Highway Plan Phase Info
Phase Funding FY Amount
Planning NH 2025 $250,000.00
Design NH 2026 $2,080,000.00
Right of way NH 2028 $550,000.00
Utility Relocation NH 2028 $2,240,000.00
Construction NH 2030 $39,200,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
P NH $250,000.00 2025 ESTIMATED $0.00
D NH $2,080,000.00 2026 ESTIMATED $0.00
R NH $550,000.00 2028 ESTIMATED $0.00
U NH $2,240,000.00 2028 ESTIMATED $0.00
C NH $39,200,000.00 2030 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: ADDRESS SAFETY, CONGESTION, AND FUTURE CAPACITY ISSUES FROM US 60 TO US 68 IN PADUCAH. SEE MARCH, 2002 PADUCAH-MCCRACKEN COUNTY TRANSPORTATION STUDY. (2024CCN)
Location:
Route 1 McCracken County I -24 from MP 4.328 to MP 16.151
Route 2 County - from MP to MP
Item #: 1-80305.00
Project Manager: KYTC\AUSTIN.HART
Road Engineer:
Type of Work: CONGESTION MITIGTN(O)
Concerns:
Bridge Engineer:
Bridge Structure Number: 073B00009N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 99
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\AUSTIN.HART       Item #: 1-80305.00
Project Description: ADDRESS SAFETY, CONGESTION, AND FUTURE CAPACITY ISSUES FROM US 60 TO US 68 IN PADUCAH. SEE MARCH, 2002 PADUCAH-MCCRACKEN COUNTY TRANSPORTATION STUDY. (2024CCN)

This Project has no Milesones defined.
Project Manager: KYTC\AUSTIN.HART       Item #: 1-80305.00
Project Description: ADDRESS SAFETY, CONGESTION, AND FUTURE CAPACITY ISSUES FROM US 60 TO US 68 IN PADUCAH. SEE MARCH, 2002 PADUCAH-MCCRACKEN COUNTY TRANSPORTATION STUDY. (2024CCN)
Authoritative Source for Environmental Data:  EATS
This Project has no Environmental data.

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\AUSTIN.HART       Item #: 1-80305.00
Project Description: ADDRESS SAFETY, CONGESTION, AND FUTURE CAPACITY ISSUES FROM US 60 TO US 68 IN PADUCAH. SEE MARCH, 2002 PADUCAH-MCCRACKEN COUNTY TRANSPORTATION STUDY. (2024CCN)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 1-80305.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\AUSTIN.HART       Item #: 1-80305.00
Project Description: ADDRESS SAFETY, CONGESTION, AND FUTURE CAPACITY ISSUES FROM US 60 TO US 68 IN PADUCAH. SEE MARCH, 2002 PADUCAH-MCCRACKEN COUNTY TRANSPORTATION STUDY. (2024CCN)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\AUSTIN.HART       Item #: 1-80305.00
Project Description: ADDRESS SAFETY, CONGESTION, AND FUTURE CAPACITY ISSUES FROM US 60 TO US 68 IN PADUCAH. SEE MARCH, 2002 PADUCAH-MCCRACKEN COUNTY TRANSPORTATION STUDY. (2024CCN)
This Project has no Vendors Assigned.