US 68 |
BARREN |
$250,000.00 |
87406 - 2 |
11/15/2013 |
THIS AUTHORIZATION PROVIDES CONSTRUCTION FUNDS BASED ON THE CURRENT ESTIMATE PRIOR TO THE PROJECT BEING LET. |
NEW BOWLING GREEN ROAD @ KY 25 |
US 68 |
BARREN |
$125,000.00 |
87406 - 1 |
4/17/2013 |
THIS AUTHORIZATION PROVIDES INITIAL RIGHT OF WAY FUNDS (4 PARCELS; 1 RELO), AND ALSO PROVIDES INITIAL UTILITY FUNDS (2 UTILITY ADJUSTMENTS) FOR THE PROJECT. FUNDING FOR THE R/W PHASE OF THIS PROJECT IS PART OF THE “ADVANCE ACQUISITION OF R/W” PROGRAM TEMPORARILY USING STATE FUNDS, AND THE R/W PHASE WILL BE PROGRAMMED FOR REIMBURSEMENT OF FEDERAL FUNDING UPON COMPLETION OF THE PROJECT ENVIRONMENTAL DOCUMENT. TJ. |
NEW BOWLING GREEN ROAD @ KY 25 |
US 68 |
BARREN |
$25,000.00 |
87406 - 0 |
11/5/2012 |
THIS AUTHORIZATION PROVIDES INITIAL DESIGN FUNDS TO BEGIN THE DESIGN PHASE OF THE PROJECT. TJ. |
NEW BOWLING GREEN ROAD @ KY 25 |