - STATE FUNDED COMPONENT OF FEDERAL GRANT RECEIVED IN LATE 2023. (2024CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\ROBIN.SPRAGUE       Item #: 7-462.00
Project Description: SAFETY IMPROVEMENTS TO NEW CIRCLE ROAD BETWEEN BOARDWALK AND BRYAN STATION ROAD. - STATE FUNDED COMPONENT OF FEDERAL GRANT RECEIVED IN LATE 2023. (2024CCR)
This Project has no Vendors Assigned.