The Commonwealth pays employees on a semi-monthly basis with a scheduled pay day on the 15th and 30th of each month. The two monthly pay periods are from the 1st to the 15th of the month and the 16th through the last day of the month. Pay check distribution is delayed by one pay period to allow for system processing. For example work performed during the 1st to the 15th day of the month is paid to the employee on the 30th of the month. Accordingly the cost accounting charges for labor costs posting in eMARS to operating accounts and highway projects are also delayed by approximately one pay period.
A good rule of measure is that the cost accounting charges for the pay period ending on the 15th of the month will post to eMARS by the 25th and those for the pay period ending on the last day of the month will post to eMARS by the 10th of the following month.

x close panel
Detailed Project Expenditure Report
Total E-MARS Expenditures for 9011101D = $1,788,254.33
Click here for Labor Costs Information
Year Month PBU Charge District Object Phase Program Code County Date ACT Activity Name Trans ID Reference # Vendor Name Expenditure Line Description
2024 10 FD52 08 E143 D 9011101D 069 4/5/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400201832 PON21900004878 QK4 INC $3,063.71 Lincoln County 8-167
2024 9 FD52 08 E143 D 9011101D 069 3/4/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400177866 PON21900004878 QK4 INC $17,426.90 Lincoln County 8-167
2024 8 FD52 08 E143 D 9011101D 069 2/19/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400163272 PON21900004878 QK4 INC $11,694.80 Lincoln County 8-167
2024 8 FD52 08 E143 D 9011101D 069 2/19/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400165970 PON21900004878 QK4 INC $20,754.15 Lincoln County 8-167
2024 7 FD52 08 E111 D 9011101D 069 1/11/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011O1062400506030 $700.80
2024 7 FD52 08 E111 D 9011101D 069 1/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400506030 $712.70
2024 7 FD52 08 E121 D 9011101D 069 1/11/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011O1062400506030 $52.72
2024 7 FD52 08 E121 D 9011101D 069 1/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400506030 $53.29
2024 7 FD52 08 E122 D 9011101D 069 1/11/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011O1062400506030 $463.62
2024 7 FD52 08 E122 D 9011101D 069 1/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400506030 $471.59
2024 7 FD52 08 E123 D 9011101D 069 1/11/2024 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011O1062400506030 $88.93
2024 7 FD52 08 E123 D 9011101D 069 1/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400506030 $95.50
2024 6 FD52 08 E111 D 9011101D 069 12/22/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122N1062335505212 $1,798.72
2024 6 FD52 08 E111 D 9011101D 069 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335505212 $499.40
2024 6 FD52 08 E121 D 9011101D 069 12/22/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122N1062335505212 $133.84
2024 6 FD52 08 E121 D 9011101D 069 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335505212 $37.45
2024 6 FD52 08 E122 D 9011101D 069 12/22/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122N1062335505212 $1,189.80
2024 6 FD52 08 E122 D 9011101D 069 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335505212 $330.44
2024 6 FD52 08 E123 D 9011101D 069 12/22/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122N1062335505212 $267.13
2024 6 FD52 08 E123 D 9011101D 069 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335505212 $66.10
2024 6 FD52 08 E124 D 9011101D 069 12/22/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122N1062335505212 $0.55
2024 6 FD52 08 E124 D 9011101D 069 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335505212 $0.15
2024 6 FD52 08 E111 D 9011101D 069 12/11/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121N1062334204067 $1,660.56
2024 6 FD52 08 E111 D 9011101D 069 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334204067 $1,020.52
2024 6 FD52 08 E121 D 9011101D 069 12/11/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121N1062334204067 $117.78
2024 6 FD52 08 E121 D 9011101D 069 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334204067 $73.51
2024 6 FD52 08 E122 D 9011101D 069 12/11/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121N1062334204067 $1,098.80
2024 6 FD52 08 E122 D 9011101D 069 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334204067 $675.27
2024 6 FD52 08 E123 D 9011101D 069 12/11/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121N1062334204067 $312.95
2024 6 FD52 08 E123 D 9011101D 069 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334204067 $177.02
2024 6 FD52 08 E143 D 9011101D 069 12/5/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400111579 PON21900004878 QK4 INC $19,139.94 Lincoln County 8-167
2024 5 FD52 08 E111 D 9011101D 069 11/30/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112N1062332503084 $1,300.57
2024 5 FD52 08 E111 D 9011101D 069 11/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332503084 $291.43
2024 5 FD52 08 E121 D 9011101D 069 11/30/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112N1062332503084 $96.22
2024 5 FD52 08 E121 D 9011101D 069 11/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332503084 $21.53
2024 5 FD52 08 E122 D 9011101D 069 11/30/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112N1062332503084 $860.53
2024 5 FD52 08 E122 D 9011101D 069 11/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332503084 $192.83
2024 5 FD52 08 E123 D 9011101D 069 11/30/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112N1062332503084 $197.51
2024 5 FD52 08 E123 D 9011101D 069 11/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332503084 $44.53
2024 5 FD52 08 E124 D 9011101D 069 11/30/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112N1062332503084 $0.36
2024 5 FD52 08 E124 D 9011101D 069 11/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332503084 $0.09
2024 5 FD52 08 E229 D 9011101D 069 11/14/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162523314012780 $38.20
2024 5 FD52 08 E143 D 9011101D 069 11/9/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400091951 PON21900004878 QK4 INC $6,852.17 Lincoln County 8-167
2024 5 FD52 08 E111 D 9011101D 069 11/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111N1062331201970 $2,794.78
2024 5 FD52 08 E111 D 9011101D 069 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201970 $92.36
2024 5 FD52 08 E121 D 9011101D 069 11/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111N1062331201970 $204.20
2024 5 FD52 08 E121 D 9011101D 069 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201970 $6.75
2024 5 FD52 08 E122 D 9011101D 069 11/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111N1062331201970 $1,849.37
2024 5 FD52 08 E122 D 9011101D 069 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201970 $61.12
2024 5 FD52 08 E123 D 9011101D 069 11/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111N1062331201970 $428.03
2024 5 FD52 08 E123 D 9011101D 069 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201970 $13.14
2024 4 FD52 08 E111 D 9011101D 069 10/30/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102N1062329600952 $1,368.03
2024 4 FD52 08 E111 D 9011101D 069 10/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102N1062329600952 $1,757.72
2024 4 FD52 08 E121 D 9011101D 069 10/30/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102N1062329600952 $99.74
2024 4 FD52 08 E121 D 9011101D 069 10/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102N1062329600952 $127.44
2024 4 FD52 08 E122 D 9011101D 069 10/30/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102N1062329600952 $905.43
2024 4 FD52 08 E122 D 9011101D 069 10/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102N1062329600952 $1,163.09
2024 4 FD52 08 E123 D 9011101D 069 10/30/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102N1062329600952 $251.13
2024 4 FD52 08 E123 D 9011101D 069 10/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102N1062329600952 $329.81
2024 4 FD52 08 E124 D 9011101D 069 10/30/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102N1062329600952 $0.40
2024 4 FD52 08 E124 D 9011101D 069 10/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102N1062329600952 $0.48
2024 4 FD52 08 E111 D 9011101D 069 10/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101N1062328010201 $1,704.52
2024 4 FD52 08 E111 D 9011101D 069 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328010201 $120.70
2024 4 FD52 08 E121 D 9011101D 069 10/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101N1062328010201 $125.12
2024 4 FD52 08 E121 D 9011101D 069 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328010201 $8.66
2024 4 FD52 08 E122 D 9011101D 069 10/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101N1062328010201 $1,127.86
2024 4 FD52 08 E122 D 9011101D 069 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328010201 $79.87
2024 4 FD52 08 E123 D 9011101D 069 10/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101N1062328010201 $254.70
2024 4 FD52 08 E123 D 9011101D 069 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328010201 $20.29
2024 3 FD52 08 E111 D 9011101D 069 9/29/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062327209197 $1,326.01
2024 3 FD52 08 E111 D 9011101D 069 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327209197 $953.41
2024 3 FD52 08 E121 D 9011101D 069 9/29/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062327209197 $95.88
2024 3 FD52 08 E121 D 9011101D 069 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327209197 $68.94
2024 3 FD52 08 E122 D 9011101D 069 9/29/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062327209197 $877.43
2024 3 FD52 08 E122 D 9011101D 069 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327209197 $630.87
2024 3 FD52 08 E123 D 9011101D 069 9/29/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062327209197 $256.92
2024 3 FD52 08 E123 D 9011101D 069 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327209197 $182.41
2024 3 FD52 08 E124 D 9011101D 069 9/29/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062327209197 $0.36
2024 3 FD52 08 E124 D 9011101D 069 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327209197 $0.27
2024 3 FD52 08 E143 D 9011101D 069 9/28/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400063476 PON21900004878 QK4 INC $1,614.21 Lincoln County 8-167
2024 3 FD52 08 E111 D 9011101D 069 9/28/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062326507846 ($1,326.01)
2024 3 FD52 08 E111 D 9011101D 069 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507846 ($953.41)
2024 3 FD52 08 E121 D 9011101D 069 9/28/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062326507846 ($95.88)
2024 3 FD52 08 E121 D 9011101D 069 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507846 ($68.94)
2024 3 FD52 08 E122 D 9011101D 069 9/28/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062326507846 ($877.43)
2024 3 FD52 08 E122 D 9011101D 069 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507846 ($630.87)
2024 3 FD52 08 E123 D 9011101D 069 9/28/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062326507846 ($256.92)
2024 3 FD52 08 E123 D 9011101D 069 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507846 ($182.41)
2024 3 FD52 08 E124 D 9011101D 069 9/28/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062326507846 ($0.36)
