Some critical dates have not been assigned. (Letting Date not Established)
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ON I-265 FROM I-65 TO US-31E. (2024CCR) Location: Route 1 Jefferson County I -265 from MP 10.25 to MP 17.3 Route 2 County - from MP to MP Item #: 5-554.00 Project Manager: KYTC\TRACY.LOVELL Road Engineer: Type of Work: RECONSTRUCTION Concerns:
Bridge Engineer: Bridge Structure Number: 056B00322L Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report Bridge Suff. Rate: 88 NBI Rating: Not Deficient Posting: NO |
Project Manager: KYTC\TRACY.LOVELL Item #: 5-554.00 Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ON I-265 FROM I-65 TO US-31E. (2024CCR) |
Milestones
|
Project Manager: KYTC\TRACY.LOVELL Item #: 5-554.00 Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ON I-265 FROM I-65 TO US-31E. (2024CCR) Authoritative Source for Environmental Data: EATS |
Project Manager: KYTC\TRACY.LOVELL Item #: 5-554.00 Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ON I-265 FROM I-65 TO US-31E. (2024CCR) Authoritative Source for R/W Data: KROWDS View Communicating All Promises (CAP) Report for Item# 5-554.00 |
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
|
Project Manager: KYTC\TRACY.LOVELL Item #: 5-554.00 Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ON I-265 FROM I-65 TO US-31E. (2024CCR) Authoritative Source for Utilities and Rail Tracking Data: KURTS |
Utility Companies | |
Utility Name | Facility Name |
Project Manager: KYTC\TRACY.LOVELL Item #: 5-554.00 Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ON I-265 FROM I-65 TO US-31E. (2024CCR) |