Highway Plan Phase Info
Phase Funding FY Amount
Right of way NH 2026 $2,200,000.00
Utility Relocation NH 2026 $3,000,000.00
Construction NH 2028 $28,250,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D NH $0.00 2023 AUTHORIZED 7/12/2022 $2,000,000.00
R NH $2,200,000.00 2026 ESTIMATED $0.00
U NH $8,000,000.00 2026 ESTIMATED $0.00
C NH $56,297,000.00 2026 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 15291 1529101D $2,000,000.00 $0.00 $858,704.79 $316,808.05 $829,157.70
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: REDUCE CONGESTION ON KY-4 (NEW CIRCLE RD) FROM TRADE CENTER DR TO WOODHILL DR. (2024CCR)
Location:
Route 1 Fayette County KY-4 from MP 13.195 to MP 14.508
Route 2 County - from MP to MP
Item #: 7-438.00
Project Manager: KYTC\LAUREN.MEIGHAN
Road Engineer:
Type of Work: MAJOR WIDENING
Concerns:
Bridge Engineer:
Bridge Structure Number: 034B00103N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-438.00
Project Description: REDUCE CONGESTION ON KY-4 (NEW CIRCLE RD) FROM TRADE CENTER DR TO WOODHILL DR. (2024CCR)

Milestones
Milestones Status Status Date Scheduled
Right of Way Plans 01/01/1900
Final Plans Submittal 01/01/1900
Railroad Clearance 01/01/1900
Environmental Approval 01/01/1900
Preliminary Engineering 06/29/2023
Final Design 01/01/1900
Geotechnical - Roadway Design Investigation 01/01/1900
Utility Clearance 01/01/1900
Roadway Plans 01/01/1900
Utility Agreement 01/01/1900
Planning 01/01/1900
Letting 01/01/1900
ROW Clearance 01/01/1900
Design Executive Summary 06/29/2023
Right of Way Acquisition 01/01/1900
Alternative Selection 06/29/2023
Structure Plans 01/01/1900
 
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-438.00
Project Description: REDUCE CONGESTION ON KY-4 (NEW CIRCLE RD) FROM TRADE CENTER DR TO WOODHILL DR. (2024CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
District Office CE LVL 1 8/25/2022 8/25/2022 9/30/2023

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-438.00
Project Description: REDUCE CONGESTION ON KY-4 (NEW CIRCLE RD) FROM TRADE CENTER DR TO WOODHILL DR. (2024CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 7-438.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-438.00
Project Description: REDUCE CONGESTION ON KY-4 (NEW CIRCLE RD) FROM TRADE CENTER DR TO WOODHILL DR. (2024CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-438.00
Project Description: REDUCE CONGESTION ON KY-4 (NEW CIRCLE RD) FROM TRADE CENTER DR TO WOODHILL DR. (2024CCR)
Phase Vendor
D PALMER ENGINEERING CO