2024 3 FD52 08 E124 D 9011101D 069 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507846 ($0.27)
2024 3 FD52 08 E111 D 9011101D 069 9/25/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062326507846 $1,326.01
2024 3 FD52 08 E111 D 9011101D 069 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507846 $953.41
2024 3 FD52 08 E121 D 9011101D 069 9/25/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062326507846 $95.88
2024 3 FD52 08 E121 D 9011101D 069 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507846 $68.94
2024 3 FD52 08 E122 D 9011101D 069 9/25/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062326507846 $877.43
2024 3 FD52 08 E122 D 9011101D 069 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507846 $630.87
2024 3 FD52 08 E123 D 9011101D 069 9/25/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062326507846 $256.92
2024 3 FD52 08 E123 D 9011101D 069 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507846 $182.41
2024 3 FD52 08 E124 D 9011101D 069 9/25/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092N1062326507846 $0.36
2024 3 FD52 08 E124 D 9011101D 069 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507846 $0.27
2024 3 FD52 08 E229 D 9011101D 069 9/13/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162523253012140 $18.60
2024 3 FD52 08 E111 D 9011101D 069 9/11/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091N1062325106502 $2,539.22
2024 3 FD52 08 E111 D 9011101D 069 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106502 $135.47
2024 3 FD52 08 E121 D 9011101D 069 9/11/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091N1062325106502 $183.91
2024 3 FD52 08 E121 D 9011101D 069 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106502 $10.20
2024 3 FD52 08 E122 D 9011101D 069 9/11/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091N1062325106502 $1,680.20
2024 3 FD52 08 E122 D 9011101D 069 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106502 $89.65
2024 3 FD52 08 E123 D 9011101D 069 9/11/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091N1062325106502 $435.43
2024 3 FD52 08 E123 D 9011101D 069 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106502 $18.68
2024 2 FD52 08 E229 D 9011101D 069 8/29/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162523237013650 $31.20
2024 2 FD52 08 E111 D 9011101D 069 8/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082N1062323505572 $3,458.14
2024 2 FD52 08 E111 D 9011101D 069 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323505572 $463.92
2024 2 FD52 08 E121 D 9011101D 069 8/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082N1062323505572 $256.87
2024 2 FD52 08 E121 D 9011101D 069 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323505572 $34.56
2024 2 FD52 08 E122 D 9011101D 069 8/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082N1062323505572 $2,288.84
2024 2 FD52 08 E122 D 9011101D 069 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323505572 $306.96
2024 2 FD52 08 E123 D 9011101D 069 8/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082N1062323505572 $532.93
2024 2 FD52 08 E123 D 9011101D 069 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323505572 $69.13
2024 2 FD52 08 E124 D 9011101D 069 8/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082N1062323505572 $1.12
2024 2 FD52 08 E124 D 9011101D 069 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323505572 $0.15
2024 2 FD52 08 E122 D 9011101D 069 8/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081N1062322004362 $1,447.16
2024 2 FD52 08 E122 D 9011101D 069 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322004362 $53.15
2024 2 FD52 08 E123 D 9011101D 069 8/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081N1062322004362 $301.48
2024 2 FD52 08 E123 D 9011101D 069 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322004362 $8.38
2024 2 FD52 08 E111 D 9011101D 069 8/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081N1062322004362 $2,187.03
2024 2 FD52 08 E111 D 9011101D 069 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322004362 $80.32
2024 2 FD52 08 E121 D 9011101D 069 8/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081N1062322004362 $162.04
2024 2 FD52 08 E121 D 9011101D 069 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322004362 $6.09
2024 1 FD52 08 E111 D 9011101D 069 7/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072N1062320203329 $3,044.23
2024 1 FD52 08 E111 D 9011101D 069 7/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320203329 $811.11
2024 1 FD52 08 E121 D 9011101D 069 7/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072N1062320203329 $226.82
2024 1 FD52 08 E121 D 9011101D 069 7/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320203329 $60.46
2024 1 FD52 08 E122 D 9011101D 069 7/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072N1062320203329 $2,014.47
2024 1 FD52 08 E122 D 9011101D 069 7/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320203329 $536.71
2024 1 FD52 08 E123 D 9011101D 069 7/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072N1062320203329 $441.52
2024 1 FD52 08 E123 D 9011101D 069 7/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320203329 $115.53
2024 1 FD52 08 E124 D 9011101D 069 7/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072N1062320203329 $0.90
2024 1 FD52 08 E124 D 9011101D 069 7/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320203329 $0.26
2024 1 FD52 08 E111 D 9011101D 069 7/14/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071N1062319102128 $2,400.22
2024 1 FD52 08 E111 D 9011101D 069 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319102128 $166.26
2024 1 FD52 08 E121 D 9011101D 069 7/14/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071N1062319102128 $172.81
2024 1 FD52 08 E121 D 9011101D 069 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319102128 $12.51
2024 1 FD52 08 E122 D 9011101D 069 7/14/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071N1062319102128 $1,872.42
2024 1 FD52 08 E122 D 9011101D 069 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319102128 $129.69
2024 1 FD52 08 E123 D 9011101D 069 7/14/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071N1062319102128 $423.40
2024 1 FD52 08 E123 D 9011101D 069 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319102128 $22.66
2023 12 FD52 08 E111 D 9011101D 069 6/26/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062N1062317401031 $2,006.35
2023 12 FD52 08 E111 D 9011101D 069 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317401031 $840.22
2023 12 FD52 08 E121 D 9011101D 069 6/26/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062N1062317401031 $149.29
2023 12 FD52 08 E121 D 9011101D 069 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317401031 $62.40
2023 12 FD52 08 E122 D 9011101D 069 6/26/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062N1062317401031 $1,565.13
2023 12 FD52 08 E122 D 9011101D 069 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317401031 $655.37
2023 12 FD52 08 E123 D 9011101D 069 6/26/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062N1062317401031 $327.99
2023 12 FD52 08 E123 D 9011101D 069 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317401031 $143.49
2023 12 FD52 08 E124 D 9011101D 069 6/26/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062N1062317401031 $0.70
2023 12 FD52 08 E124 D 9011101D 069 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317401031 $0.33
2023 12 FD52 08 E111 D 9011101D 069 6/8/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061N1062315810654 $2,221.82
2023 12 FD52 08 E111 D 9011101D 069 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810654 $966.34
2023 12 FD52 08 E121 D 9011101D 069 6/8/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061N1062315810654 $163.25
2023 12 FD52 08 E121 D 9011101D 069 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810654 $70.70
2023 12 FD52 08 E122 D 9011101D 069 6/8/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061N1062315810654 $1,733.44
2023 12 FD52 08 E122 D 9011101D 069 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810654 $753.77
2023 12 FD52 08 E123 D 9011101D 069 6/8/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061N1062315810654 $356.95
2023 12 FD52 08 E123 D 9011101D 069 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810654 $153.02
2023 12 FD52 08 E143 D 9011101D 069 6/1/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300235153 PON21900004878 QK4 INC $8,268.72 Lincoln County 8-167
2023 11 FD52 08 E111 D 9011101D 069 5/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052N1062314309619 $3,018.02
2023 11 FD52 08 E111 D 9011101D 069 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309619 $185.51
2023 11 FD52 08 E121 D 9011101D 069 5/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052N1062314309619 $219.98
2023 11 FD52 08 E121 D 9011101D 069 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309619 $14.01
2023 11 FD52 08 E122 D 9011101D 069 5/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052N1062314309619 $2,354.02
2023 11 FD52 08 E122 D 9011101D 069 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309619 $144.70
2023 11 FD52 08 E123 D 9011101D 069 5/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052N1062314309619 $621.15
2023 11 FD52 08 E123 D 9011101D 069 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309619 $25.56
2023 11 FD52 08 E124 D 9011101D 069 5/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052N1062314309619 $1.11
2023 11 FD52 08 E124 D 9011101D 069 5/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309619 $0.07
2023 11 FD52 08 E111 D 9011101D 069 5/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051N1062312808497 $1,516.75
2023 11 FD52 08 E111 D 9011101D 069 5/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808497 $247.20
2023 11 FD52 08 E121 D 9011101D 069 5/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051N1062312808497 $108.46
2023 11 FD52 08 E121 D 9011101D 069 5/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808497 $17.16
2023 11 FD52 08 E122 D 9011101D 069 5/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051N1062312808497 $1,183.04
2023 11 FD52 08 E122 D 9011101D 069 5/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808497 $192.82
2023 11 FD52 08 E123 D 9011101D 069 5/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051N1062312808497 $325.26
2023 11 FD52 08 E123 D 9011101D 069 5/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808497 $60.34
2023 11 FD52 08 E143 D 9011101D 069 5/3/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300210824 PON21900004878 QK4 INC $17,188.36 Lincoln County 8-167
2023 10 FD52 08 E111 D 9011101D 069 4/28/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042N1062311107545 $2,867.97
2023 10 FD52 08 E111 D 9011101D 069 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311107545 $902.43
2023 10 FD52 08 E121 D 9011101D 069 4/28/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042N1062311107545 $214.28
2023 10 FD52 08 E121 D 9011101D 069 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311107545 $65.63
2023 10 FD52 08 E122 D 9011101D 069 4/28/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042N1062311107545 $2,237.24
2023 10 FD52 08 E122 D 9011101D 069 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311107545 $703.91
2023 10 FD52 08 E123 D 9011101D 069 4/28/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042N1062311107545 $487.51
