Highway Plan Phase Info
Phase Funding FY Amount
Design STP 2022 $541,000.00
Right of way SPP 2024 $2,894,000.00
Utility Relocation SPP 2025 $337,000.00
Construction SPP 2026 $3,581,600.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D STP $0.00 2022 AUTHORIZED 10/20/2022 $541,000.00
R SPP $6,000,000.00 2024 ESTIMATED $0.00
U SPP $300,000.00 2024 ESTIMATED $0.00
C SPP $4,600,000.00 2026 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 15843 1584301D $542,000.00 $0.00 $153,754.11 $69,550.92 $319,723.63
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: Improve access to KY 237 for Litton Lane. (2022CCN)
Location:
Route 1 Boone County KY-237 from MP 10.25 to MP 10.45
Route 2 County - from MP to MP
Item #: 6-80209.00
Project Manager: KYTC\ELLEN.GREGORY
Road Engineer:
Type of Work: CONGESTION MITIGTN(O)
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\ELLEN.GREGORY       Item #: 6-80209.00
Project Description: Improve access to KY 237 for Litton Lane. (2022CCN)

This Project has no Milesones defined.
Project Manager: KYTC\ELLEN.GREGORY       Item #: 6-80209.00
Project Description: Improve access to KY 237 for Litton Lane. (2022CCN)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
CE LVL 2 8/1/2023 QK4, Inc.

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\ELLEN.GREGORY       Item #: 6-80209.00
Project Description: Improve access to KY 237 for Litton Lane. (2022CCN)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 6-80209.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\ELLEN.GREGORY       Item #: 6-80209.00
Project Description: Improve access to KY 237 for Litton Lane. (2022CCN)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\ELLEN.GREGORY       Item #: 6-80209.00
Project Description: Improve access to KY 237 for Litton Lane. (2022CCN)
This Project has no Vendors Assigned.