Highway Plan Phase Info
Phase Funding FY Amount
Design STP 2023 $2,500,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D STP $0.00 2023 AUTHORIZED 8/3/2022 $1,500,000.00
R STP $5,250,000.00 2025 ESTIMATED $0.00
U STP $3,450,000.00 2026 ESTIMATED $0.00
C STP $19,550,000.00 2028 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 15468 1546801D $1,500,000.00 $0.00 $115,457.16 $617,108.91 $768,392.83
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: IMPROVE LEVEL OF SERVICE, SAFETY, AND CONNECTIVITY ON KY-82 FROM KY-89 IN ESTILL CO. TO NEW CONSTRUCTION LOCATED NORTH OF HUDSON MILL ROAD IN ESTILL COUNTY. (2022CCR)
Location:
Route 1 Estill County KY-82 from MP 0 to MP 4.1
Route 2 County - from MP to MP
Item #: 10-205.00
Project Manager: KYTC\Aric.Skaggs
Road Engineer:
Type of Work: RECONSTRUCTION
Concerns:
Bridge Engineer:
Bridge Structure Number: 033B00042N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 69.1
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\Aric.Skaggs       Item #: 10-205.00
Project Description: IMPROVE LEVEL OF SERVICE, SAFETY, AND CONNECTIVITY ON KY-82 FROM KY-89 IN ESTILL CO. TO NEW CONSTRUCTION LOCATED NORTH OF HUDSON MILL ROAD IN ESTILL COUNTY. (2022CCR)

Milestones
Milestones Status Status Date Scheduled
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
GEOTEC ENGINEERING - ROADWAY UNKNOWN 07/10/2018 07/10/2018
RIGHT OF WAY PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - LIGHTING UNKNOWN 07/10/2018 07/10/2018
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
DRAINAGE INSPECTION UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - SIGNING UNKNOWN 07/10/2018 07/10/2018
GEOTEC ENGINEERING - BRIDGES UNKNOWN 07/10/2018 07/10/2018
JOINT INSPECTION UNKNOWN 07/10/2018 07/10/2018
ROAD PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 07/10/2018 07/10/2018
PRELIMINARY LINE AND GRADE UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - SIGNALS UNKNOWN 07/10/2018 07/10/2018
 
Project Manager: KYTC\Aric.Skaggs       Item #: 10-205.00
Project Description: IMPROVE LEVEL OF SERVICE, SAFETY, AND CONNECTIVITY ON KY-82 FROM KY-89 IN ESTILL CO. TO NEW CONSTRUCTION LOCATED NORTH OF HUDSON MILL ROAD IN ESTILL COUNTY. (2022CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
Preliminary 2/22/2022

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\Aric.Skaggs       Item #: 10-205.00
Project Description: IMPROVE LEVEL OF SERVICE, SAFETY, AND CONNECTIVITY ON KY-82 FROM KY-89 IN ESTILL CO. TO NEW CONSTRUCTION LOCATED NORTH OF HUDSON MILL ROAD IN ESTILL COUNTY. (2022CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 10-205.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\Aric.Skaggs       Item #: 10-205.00
Project Description: IMPROVE LEVEL OF SERVICE, SAFETY, AND CONNECTIVITY ON KY-82 FROM KY-89 IN ESTILL CO. TO NEW CONSTRUCTION LOCATED NORTH OF HUDSON MILL ROAD IN ESTILL COUNTY. (2022CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\Aric.Skaggs       Item #: 10-205.00
Project Description: IMPROVE LEVEL OF SERVICE, SAFETY, AND CONNECTIVITY ON KY-82 FROM KY-89 IN ESTILL CO. TO NEW CONSTRUCTION LOCATED NORTH OF HUDSON MILL ROAD IN ESTILL COUNTY. (2022CCR)
Phase Vendor
D STANTEC CONSULTING SERVICES INC