2023 10 FD52 08 E123 D 9011101D 069 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311107545 $187.67
2023 10 FD52 08 E124 D 9011101D 069 4/28/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042N1062311107545 $1.11
2023 10 FD52 08 E124 D 9011101D 069 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311107545 $0.33
2023 10 FD52 08 E111 D 9011101D 069 4/10/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041N1062309606382 $1,487.02
2023 10 FD52 08 E111 D 9011101D 069 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309606382 $277.04
2023 10 FD52 08 E121 D 9011101D 069 4/10/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041N1062309606382 $105.60
2023 10 FD52 08 E121 D 9011101D 069 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309606382 $19.30
2023 10 FD52 08 E122 D 9011101D 069 4/10/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041N1062309606382 $1,159.79
2023 10 FD52 08 E122 D 9011101D 069 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309606382 $216.09
2023 10 FD52 08 E123 D 9011101D 069 4/10/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041N1062309606382 $329.78
2023 10 FD52 08 E123 D 9011101D 069 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309606382 $66.58
2023 9 FD52 08 E111 D 9011101D 069 3/27/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032N1062308305244 $1,906.78
2023 9 FD52 08 E111 D 9011101D 069 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308305244 $51.97
2023 9 FD52 08 E121 D 9011101D 069 3/27/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032N1062308305244 $141.04
2023 9 FD52 08 E121 D 9011101D 069 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308305244 $3.95
2023 9 FD52 08 E122 D 9011101D 069 3/27/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032N1062308305244 $1,487.22
2023 9 FD52 08 E122 D 9011101D 069 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308305244 $40.54
2023 9 FD52 08 E123 D 9011101D 069 3/27/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032N1062308305244 $315.37
2023 9 FD52 08 E123 D 9011101D 069 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308305244 $5.39
2023 9 FD52 08 E124 D 9011101D 069 3/27/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032N1062308305244 $0.59
2023 9 FD52 08 E124 D 9011101D 069 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308305244 $0.01
2023 9 FD52 08 E111 D 9011101D 069 3/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031N1062306704095 $1,902.42
2023 9 FD52 08 E111 D 9011101D 069 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306704095 $190.19
2023 9 FD52 08 E121 D 9011101D 069 3/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031N1062306704095 $136.99
2023 9 FD52 08 E121 D 9011101D 069 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306704095 $14.31
2023 9 FD52 08 E122 D 9011101D 069 3/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031N1062306704095 $1,483.88
2023 9 FD52 08 E122 D 9011101D 069 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306704095 $148.34
2023 9 FD52 08 E123 D 9011101D 069 3/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031N1062306704095 $384.09
2023 9 FD52 08 E123 D 9011101D 069 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306704095 $28.05
2023 8 FD52 08 E121 D 9011101D 069 2/23/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022N1062305303161 $50.59
2023 8 FD52 08 E121 D 9011101D 069 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305303161 $2.22
2023 8 FD52 08 E122 D 9011101D 069 2/23/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022N1062305303161 $519.65
2023 8 FD52 08 E122 D 9011101D 069 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305303161 $22.86
2023 8 FD52 08 E123 D 9011101D 069 2/23/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022N1062305303161 $70.02
2023 8 FD52 08 E123 D 9011101D 069 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305303161 $3.04
2023 8 FD52 08 E124 D 9011101D 069 2/23/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022N1062305303161 $0.18
2023 8 FD52 08 E124 D 9011101D 069 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305303161 $0.01
2023 8 FD52 08 E111 D 9011101D 069 2/23/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022N1062305303160 $666.33
2023 8 FD52 08 E111 D 9011101D 069 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305303160 $29.31
2023 8 FD52 08 E143 D 9011101D 069 2/21/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300156900 PON21900004878 QK4 INC $2,141.30 Lincoln County 8-167
2023 8 FD52 08 E111 D 9011101D 069 2/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021N1062303901916 $1,461.85
2023 8 FD52 08 E111 D 9011101D 069 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901916 $140.60
2023 8 FD52 08 E121 D 9011101D 069 2/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021N1062303901916 $104.18
2023 8 FD52 08 E121 D 9011101D 069 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901916 $10.06
2023 8 FD52 08 E122 D 9011101D 069 2/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021N1062303901916 $1,140.24
2023 8 FD52 08 E122 D 9011101D 069 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901916 $109.67
2023 8 FD52 08 E123 D 9011101D 069 2/9/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021N1062303901916 $294.38
2023 8 FD52 08 E123 D 9011101D 069 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901916 $27.32
2023 7 FD52 08 E143 D 9011101D 069 1/27/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300136496 PON21900004878 QK4 INC $23,751.97 Lincoln County 8-167
2023 7 FD52 08 E111 D 9011101D 069 1/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012N1062302300906 $1,232.89
2023 7 FD52 08 E111 D 9011101D 069 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300906 $169.52
2023 7 FD52 08 E121 D 9011101D 069 1/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012N1062302300906 $92.06
2023 7 FD52 08 E121 D 9011101D 069 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300906 $12.65
2023 7 FD52 08 E122 D 9011101D 069 1/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012N1062302300906 $961.77
2023 7 FD52 08 E122 D 9011101D 069 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300906 $132.22
2023 7 FD52 08 E123 D 9011101D 069 1/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012N1062302300906 $185.30
2023 7 FD52 08 E123 D 9011101D 069 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300906 $25.52
2023 7 FD52 08 E124 D 9011101D 069 1/24/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012N1062302300906 $0.40
2023 7 FD52 08 E124 D 9011101D 069 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300906 $0.05
2023 7 FD52 08 E111 D 9011101D 069 1/12/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011N1062300610644 $909.34
2023 7 FD52 08 E111 D 9011101D 069 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610644 $1,550.25
2023 7 FD52 08 E121 D 9011101D 069 1/12/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011N1062300610644 $67.21
2023 7 FD52 08 E121 D 9011101D 069 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610644 $109.34
2023 7 FD52 08 E122 D 9011101D 069 1/12/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011N1062300610644 $709.38
2023 7 FD52 08 E122 D 9011101D 069 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610644 $1,209.20
2023 7 FD52 08 E123 D 9011101D 069 1/12/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011N1062300610644 $136.58
2023 7 FD52 08 E123 D 9011101D 069 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610644 $332.67
2023 6 FD52 08 E111 D 9011101D 069 12/22/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122M1062235509752 $2,548.61
2023 6 FD52 08 E121 D 9011101D 069 12/22/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122M1062235509752 $187.29
2023 6 FD52 08 E122 D 9011101D 069 12/22/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122M1062235509752 $1,987.91
2023 6 FD52 08 E123 D 9011101D 069 12/22/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122M1062235509752 $409.28
2023 6 FD52 08 E124 D 9011101D 069 12/22/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122M1062235509752 $0.81
2023 6 FD52 08 E111 D 9011101D 069 12/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121M1062234208638 $1,396.04
2023 6 FD52 08 E111 D 9011101D 069 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208638 $310.06
2023 6 FD52 08 E121 D 9011101D 069 12/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121M1062234208638 $99.84
2023 6 FD52 08 E121 D 9011101D 069 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208638 $22.17
2023 6 FD52 08 E122 D 9011101D 069 12/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121M1062234208638 $1,089.18
2023 6 FD52 08 E122 D 9011101D 069 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208638 $241.84
2023 6 FD52 08 E123 D 9011101D 069 12/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121M1062234208638 $233.29
2023 6 FD52 08 E123 D 9011101D 069 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208638 $51.18
2023 5 FD52 08 E111 D 9011101D 069 11/23/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112M1062232607697 $2,886.50
2023 5 FD52 08 E111 D 9011101D 069 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607697 $927.27
2023 5 FD52 08 E121 D 9011101D 069 11/23/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112M1062232607697 $215.62
2023 5 FD52 08 E121 D 9011101D 069 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607697 $69.54
2023 5 FD52 08 E122 D 9011101D 069 11/23/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112M1062232607697 $2,251.54
2023 5 FD52 08 E122 D 9011101D 069 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607697 $723.27
2023 5 FD52 08 E123 D 9011101D 069 11/23/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112M1062232607697 $414.76
2023 5 FD52 08 E123 D 9011101D 069 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607697 $123.08
2023 5 FD52 08 E124 D 9011101D 069 11/23/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112M1062232607697 $1.04
2023 5 FD52 08 E124 D 9011101D 069 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607697 $0.33
2023 5 FD52 08 E111 D 9011101D 069 11/7/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111M1062230806604 $2,646.21
2023 5 FD52 08 E111 D 9011101D 069 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806604 $192.45
2023 5 FD52 08 E121 D 9011101D 069 11/7/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111M1062230806604 $190.06
2023 5 FD52 08 E121 D 9011101D 069 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806604 $14.54
2023 5 FD52 08 E122 D 9011101D 069 11/7/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111M1062230806604 $2,063.85
2023 5 FD52 08 E122 D 9011101D 069 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806604 $150.11
2023 5 FD52 08 E123 D 9011101D 069 11/7/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111M1062230806604 $457.01
2023 5 FD52 08 E123 D 9011101D 069 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806604 $22.30
2023 5 FD52 08 E143 D 9011101D 069 11/1/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300079515 PON21900004878 QK4 INC $6,094.48 Lincoln County 8-167
2023 4 FD52 08 E111 D 9011101D 069 10/31/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102M1062229405649 $1,483.00
2023 4 FD52 08 E111 D 9011101D 069 10/31/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405649 $1,438.78
2023 4 FD52 08 E121 D 9011101D 069 10/31/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102M1062229405649 $109.63
