Some critical dates have not been assigned. (Letting Date not Established)
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR) Location: Route 1 Washington County KY-555 from MP 8.643 to MP 14.639 Route 2 County - from MP to MP Item #: 4-164.20 Project Manager: KYTC\KEVIN.BLAIN Road Engineer: Type of Work: AIR QUALITY(P) Concerns:
Bridge Engineer: Bridge Structure Number: Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report Bridge Suff. Rate: NBI Rating: Posting: |
Project Manager: KYTC\KEVIN.BLAIN Item #: 4-164.20 Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR) |
Milestones
|
Project Manager: KYTC\KEVIN.BLAIN Item #: 4-164.20 Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR) Authoritative Source for Environmental Data: EATS |
Requestor | Request Type | Request Date | Assigned Name | Assigned Date | Scheduled Completion Date |
Actual Completion Date | Expiration Date |
Environmental Analysis | Preliminary | 11/15/2022 | 11/15/2022 | 11/30/2022 | |||
District Office | CE LVL 1 | 9/12/2022 | Palmer Engineering | 12/16/2022 | 7/15/2024 | 8/27/2024 | 8/27/2026 |
Project Manager: KYTC\KEVIN.BLAIN Item #: 4-164.20 Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR) Authoritative Source for R/W Data: KROWDS View Communicating All Promises (CAP) Report for Item# 4-164.20 |
Authorized Amount for R/W Phase: 2100000 | ||||||||||||||
This Project has no Right Of Way Data available from RWMS.
RIGHT OF WAY STATUS REPORT (KROWDS)
|
Project Manager: KYTC\KEVIN.BLAIN Item #: 4-164.20 Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR) Authoritative Source for Utilities and Rail Tracking Data: KURTS |
Utility Companies | |
Utility Name | Facility Name |
Salt River Electric Cooperative Corp. | Electric |
Atmos Energy | Natural Gas |
AT&T Kentucky | Telephone |
Springfield Water & Sewer Commission | Water |
Agreements | ||||||||
Utility Company | Agreement Status | Agreement Amnt | Document Type | Estimate Approval Date | Plans Approval Date | Working Days | Estimated Completion Date | Work Status |
Springfield Water & Sewer Commission - Water | Executed | 22080 | KRS 177 Engineering Service Agreement | 6/11/2025 | 0 |
Project Manager: KYTC\KEVIN.BLAIN Item #: 4-164.20 Project Description: IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY (2022CCN) (2024CCR) |