Highway Plan Phase Info
Phase Funding FY Amount
Design STP 2024 $1,500,000.00
Right of way STP 2025 $2,100,000.00
Utility Relocation STP 2026 $4,430,000.00
Construction STP 2027 $19,720,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D STP $1,500,000.00 2025 SENTTOFHWA $0.00
R STP $0.00 2025 AUTHORIZED 10/23/2024 $2,100,000.00
U STP $4,500,000.00 2026 ESTIMATED $0.00
C STP $18,000,000.00 2028 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
R 12841 1284102R $2,100,000.00 $0.00 $10,357.17 $0.00 $2,089,642.83
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR)
Location:
Route 1 Washington County KY-555 from MP 8.643 to MP 14.639
Route 2 County - from MP to MP
Item #: 4-164.20
Project Manager: KYTC\KEVIN.BLAIN
Road Engineer:
Type of Work: AIR QUALITY(P)
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\KEVIN.BLAIN       Item #: 4-164.20
Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR)

Milestones
Milestones Status Status Date Scheduled
Traffic Signals Plans 06/27/2024
Final Plans Submittal 06/27/2024
PS&E 06/27/2024
Check Prints 06/27/2024
Funding for Preliminary Engineering 06/27/2024
Final Design Notice to Proceed 02/12/2025
Pavement Design 06/27/2024
Planning Study and Reports 06/27/2024
Letting 06/27/2024
RR Real Estate 06/27/2024
Signing Plans 06/27/2024
Environmental Approval 06/27/2024
ROW Clearance 06/27/2024
Traffic Lighting Plans 06/27/2024
Additional Design Funding 06/27/2024
Structure Plans 06/27/2024
Additional Design Funding 06/27/2024
RR Engineering Agreement 06/27/2024
Roadway Plans 06/27/2024
Geotechnical - Roadway Design Investigation 06/27/2024
Planning Funding 06/27/2024
Advertisement 06/27/2024
Right of Way Inspection 06/27/2024
Final Design 06/27/2024
Alternative Selection 08/23/2024
Joint Inspection Meeting 02/12/2025
Traffic Control Electrical Device Plans 06/27/2024
Utility Clearance 06/27/2024
Highway Drainage Design 02/12/2025
FHWA Scope Verification Meeting 06/27/2024
Preliminary Engineering Notice to Proceed 06/27/2024
Planning 06/27/2024
Preliminary Engineering 06/27/2024
Railroad Clearance 06/27/2024
Design Executive Summary 02/12/2025
Utility Agreement 06/27/2024
Drainage Inspection 02/12/2025
Right of Way Plans 02/12/2025
Traffic Management Plan 06/27/2024
Right of Way Acquisition 06/27/2024
Right of Way Consultant Notice to Proceed 06/27/2024
 
Project Manager: KYTC\KEVIN.BLAIN       Item #: 4-164.20
Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
Environmental Analysis Preliminary 11/15/2022 11/15/2022 11/30/2022
District Office CE LVL 1 9/12/2022 Palmer Engineering 12/16/2022 7/15/2024 8/27/2024 8/27/2026

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\KEVIN.BLAIN       Item #: 4-164.20
Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 4-164.20
Authorized Amount for R/W Phase: 2100000
This Project has no Right Of Way Data available from RWMS.
RIGHT OF WAY STATUS REPORT (KROWDS)
KROWDS Parcel Input Summary (RW000407)
Total Parcels 3
Parcels Cleared 1
Offers Made 3
Deeds Recorded 1
Suits Submitted to CO 0
Right of Entry 0
Project Manager: KYTC\KEVIN.BLAIN       Item #: 4-164.20
Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
Salt River Electric Cooperative Corp. Electric
Atmos Energy Natural Gas
AT&T Kentucky Telephone
Springfield Water & Sewer Commission Water
Agreements
Utility Company Agreement Status Agreement Amnt Document Type Estimate Approval Date Plans Approval Date Working Days Estimated Completion Date Work Status
Springfield Water & Sewer Commission - Water Executed 22080 KRS 177 Engineering Service Agreement 6/11/2025 0
Project Manager: KYTC\KEVIN.BLAIN       Item #: 4-164.20
Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR)
This Project has no Vendors Assigned.