2023 4 FD52 08 E121 D 9011101D 069 10/31/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405649 $104.81
2023 4 FD52 08 E122 D 9011101D 069 10/31/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102M1062229405649 $1,156.58
2023 4 FD52 08 E122 D 9011101D 069 10/31/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405649 $1,122.24
2023 4 FD52 08 E123 D 9011101D 069 10/31/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102M1062229405649 $231.63
2023 4 FD52 08 E123 D 9011101D 069 10/31/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405649 $264.81
2023 4 FD52 08 E124 D 9011101D 069 10/31/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102M1062229405649 $0.50
2023 4 FD52 08 E124 D 9011101D 069 10/31/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405649 $0.53
2023 4 FD52 08 E111 D 9011101D 069 10/10/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101M1062228004506 $2,468.42
2023 4 FD52 08 E111 D 9011101D 069 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228004506 $87.90
2023 4 FD52 08 E121 D 9011101D 069 10/10/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101M1062228004506 $176.56
2023 4 FD52 08 E121 D 9011101D 069 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228004506 $6.61
2023 4 FD52 08 E122 D 9011101D 069 10/10/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101M1062228004506 $1,925.61
2023 4 FD52 08 E122 D 9011101D 069 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228004506 $68.56
2023 4 FD52 08 E123 D 9011101D 069 10/10/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101M1062228004506 $439.76
2023 4 FD52 08 E123 D 9011101D 069 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228004506 $12.10
2023 3 FD52 08 E111 D 9011101D 069 9/26/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092M1062226603427 $2,601.75
2023 3 FD52 08 E111 D 9011101D 069 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226603427 $463.20
2023 3 FD52 08 E121 D 9011101D 069 9/26/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092M1062226603427 $189.93
2023 3 FD52 08 E121 D 9011101D 069 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226603427 $34.41
2023 3 FD52 08 E122 D 9011101D 069 9/26/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092M1062226603427 $2,029.54
2023 3 FD52 08 E122 D 9011101D 069 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226603427 $361.30
2023 3 FD52 08 E123 D 9011101D 069 9/26/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092M1062226603427 $457.15
2023 3 FD52 08 E123 D 9011101D 069 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226603427 $65.36
2023 3 FD52 08 E124 D 9011101D 069 9/26/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092M1062226603427 $0.89
2023 3 FD52 08 E124 D 9011101D 069 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226603427 $0.13
2023 3 FD52 08 E111 D 9011101D 069 9/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091M1062225102216 $1,860.70
2023 3 FD52 08 E111 D 9011101D 069 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225102216 $123.84
2023 3 FD52 08 E121 D 9011101D 069 9/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091M1062225102216 $133.39
2023 3 FD52 08 E121 D 9011101D 069 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225102216 $8.57
2023 3 FD52 08 E122 D 9011101D 069 9/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091M1062225102216 $1,451.28
2023 3 FD52 08 E122 D 9011101D 069 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225102216 $96.59
2023 3 FD52 08 E123 D 9011101D 069 9/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091M1062225102216 $322.78
2023 3 FD52 08 E123 D 9011101D 069 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225102216 $25.02
2023 2 FD52 08 E111 D 9011101D 069 8/24/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082M1062223501084 $2,411.53
2023 2 FD52 08 E111 D 9011101D 069 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223501084 $782.56
2023 2 FD52 08 E121 D 9011101D 069 8/24/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082M1062223501084 $179.19
2023 2 FD52 08 E121 D 9011101D 069 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223501084 $56.28
2023 2 FD52 08 E122 D 9011101D 069 8/24/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082M1062223501084 $1,881.00
2023 2 FD52 08 E122 D 9011101D 069 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223501084 $610.40
2023 2 FD52 08 E123 D 9011101D 069 8/24/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082M1062223501084 $359.22
2023 2 FD52 08 E123 D 9011101D 069 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223501084 $156.15
2023 2 FD52 08 E124 D 9011101D 069 8/24/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082M1062223501084 $0.84
2023 2 FD52 08 E124 D 9011101D 069 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223501084 $0.27
2023 2 FD52 08 E121 D 9011101D 069 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110654 $3.54
2023 2 FD52 08 E122 D 9011101D 069 8/10/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081M1062222110654 $3,243.23
2023 2 FD52 08 E122 D 9011101D 069 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110654 $40.90
2023 2 FD52 08 E123 D 9011101D 069 8/10/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081M1062222110654 $666.88
2023 2 FD52 08 E123 D 9011101D 069 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110654 $12.01
2023 2 FD52 08 E111 D 9011101D 069 8/10/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081M1062222110653 $4,157.84
2023 2 FD52 08 E111 D 9011101D 069 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110653 $52.44
2023 2 FD52 08 E121 D 9011101D 069 8/10/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081M1062222110653 $302.01
2023 1 FD52 08 E121 D 9011101D 069 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220309603 $42.66
2023 1 FD52 08 E122 D 9011101D 069 7/25/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072M1062220309603 $2,267.00
2023 1 FD52 08 E122 D 9011101D 069 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220309603 $458.55
2023 1 FD52 08 E123 D 9011101D 069 7/25/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072M1062220309603 $464.11
2023 1 FD52 08 E123 D 9011101D 069 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220309603 $111.72
2023 1 FD52 08 E124 D 9011101D 069 7/25/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072M1062220309603 $1.03
2023 1 FD52 08 E124 D 9011101D 069 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220309603 $0.23
2023 1 FD52 08 E111 D 9011101D 069 7/25/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072M1062220309603 $2,906.23
2023 1 FD52 08 E111 D 9011101D 069 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220309603 $587.89
2023 1 FD52 08 E121 D 9011101D 069 7/25/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072M1062220309603 $215.10
2023 1 FD52 08 E111 D 9011101D 069 7/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071M1062219208452 $1,989.88
2023 1 FD52 08 E111 D 9011101D 069 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219208452 $30.84
2023 1 FD52 08 E121 D 9011101D 069 7/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071M1062219208452 $142.10
2023 1 FD52 08 E121 D 9011101D 069 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219208452 $2.34
2023 1 FD52 08 E122 D 9011101D 069 7/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071M1062219208452 $1,670.90
2023 1 FD52 08 E122 D 9011101D 069 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219208452 $25.90
2023 1 FD52 08 E123 D 9011101D 069 7/12/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071M1062219208452 $384.06
2023 1 FD52 08 E123 D 9011101D 069 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219208452 $3.17
2023 1 FD52 08 E143 D 9011101D 069 7/5/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300001132 PON21900004878 QK4 INC $4,677.92 Lincoln County 8-167
2022 12 FD52 08 E111 D 9011101D 069 6/27/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062M1062217507353 $3,378.43
2022 12 FD52 08 E111 D 9011101D 069 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217507353 $792.27
2022 12 FD52 08 E121 D 9011101D 069 6/27/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062M1062217507353 $249.72
2022 12 FD52 08 E121 D 9011101D 069 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217507353 $59.25
2022 12 FD52 08 E122 D 9011101D 069 6/27/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062M1062217507353 $2,836.87
2022 12 FD52 08 E122 D 9011101D 069 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217507353 $665.27
2022 12 FD52 08 E123 D 9011101D 069 6/27/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062M1062217507353 $570.83
2022 12 FD52 08 E123 D 9011101D 069 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217507353 $112.61
2022 12 FD52 08 E124 D 9011101D 069 6/27/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062M1062217507353 $1.26
2022 12 FD52 08 E124 D 9011101D 069 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217507353 $0.30
2022 12 FD52 08 E111 D 9011101D 069 6/14/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061M1062215906217 $2,810.89
2022 12 FD52 08 E111 D 9011101D 069 6/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215906217 $717.85
2022 12 FD52 08 E121 D 9011101D 069 6/14/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061M1062215906217 $207.20
2022 12 FD52 08 E121 D 9011101D 069 6/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215906217 $52.21
2022 12 FD52 08 E122 D 9011101D 069 6/14/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061M1062215906217 $2,360.68
2022 12 FD52 08 E122 D 9011101D 069 6/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215906217 $602.78
2022 12 FD52 08 E123 D 9011101D 069 6/14/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061M1062215906217 $426.63
2022 12 FD52 08 E123 D 9011101D 069 6/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215906217 $113.90
2022 11 FD52 08 E123 D 9011101D 069 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214005201 $73.59
2022 11 FD52 08 E124 D 9011101D 069 5/23/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052M1062214005201 $1.29
2022 11 FD52 08 E124 D 9011101D 069 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214005201 $0.13
2022 11 FD52 08 E111 D 9011101D 069 5/23/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052M1062214005200 $3,381.73
2022 11 FD52 08 E111 D 9011101D 069 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214005200 $319.62
2022 11 FD52 08 E121 D 9011101D 069 5/23/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052M1062214005200 $250.47
2022 11 FD52 08 E121 D 9011101D 069 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214005200 $22.80
2022 11 FD52 08 E122 D 9011101D 069 5/23/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052M1062214005200 $2,839.63
2022 11 FD52 08 E122 D 9011101D 069 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214005200 $268.38
2022 11 FD52 08 E123 D 9011101D 069 5/23/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052M1062214005200 $564.54
2022 11 FD52 08 E111 D 9011101D 069 5/13/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051M1062212604122 $1,855.35
2022 11 FD52 08 E111 D 9011101D 069 5/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212604122 $321.29
2022 11 FD52 08 E121 D 9011101D 069 5/13/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051M1062212604122 $137.26
2022 11 FD52 08 E121 D 9011101D 069 5/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212604123 $23.12
