Highway Plan Phase Info
Phase Funding FY Amount
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
P FED $250,000.00 2022 ESTIMATED $0.00
D STP $1,050,000.00 2026 NON-SIXYEAR $0.00
R STP $3,150,000.00 2027 NON-SIXYEAR $0.00
U STP $1,050,000.00 2027 NON-SIXYEAR $0.00
C STP $10,000,000.00 2028 NON-SIXYEAR $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: Address congestion, access management, and safety issues on US 25 North from Hal Rogers Parkway near KY State Police Post to KY 490.
Location:
Route 1 Laurel County US-25 from MP 13.556 to MP 16.7
Route 2 County - from MP to MP
Item #: 11-181.00
Project Manager: KYTC\STEPHEN.DEWITTE
Road Engineer:
Type of Work: CongestionManagement(
Concerns:
Bridge Engineer:
Bridge Structure Number: 063B00006N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 84.9
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\STEPHEN.DEWITTE       Item #: 11-181.00
Project Description: Address congestion, access management, and safety issues on US 25 North from Hal Rogers Parkway near KY State Police Post to KY 490.

This Project has no Milesones defined.
Project Manager: KYTC\STEPHEN.DEWITTE       Item #: 11-181.00
Project Description: Address congestion, access management, and safety issues on US 25 North from Hal Rogers Parkway near KY State Police Post to KY 490.
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
Preliminary 3/31/2023

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\STEPHEN.DEWITTE       Item #: 11-181.00
Project Description: Address congestion, access management, and safety issues on US 25 North from Hal Rogers Parkway near KY State Police Post to KY 490.
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 11-181.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\STEPHEN.DEWITTE       Item #: 11-181.00
Project Description: Address congestion, access management, and safety issues on US 25 North from Hal Rogers Parkway near KY State Police Post to KY 490.
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\STEPHEN.DEWITTE       Item #: 11-181.00
Project Description: Address congestion, access management, and safety issues on US 25 North from Hal Rogers Parkway near KY State Police Post to KY 490.
This Project has no Vendors Assigned.