Highway Plan Phase Info
Phase Funding FY Amount
Design SPP 2023 $4,606,000.00
Right of way SPP 2026 $4,221,000.00
Utility Relocation SPP 2027 $1,974,000.00
Construction SPP 2027 $51,321,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D SPP $0.00 2023 AUTHORIZED 8/3/2022 $1,200,000.00
R SPP $1,400,000.00 2026 ESTIMATED $0.00
U SPP $1,000,000.00 2026 ESTIMATED $0.00
C SPP $20,000,000.00 2028 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 15497 1549701D $1,200,000.00 $0.00 $367,668.47 $345,174.45 $500,101.86
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: Updating US-25 from KY 1994 to KY 491 north junction. (2022CCN)
Location:
Route 1 Grant County US-25 from MP 19.4 to MP 23.2
Route 2 County - from MP to MP
Item #: 6-80216.00
Project Manager: KYTC\ELLEN.GREGORY
Road Engineer:
Type of Work: RECONSTRUCTION(O)
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\ELLEN.GREGORY       Item #: 6-80216.00
Project Description: Updating US-25 from KY 1994 to KY 491 north junction. (2022CCN)

This Project has no Milesones defined.
Project Manager: KYTC\ELLEN.GREGORY       Item #: 6-80216.00
Project Description: Updating US-25 from KY 1994 to KY 491 north junction. (2022CCN)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
District Office CE LVL 2 2/3/2024 QK4, Inc. 2/1/2025

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\ELLEN.GREGORY       Item #: 6-80216.00
Project Description: Updating US-25 from KY 1994 to KY 491 north junction. (2022CCN)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 6-80216.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\ELLEN.GREGORY       Item #: 6-80216.00
Project Description: Updating US-25 from KY 1994 to KY 491 north junction. (2022CCN)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\ELLEN.GREGORY       Item #: 6-80216.00
Project Description: Updating US-25 from KY 1994 to KY 491 north junction. (2022CCN)
This Project has no Vendors Assigned.