2022 11 FD52 08 E122 D 9011101D 069 5/9/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051M1062212604123 $1,557.99
2022 11 FD52 08 E122 D 9011101D 069 5/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212604123 $269.78
2022 11 FD52 08 E123 D 9011101D 069 5/9/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051M1062212604123 $334.23
2022 11 FD52 08 E123 D 9011101D 069 5/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212604123 $68.62
2022 10 FD52 08 E111 D 9011101D 069 4/28/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042M1062211203139 $2,670.93
2022 10 FD52 08 E111 D 9011101D 069 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211203139 $869.29
2022 10 FD52 08 E121 D 9011101D 069 4/28/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042M1062211203139 $197.22
2022 10 FD52 08 E121 D 9011101D 069 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211203139 $62.81
2022 10 FD52 08 E122 D 9011101D 069 4/28/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042M1062211203139 $2,242.96
2022 10 FD52 08 E122 D 9011101D 069 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211203139 $729.95
2022 10 FD52 08 E123 D 9011101D 069 4/28/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042M1062211203139 $467.66
2022 10 FD52 08 E123 D 9011101D 069 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211203139 $176.52
2022 10 FD52 08 E124 D 9011101D 069 4/28/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042M1062211203139 $1.04
2022 10 FD52 08 E124 D 9011101D 069 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211203139 $0.34
2022 10 FD52 08 E229 D 9011101D 069 4/26/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162522115010190 $61.50
2022 10 FD52 08 E229 D 9011101D 069 4/13/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162522100006750 $2.30
2022 10 FD52 08 E111 D 9011101D 069 4/13/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041M1062209801985 $2,345.64
2022 10 FD52 08 E111 D 9011101D 069 4/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801985 $48.58
2022 10 FD52 08 E121 D 9011101D 069 4/13/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041M1062209801985 $175.47
2022 10 FD52 08 E121 D 9011101D 069 4/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801985 $3.46
2022 10 FD52 08 E122 D 9011101D 069 4/13/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041M1062209801985 $1,969.54
2022 10 FD52 08 E122 D 9011101D 069 4/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801985 $40.80
2022 10 FD52 08 E123 D 9011101D 069 4/13/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041M1062209801985 $338.14
2022 10 FD52 08 E123 D 9011101D 069 4/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801985 $11.57
2022 9 FD52 08 E229 D 9011101D 069 3/28/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162522084010110 $52.50
2022 9 FD52 08 E111 D 9011101D 069 3/24/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032M1062208200959 $2,336.19
2022 9 FD52 08 E111 D 9011101D 069 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200959 $187.33
2022 9 FD52 08 E121 D 9011101D 069 3/24/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032M1062208200959 $172.88
2022 9 FD52 08 E121 D 9011101D 069 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200959 $13.54
2022 9 FD52 08 E122 D 9011101D 069 3/24/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032M1062208200959 $1,961.65
2022 9 FD52 08 E122 D 9011101D 069 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200959 $157.31
2022 9 FD52 08 E123 D 9011101D 069 3/24/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032M1062208200959 $391.93
2022 9 FD52 08 E123 D 9011101D 069 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200959 $40.01
2022 9 FD52 08 E124 D 9011101D 069 3/24/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032M1062208200959 $0.91
2022 9 FD52 08 E124 D 9011101D 069 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200959 $0.08
2022 9 FD52 08 E111 D 9011101D 069 3/9/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031M1062206709868 $1,980.59
2022 9 FD52 08 E111 D 9011101D 069 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709868 $18.57
2022 9 FD52 08 E121 D 9011101D 069 3/9/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031M1062206709868 $148.33
2022 9 FD52 08 E121 D 9011101D 069 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709868 $1.39
2022 9 FD52 08 E122 D 9011101D 069 3/9/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031M1062206709868 $1,663.10
2022 9 FD52 08 E122 D 9011101D 069 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709868 $15.59
2022 9 FD52 08 E123 D 9011101D 069 3/9/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031M1062206709868 $284.85
2022 9 FD52 08 E123 D 9011101D 069 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709868 $3.19
2022 8 FD52 08 E111 D 9011101D 069 2/25/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022M1062205308960 $3,596.03
2022 8 FD52 08 E111 D 9011101D 069 2/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022M1062205308960 $624.06
2022 8 FD52 08 E121 D 9011101D 069 2/25/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022M1062205308960 $265.93
2022 8 FD52 08 E121 D 9011101D 069 2/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022M1062205308960 $45.94
2022 8 FD52 08 E122 D 9011101D 069 2/25/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022M1062205308960 $3,019.69
2022 8 FD52 08 E122 D 9011101D 069 2/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022M1062205308960 $524.02
2022 8 FD52 08 E123 D 9011101D 069 2/25/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022M1062205308960 $601.33
2022 8 FD52 08 E123 D 9011101D 069 2/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022M1062205308960 $102.41
2022 8 FD52 08 E124 D 9011101D 069 2/25/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022M1062205308960 $1.36
2022 8 FD52 08 E124 D 9011101D 069 2/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022M1062205308960 $0.22
2022 8 FD52 08 E123 D 9011101D 069 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907873 $41.88
2022 8 FD52 08 E111 D 9011101D 069 2/9/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021M1062203907873 $2,508.05
2022 8 FD52 08 E111 D 9011101D 069 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907873 $264.55
2022 8 FD52 08 E121 D 9011101D 069 2/9/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021M1062203907873 $187.17
2022 8 FD52 08 E121 D 9011101D 069 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907873 $19.75
2022 8 FD52 08 E122 D 9011101D 069 2/9/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021M1062203907873 $2,106.07
2022 8 FD52 08 E122 D 9011101D 069 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907873 $222.15
2022 8 FD52 08 E123 D 9011101D 069 2/9/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021M1062203907873 $400.82
2022 7 FD52 08 E111 D 9011101D 069 1/27/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012M1062202106906 $2,922.15
2022 7 FD52 08 E111 D 9011101D 069 1/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012M1062202106906 $154.46
2022 7 FD52 08 E121 D 9011101D 069 1/27/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012M1062202106906 $217.05
2022 7 FD52 08 E121 D 9011101D 069 1/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012M1062202106906 $11.19
2022 7 FD52 08 E122 D 9011101D 069 1/27/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012M1062202106906 $2,453.65
2022 7 FD52 08 E122 D 9011101D 069 1/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012M1062202106906 $129.69
2022 7 FD52 08 E123 D 9011101D 069 1/27/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012M1062202106906 $467.06
2022 7 FD52 08 E123 D 9011101D 069 1/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012M1062202106906 $32.76
2022 7 FD52 08 E124 D 9011101D 069 1/27/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012M1062202106906 $1.10
2022 7 FD52 08 E124 D 9011101D 069 1/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012M1062202106906 $0.06
2022 7 FD52 08 E111 D 9011101D 069 1/14/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011M1062200705896 $1,290.03
2022 7 FD52 08 E111 D 9011101D 069 1/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705896 $1,111.00
2022 7 FD52 08 E121 D 9011101D 069 1/14/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011M1062200705896 $95.32
2022 7 FD52 08 E121 D 9011101D 069 1/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705896 $82.53
2022 7 FD52 08 E122 D 9011101D 069 1/14/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011M1062200705896 $1,083.20
2022 7 FD52 08 E122 D 9011101D 069 1/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705896 $932.91
2022 7 FD52 08 E123 D 9011101D 069 1/14/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011M1062200705896 $230.35
2022 7 FD52 08 E123 D 9011101D 069 1/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705896 $183.24
2022 7 FD52 08 E143 D 9011101D 069 1/11/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200114957 PON21900004878 QK4 INC $3,329.68 Lincoln County 8-167
2022 7 FD52 08 E111 D 9011101D 069 1/6/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122L1062135505040 $2,715.21
2022 7 FD52 08 E111 D 9011101D 069 1/6/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135505040 $195.39
2022 7 FD52 08 E121 D 9011101D 069 1/6/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122L1062135505040 $198.46
2022 7 FD52 08 E121 D 9011101D 069 1/6/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135505040 $14.69
2022 7 FD52 08 E122 D 9011101D 069 1/6/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122L1062135505040 $2,279.95
2022 7 FD52 08 E122 D 9011101D 069 1/6/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135505040 $164.07
2022 7 FD52 08 E123 D 9011101D 069 1/6/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122L1062135505040 $508.08
2022 7 FD52 08 E123 D 9011101D 069 1/6/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135505040 $28.72
2022 7 FD52 08 E124 D 9011101D 069 1/6/2022 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122L1062135505040 $1.09
2022 7 FD52 08 E124 D 9011101D 069 1/6/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135505040 $0.09
2022 6 FD52 08 E111 D 9011101D 069 12/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121L1062134103946 $1,185.48
2022 6 FD52 08 E111 D 9011101D 069 12/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103946 $550.09
2022 6 FD52 08 E121 D 9011101D 069 12/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121L1062134103946 $85.26
2022 6 FD52 08 E121 D 9011101D 069 12/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103946 $39.17
2022 6 FD52 08 E122 D 9011101D 069 12/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121L1062134103946 $995.57
2022 6 FD52 08 E122 D 9011101D 069 12/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103946 $461.91
2022 6 FD52 08 E123 D 9011101D 069 12/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121L1062134103946 $231.79
2022 6 FD52 08 E123 D 9011101D 069 12/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103946 $109.27
2022 5 FD52 08 E111 D 9011101D 069 11/29/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112L1062132603031 $2,309.14
2022 5 FD52 08 E111 D 9011101D 069 11/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132603031 $505.51
2022 5 FD52 08 E121 D 9011101D 069 11/29/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112L1062132603031 $169.00
2022 5 FD52 08 E121 D 9011101D 069 11/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132603031 $37.53
2022 5 FD52 08 E122 D 9011101D 069 11/29/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112L1062132603031 $1,938.97
2022 5 FD52 08 E122 D 9011101D 069 11/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132603031 $424.47
2022 5 FD52 08 E123 D 9011101D 069 11/29/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112L1062132603031 $424.52
2022 5 FD52 08 E123 D 9011101D 069 11/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132603031 $82.78
2022 5 FD52 08 E124 D 9011101D 069 11/29/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112L1062132603031 $0.91
2022 5 FD52 08 E124 D 9011101D 069 11/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132603031 $0.22
2022 5 FD52 08 E143 D 9011101D 069 11/19/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200088047 PON21900004878 QK4 INC $10,379.38 Lincoln County 8-167
2022 5 FD52 08 E111 D 9011101D 069 11/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111L1062130901980 $1,118.32
2022 5 FD52 08 E111 D 9011101D 069 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901980 $130.84
2022 5 FD52 08 E121 D 9011101D 069 11/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111L1062130901980 $79.93
2022 5 FD52 08 E121 D 9011101D 069 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901980 $9.12
2022 5 FD52 08 E122 D 9011101D 069 11/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111L1062130901980 $939.23
2022 5 FD52 08 E122 D 9011101D 069 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901980 $109.87
2022 5 FD52 08 E123 D 9011101D 069 11/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111L1062130901980 $220.74
2022 5 FD52 08 E123 D 9011101D 069 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901980 $27.69
2022 4 FD52 08 E229 D 9011101D 069 10/27/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162521298010600 $10.00
2022 4 FD52 08 E111 D 9011101D 069 10/25/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102L1062129501000 $1,422.68
2022 4 FD52 08 E111 D 9011101D 069 10/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102L1062129501000 $731.92
2022 4 FD52 08 E121 D 9011101D 069 10/25/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102L1062129501000 $103.91
2022 4 FD52 08 E121 D 9011101D 069 10/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102L1062129501000 $52.05
2022 4 FD52 08 E122 D 9011101D 069 10/25/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102L1062129501000 $1,194.65
2022 4 FD52 08 E122 D 9011101D 069 10/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102L1062129501000 $614.59
2022 4 FD52 08 E123 D 9011101D 069 10/25/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102L1062129501000 $286.11
2022 4 FD52 08 E123 D 9011101D 069 10/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102L1062129501000 $166.74
2022 4 FD52 08 E124 D 9011101D 069 10/25/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102L1062129501000 $0.64
2022 4 FD52 08 E124 D 9011101D 069 10/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102L1062129501000 $0.30
2022 4 FD52 08 E111 D 9011101D 069 10/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101L1062128110619 $803.31
2022 4 FD52 08 E111 D 9011101D 069 10/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101L1062128110619 $6.91
2022 4 FD52 08 E121 D 9011101D 069 10/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101L1062128110619 $58.50
2022 4 FD52 08 E121 D 9011101D 069 10/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101L1062128110619 $0.47
2022 4 FD52 08 E122 D 9011101D 069 10/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101L1062128110619 $674.72
2022 4 FD52 08 E122 D 9011101D 069 10/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101L1062128110619 $5.80
2022 4 FD52 08 E123 D 9011101D 069 10/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101L1062128110619 $147.61
2022 4 FD52 08 E123 D 9011101D 069 10/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101L1062128110619 $1.63
2022 3 FD52 08 E111 D 9011101D 069 9/27/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092L1062126709612 $1,197.51
2022 3 FD52 08 E111 D 9011101D 069 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709612 $125.04
2022 3 FD52 08 E121 D 9011101D 069 9/27/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092L1062126709612 $88.00
2022 3 FD52 08 E121 D 9011101D 069 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709612 $9.19
2022 3 FD52 08 E122 D 9011101D 069 9/27/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092L1062126709612 $1,005.52
2022 3 FD52 08 E122 D 9011101D 069 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709612 $104.99
2022 3 FD52 08 E123 D 9011101D 069 9/27/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092L1062126709612 $231.42
2022 3 FD52 08 E123 D 9011101D 069 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709612 $23.73
2022 3 FD52 08 E124 D 9011101D 069 9/27/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092L1062126709612 $0.54
2022 3 FD52 08 E124 D 9011101D 069 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709612 $0.06
2022 3 FD52 08 E229 D 9011101D 069 9/13/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162521253006340 $4.60
2022 3 FD52 08 E123 D 9011101D 069 9/13/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091L1062125208481 $19.42
2022 3 FD52 08 E111 D 9011101D 069 9/13/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091L1062125208480 $942.75
2022 3 FD52 08 E111 D 9011101D 069 9/13/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091L1062125208480 $82.58
2022 3 FD52 08 E121 D 9011101D 069 9/13/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091L1062125208480 $67.47
2022 3 FD52 08 E121 D 9011101D 069 9/13/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091L1062125208480 $5.52
2022 3 FD52 08 E122 D 9011101D 069 9/13/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091L1062125208480 $791.63
2022 3 FD52 08 E122 D 9011101D 069 9/13/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091L1062125208480 $69.34
2022 3 FD52 08 E123 D 9011101D 069 9/13/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091L1062125208480 $184.41
2022 2 FD52 08 E111 D 9011101D 069 8/27/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082L1062123607476 $751.38
2022 2 FD52 08 E111 D 9011101D 069 8/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123607476 $20.95
2022 2 FD52 08 E121 D 9011101D 069 8/27/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082L1062123607476 $55.35
2022 2 FD52 08 E121 D 9011101D 069 8/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123607476 $1.57
2022 2 FD52 08 E122 D 9011101D 069 8/27/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082L1062123607476 $630.98
2022 2 FD52 08 E122 D 9011101D 069 8/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123607476 $17.59
2022 2 FD52 08 E123 D 9011101D 069 8/27/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082L1062123607476 $142.96
2022 2 FD52 08 E123 D 9011101D 069 8/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123607476 $3.51
2022 2 FD52 08 E124 D 9011101D 069 8/27/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082L1062123607476 $0.35
2022 2 FD52 08 E124 D 9011101D 069 8/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123607476 $0.01
2022 2 FD52 08 E229 D 9011101D 069 8/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162521237006930 $2.76
2022 2 FD52 08 E229 D 9011101D 069 8/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162521237010710 $83.00
2022 2 FD52 08 E143 D 9011101D 069 8/18/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200028824 PON21900004878 QK4 INC $13,552.96 Lincoln County 8-167
2022 2 FD52 08 E229 D 9011101D 069 8/12/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162521223008380 $2.76
2022 2 FD52 08 E111 D 9011101D 069 8/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081L1062121806380 $758.86
2022 2 FD52 08 E111 D 9011101D 069 8/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121806380 $20.73
2022 2 FD52 08 E121 D 9011101D 069 8/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081L1062121806380 $56.94
2022 2 FD52 08 E121 D 9011101D 069 8/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121806380 $1.55
2022 2 FD52 08 E122 D 9011101D 069 8/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081L1062121806380 $637.26
2022 2 FD52 08 E122 D 9011101D 069 8/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121806380 $17.40
2022 2 FD52 08 E123 D 9011101D 069 8/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081L1062121806380 $124.90
2022 2 FD52 08 E123 D 9011101D 069 8/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121806380 $3.47
2022 2 FD52 08 E143 D 9011101D 069 8/10/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200019081 PON21900004878 QK4 INC $9,880.44 Lincoln County 8-167
2022 1 FD52 08 E143 D 9011101D 069 7/29/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200008908 PON22000004379 GEOTECHNOLOGY INC $45,387.91
2022 1 FD52 08 E229 D 9011101D 069 7/29/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162521207009520 $88.00
2022 1 FD52 08 E111 D 9011101D 069 7/29/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072L1062120405313 $1,164.83
2022 1 FD52 08 E111 D 9011101D 069 7/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120405313 $207.04
2022 1 FD52 08 E121 D 9011101D 069 7/29/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072L1062120405313 $86.62
2022 1 FD52 08 E121 D 9011101D 069 7/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120405313 $15.20
2022 1 FD52 08 E122 D 9011101D 069 7/29/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072L1062120405313 $978.18
2022 1 FD52 08 E122 D 9011101D 069 7/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120405313 $173.84
2022 1 FD52 08 E123 D 9011101D 069 7/29/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072L1062120405313 $209.51
2022 1 FD52 08 E123 D 9011101D 069 7/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120405313 $39.59
2022 1 FD52 08 E124 D 9011101D 069 7/29/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072L1062120405313 $0.54
2022 1 FD52 08 E124 D 9011101D 069 7/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120405313 $0.09
2022 1 FD52 00 E111 D 9011101D 069 7/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072L1062120404698 $1,439.20 000001077589-3562500610
2022 1 FD52 00 E111 D 9011101D 069 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404698 $196.45 000001077589-3562500610
2022 1 FD52 00 E121 D 9011101D 069 7/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072L1062120404698 $105.91 000001077589-3562500610
2022 1 FD52 00 E121 D 9011101D 069 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404698 $14.55 000001077589-3562500610
2022 1 FD52 00 E122 D 9011101D 069 7/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072L1062120404698 $1,208.29 000001077589-3562500610
2022 1 FD52 00 E122 D 9011101D 069 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404698 $164.95 000001077589-3562500610
2022 1 FD52 00 E123 D 9011101D 069 7/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072L1062120404698 $248.75 000001077589-3562500610
2022 1 FD52 00 E123 D 9011101D 069 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404698 $28.21 000001077589-3562500610
2022 1 FD52 00 E124 D 9011101D 069 7/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR072L1062120404698 $0.72 000001077589-3562500610
2022 1 FD52 00 E124 D 9011101D 069 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404698 $0.09 000001077589-3562500610
2022 1 FD52 08 E229 D 9011101D 069 7/12/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162521192002840 $64.50
2022 1 FD52 00 E111 D 9011101D 069 7/12/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071L1062119003561 $2,256.76 000001077589-3562500610
2022 1 FD52 00 E111 D 9011101D 069 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003561 $55.48 000001077589-3562500610
2022 1 FD52 00 E121 D 9011101D 069 7/12/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071L1062119003561 $165.87 000001077589-3562500610
2022 1 FD52 00 E121 D 9011101D 069 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003561 $4.02 000001077589-3562500610
2022 1 FD52 00 E122 D 9011101D 069 7/12/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071L1062119003561 $1,905.37 000001077589-3562500610
2022 1 FD52 00 E122 D 9011101D 069 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003561 $46.84 000001077589-3562500610
2022 1 FD52 08 E111 D 9011101D 069 7/12/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071L1062119004135 $1,731.11
2022 1 FD52 00 E123 D 9011101D 069 7/12/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR071L1062119003561 $423.57 000001077589-3562500610
2022 1 FD52 08 E121 D 9011101D 069 7/12/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071L1062119004135 $128.01
2022 1 FD52 00 E123 D 9011101D 069 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003561 $8.56 000001077589-3562500610
2022 1 FD52 08 E122 D 9011101D 069 7/12/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071L1062119004135 $1,461.57
2022 1 FD52 08 E123 D 9011101D 069 7/12/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071L1062119004135 $302.54
2022 1 FD52 08 E111 D 9011101D 069 7/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062L1062117303042 $361.68
2022 1 FD52 08 E121 D 9011101D 069 7/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062L1062117303042 $27.06
2022 1 FD52 08 E122 D 9011101D 069 7/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062L1062117303042 $305.37
2022 1 FD52 08 E123 D 9011101D 069 7/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062L1062117303042 $61.51
2022 1 FD52 08 E124 D 9011101D 069 7/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062L1062117303042 $0.18
2022 1 FD52 00 E123 D 9011101D 069 7/2/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR061L1062116001483P $347.85 000001077589-3562500610
2022 1 FD52 00 E123 D 9011101D 069 7/2/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061L1062116001483P $43.60 000001077589-3562500610
2022 1 FD52 08 E123 D 9011101D 069 7/2/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061L1062116001939P $298.74
2022 1 FD52 08 E123 D 9011101D 069 7/2/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061L1062116001939P $62.84
2022 1 FD52 00 E111 D 9011101D 069 7/1/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR062L1062117302485 $3,803.11 000001077589-3562500610
2022 1 FD52 00 E111 D 9011101D 069 7/1/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062L1062117302485 $31.71 000001077589-3562500610
2022 1 FD52 00 E121 D 9011101D 069 7/1/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR062L1062117302485 $281.13 000001077589-3562500610
2022 1 FD52 00 E121 D 9011101D 069 7/1/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062L1062117302485 $2.37 000001077589-3562500610
2022 1 FD52 00 E122 D 9011101D 069 7/1/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR062L1062117302485 $3,211.01 000001077589-3562500610
2022 1 FD52 00 E122 D 9011101D 069 7/1/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062L1062117302485 $26.77 000001077589-3562500610
2022 1 FD52 00 E123 D 9011101D 069 7/1/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR062L1062117302485 $681.38 000001077589-3562500610
2022 1 FD52 00 E123 D 9011101D 069 7/1/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062L1062117302485 $4.89 000001077589-3562500610
2022 1 FD52 00 E124 D 9011101D 069 7/1/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR062L1062117302485 $1.91 000001077589-3562500610
2022 1 FD52 00 E124 D 9011101D 069 7/1/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062L1062117302485 $0.01 000001077589-3562500610
2021 12 FD52 08 E143 D 9011101D 069 6/23/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2100214626 PON21900004878 QK4 INC $6,028.59 Lincoln County 8-167
2021 12 FD52 00 E121 D 9011101D 069 6/14/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061L1062116001483 $21.51 000001077589-3562500610
2021 12 FD52 00 E122 D 9011101D 069 6/14/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR061L1062116001483 $1,814.20 000001077589-3562500610
2021 12 FD52 00 E122 D 9011101D 069 6/14/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061L1062116001483 $245.42 000001077589-3562500610
2021 12 FD52 00 E111 D 9011101D 069 6/14/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR061L1062116001483 $2,148.82 000001077589-3562500610
2021 12 FD52 00 E111 D 9011101D 069 6/14/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061L1062116001483 $290.67 000001077589-3562500610
2021 12 FD52 00 E121 D 9011101D 069 6/14/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR061L1062116001483 $158.69 000001077589-3562500610
2021 12 FD52 08 E111 D 9011101D 069 6/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061L1062116001939 $1,202.23
2021 12 FD52 08 E111 D 9011101D 069 6/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061L1062116001939 $319.15
2021 12 FD52 08 E121 D 9011101D 069 6/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061L1062116001939 $81.02
2021 12 FD52 08 E121 D 9011101D 069 6/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061L1062116001939 $22.97
2021 12 FD52 08 E122 D 9011101D 069 6/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061L1062116001939 $1,015.04
2021 12 FD52 08 E122 D 9011101D 069 6/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061L1062116001939 $269.46
2021 11 FD52 08 E111 D 9011101D 069 5/24/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052L1062114100965 $1,483.08
2021 11 FD52 08 E121 D 9011101D 069 5/24/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052L1062114100965 $109.28
2021 11 FD52 08 E122 D 9011101D 069 5/24/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052L1062114100965 $1,252.16
2021 11 FD52 08 E123 D 9011101D 069 5/24/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052L1062114100965 $288.75
2021 11 FD52 08 E124 D 9011101D 069 5/24/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052L1062114100965 $0.70
2021 11 FD52 08 E143 D 9011101D 069 5/21/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2100193747 PON21900004878 QK4 INC $1,185.95 Lincoln County 8-167
2021 11 FD52 08 E111 D 9011101D 069 5/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051L1062112710235 $1,733.60
2021 11 FD52 08 E121 D 9011101D 069 5/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051L1062112710235 $126.39
2021 11 FD52 08 E122 D 9011101D 069 5/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051L1062112710235 $1,463.69
2021 11 FD52 08 E123 D 9011101D 069 5/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051L1062112710235 $325.23
2021 10 FD52 08 E229 D 9011101D 069 4/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162521115013270 $1.84
2021 10 FD52 00 E111 D 9011101D 088 4/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042L1062111308680 $282.59 000001077455-3562500610
2021 10 FD52 00 E111 D 9011101D 088 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308680 $13.38 000001077455-3562500610
2021 10 FD52 00 E121 D 9011101D 088 4/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042L1062111308680 $21.62 000001077455-3562500610
2021 10 FD52 00 E121 D 9011101D 088 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308680 $1.02 000001077455-3562500610
2021 10 FD52 00 E122 D 9011101D 088 4/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042L1062111308680 $238.59 000001077455-3562500610
2021 10 FD52 00 E122 D 9011101D 088 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308680 $11.30 000001077455-3562500610
2021 10 FD52 08 E111 D 9011101D 069 4/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042L1062111309231 $806.85
2021 10 FD52 08 E111 D 9011101D 069 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111309231 $110.32
2021 10 FD52 08 E121 D 9011101D 069 4/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042L1062111309231 $60.24
2021 10 FD52 08 E121 D 9011101D 069 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111309231 $7.93
2021 10 FD52 08 E122 D 9011101D 069 4/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042L1062111309231 $681.23
2021 10 FD52 08 E122 D 9011101D 069 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111309231 $93.14
2021 10 FD52 08 E123 D 9011101D 069 4/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042L1062111309231 $143.31
2021 10 FD52 08 E123 D 9011101D 069 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111309231 $24.83
2021 10 FD52 08 E124 D 9011101D 069 4/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042L1062111309231 $0.39
2021 10 FD52 08 E124 D 9011101D 069 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111309231 $0.05
2021 10 FD52 00 E111 D 9011101D 069 4/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042L1062111308689 $548.24 000001077589-3562500610
2021 10 FD52 00 E111 D 9011101D 069 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308689 $106.32 000001077589-3562500610
2021 10 FD52 00 E121 D 9011101D 069 4/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042L1062111308689 $41.01 000001077589-3562500610
2021 10 FD52 00 E121 D 9011101D 069 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308689 $7.95 000001077589-3562500610
2021 10 FD52 00 E122 D 9011101D 069 4/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042L1062111308689 $462.38 000001077589-3562500610
2021 10 FD52 00 E122 D 9011101D 069 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308689 $89.76 000001077589-3562500610
2021 10 FD52 00 E123 D 9011101D 069 4/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042L1062111308689 $81.99 000001077589-3562500610
2021 10 FD52 00 E123 D 9011101D 069 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308689 $15.75 000001077589-3562500610
2021 10 FD52 00 E124 D 9011101D 069 4/26/2021 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR042L1062111308689 $0.21 000001077589-3562500610
2021 10 FD52 00 E124 D 9011101D 069 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308689 $0.04 000001077589-3562500610
2021 10 FD52 08 E111 D 9011101D 069 4/12/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041L1062109908101 $1,610.42
2021 10 FD52 08 E115 D 9011101D 069 4/12/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041L1062109908101 $103.71
2021 10 FD52 08 E121 D 9011101D 069 4/12/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041L1062109908101 $121.94
2021 10 FD52 08 E122 D 9011101D 069 4/12/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041L1062109908101 $1,447.23
2021 10 FD52 08 E123 D 9011101D 069 4/12/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041L1062109908101 $338.60
2021 10 FD52 00 E111 D 9011101D 069 4/12/2021 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041L1062109907606 $366.48 000001053089-3562500610
2021 10 FD52 00 E111 D 9011101D 069 4/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041L1062109907606 $10.21 000001053089-3562500610
2021 10 FD52 00 E121 D 9011101D 069 4/12/2021 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041L1062109907606 $27.10 000001053089-3562500610
2021 10 FD52 00 E121 D 9011101D 069 4/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041L1062109907606 $0.75 000001053089-3562500610
2021 10 FD52 00 E122 D 9011101D 069 4/12/2021 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041L1062109907606 $309.38 000001053089-3562500610
2021 10 FD52 00 E122 D 9011101D 069 4/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041L1062109907606 $8.61 000001053089-3562500610
2021 10 FD52 00 E123 D 9011101D 069 4/12/2021 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041L1062109907606 $37.00 000001053089-3562500610
2021 10 FD52 00 E123 D 9011101D 069 4/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041L1062109907606 $1.12 000001053089-3562500610
2021 9 FD52 08 E143 D 9011101D 069 3/29/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2100159116 PON21900004878 QK4 INC $17,101.31 Lincoln County 8-167
2021 9 FD52 08 E111 D 9011101D 069 3/24/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032L1062108207119 $1,708.54
2021 9 FD52 08 E111 D 9011101D 069 3/24/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032L1062108207119 $132.38
2021 9 FD52 08 E121 D 9011101D 069 3/24/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032L1062108207119 $124.36
2021 9 FD52 08 E121 D 9011101D 069 3/24/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032L1062108207119 $9.90
2021 9 FD52 08 E122 D 9011101D 069 3/24/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032L1062108207119 $1,442.55
2021 9 FD52 08 E122 D 9011101D 069 3/24/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032L1062108207119 $111.76
2021 9 FD52 08 E123 D 9011101D 069 3/24/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032L1062108207119 $361.51
2021 9 FD52 08 E123 D 9011101D 069 3/24/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032L1062108207119 $22.18
2021 9 FD52 08 E124 D 9011101D 069 3/24/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032L1062108207119 $0.79
2021 9 FD52 08 E124 D 9011101D 069 3/24/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032L1062108207119 $0.07
2021 9 FD52 00 E111 D 9011101D 069 3/24/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR032L1062108206550 $227.56 000001073064-3562500061
2021 9 FD52 00 E111 D 9011101D 069 3/24/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032L1062108206550 $67.95 000001073064-3562500061
2021 9 FD52 00 E121 D 9011101D 069 3/24/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR032L1062108206550 $16.93 000001073064-3562500061
2021 9 FD52 00 E121 D 9011101D 069 3/24/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032L1062108206550 $5.06 000001073064-3562500061
2021 9 FD52 00 E122 D 9011101D 069 3/24/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR032L1062108206550 $192.08 000001073064-3562500061
2021 9 FD52 00 E122 D 9011101D 069 3/24/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032L1062108206550 $57.37 000001073064-3562500061
2021 9 FD52 00 E123 D 9011101D 069 3/24/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR032L1062108206550 $31.50 000001073064-3562500061
2021 9 FD52 00 E123 D 9011101D 069 3/24/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032L1062108206550 $9.23 000001073064-3562500061
2021 9 FD52 00 E124 D 9011101D 069 3/24/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR032L1062108206550 $0.09 000001073064-3562500061
2021 9 FD52 00 E124 D 9011101D 069 3/24/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032L1062108206550 $0.03 000001073064-3562500061
2021 9 FD52 08 E229 D 9011101D 069 3/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162521069012200 $35.72
2021 9 FD52 08 E111 D 9011101D 069 3/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031L1062106806027 $1,897.54
2021 9 FD52 08 E121 D 9011101D 069 3/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031L1062106806027 $136.62
2021 9 FD52 08 E122 D 9011101D 069 3/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031L1062106806027 $1,602.09
2021 9 FD52 08 E123 D 9011101D 069 3/10/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031L1062106806027 $386.14
2021 9 FD52 00 E111 D 9011101D 069 3/10/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR031L1062106805517 $278.13 000001073064-3562500061
2021 9 FD52 00 E111 D 9011101D 069 3/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031L1062106805517 $34.48 000001073064-3562500061
2021 9 FD52 00 E121 D 9011101D 069 3/10/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR031L1062106805517 $20.41 000001073064-3562500061
2021 9 FD52 00 E121 D 9011101D 069 3/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031L1062106805517 $2.54 000001073064-3562500061
2021 9 FD52 00 E122 D 9011101D 069 3/10/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR031L1062106805517 $235.06 000001073064-3562500061
2021 9 FD52 00 E122 D 9011101D 069 3/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031L1062106805517 $29.11 000001073064-3562500061
2021 9 FD52 00 E123 D 9011101D 069 3/10/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR031L1062106805517 $38.46 000001073064-3562500061
2021 9 FD52 00 E123 D 9011101D 069 3/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031L1062106805517 $4.68 000001073064-3562500061
2021 8 FD52 08 E111 D 9011101D 069 2/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022L1062105304995 $1,252.80
2021 8 FD52 08 E111 D 9011101D 069 2/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022L1062105304995 $163.27
2021 8 FD52 08 E115 D 9011101D 069 2/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022L1062105304995 $20.74
2021 8 FD52 08 E121 D 9011101D 069 2/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022L1062105304995 $94.37
2021 8 FD52 08 E121 D 9011101D 069 2/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022L1062105304995 $12.10
2021 8 FD52 08 E122 D 9011101D 069 2/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022L1062105304995 $1,075.36
2021 8 FD52 08 E122 D 9011101D 069 2/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022L1062105304995 $137.85
2021 8 FD52 08 E123 D 9011101D 069 2/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022L1062105304995 $230.78
2021 8 FD52 08 E123 D 9011101D 069 2/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022L1062105304995 $29.62
2021 8 FD52 08 E124 D 9011101D 069 2/26/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022L1062105304995 $0.62
2021 8 FD52 08 E124 D 9011101D 069 2/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022L1062105304995 $0.08
2021 8 FD52 08 E111 D 9011101D 069 2/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021L1062103603866 $1,470.12
2021 8 FD52 08 E111 D 9011101D 069 2/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021L1062103603866 $163.54
2021 8 FD52 08 E121 D 9011101D 069 2/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021L1062103603866 $106.17
2021 8 FD52 08 E121 D 9011101D 069 2/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021L1062103603866 $11.81
2021 8 FD52 08 E122 D 9011101D 069 2/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021L1062103603866 $1,241.18
2021 8 FD52 08 E122 D 9011101D 069 2/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021L1062103603866 $138.07
2021 8 FD52 08 E123 D 9011101D 069 2/8/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021L1062103603866 $288.46
2021 8 FD52 08 E123 D 9011101D 069 2/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021L1062103603866 $31.66
2021 8 FD52 08 E143 D 9011101D 069 2/2/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2100125030 PON21900004878 QK4 INC $8,071.06 Lincoln County 8-167
2021 7 FD52 08 E111 D 9011101D 069 1/25/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012L1062102202883 $2,515.44
2021 7 FD52 08 E111 D 9011101D 069 1/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012L1062102202883 $251.55
2021 7 FD52 08 E121 D 9011101D 069 1/25/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012L1062102202883 $183.87
2021 7 FD52 08 E121 D 9011101D 069 1/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012L1062102202883 $18.40
2021 7 FD52 08 E122 D 9011101D 069 1/25/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012L1062102202883 $2,123.79
2021 7 FD52 08 E122 D 9011101D 069 1/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012L1062102202883 $212.39
2021 7 FD52 08 E123 D 9011101D 069 1/25/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012L1062102202883 $516.30
2021 7 FD52 08 E123 D 9011101D 069 1/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012L1062102202883 $50.97
2021 7 FD52 08 E124 D 9011101D 069 1/25/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012L1062102202883 $1.17
2021 7 FD52 08 E124 D 9011101D 069 1/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012L1062102202883 $0.13
2021 7 FD52 08 E143 D 9011101D 069 1/12/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2100112342 PON21900004878 QK4 INC $80,253.31 Lincoln County 8-167
2021 7 FD52 08 E229 D 9011101D 069 1/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162521010001320 $42.00
2021 7 FD52 08 E111 D 9011101D 069 1/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011L1062100801830 $1,235.91
2021 7 FD52 08 E111 D 9011101D 069 1/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011L1062100801830 $882.66
2021 7 FD52 08 E121 D 9011101D 069 1/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011L1062100801830 $89.34
2021 7 FD52 08 E121 D 9011101D 069 1/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011L1062100801830 $62.80
2021 7 FD52 08 E122 D 9011101D 069 1/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011L1062100801830 $1,043.47
2021 7 FD52 08 E122 D 9011101D 069 1/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011L1062100801830 $745.22
2021 7 FD52 08 E123 D 9011101D 069 1/11/2021 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011L1062100801830 $242.74
2021 7 FD52 08 E123 D 9011101D 069 1/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011L1062100801830 $180.97
2021 6 FD52 08 E229 D 9011101D 069 12/28/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162520360002030 $42.00
2021 6 FD52 08 E122 D 9011101D 069 12/23/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122K1062035700957 $1,961.31
2021 6 FD52 08 E122 D 9011101D 069 12/23/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122K1062035700957 $45.80
2021 6 FD52 08 E123 D 9011101D 069 12/23/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122K1062035700957 $449.66
2021 6 FD52 08 E123 D 9011101D 069 12/23/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122K1062035700957 $8.82
2021 6 FD52 08 E124 D 9011101D 069 12/23/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122K1062035700957 $1.08
2021 6 FD52 08 E124 D 9011101D 069 12/23/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122K1062035700957 $0.03
2021 6 FD52 08 E111 D 9011101D 069 12/23/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122K1062035700957 $2,322.98
2021 6 FD52 08 E111 D 9011101D 069 12/23/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122K1062035700957 $54.25
2021 6 FD52 08 E121 D 9011101D 069 12/23/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122K1062035700957 $170.81
2021 6 FD52 08 E121 D 9011101D 069 12/23/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122K1062035700957 $4.06
2021 6 FD52 08 E111 D 9011101D 069 12/14/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121K1062034310117 $1,313.16
2021 6 FD52 08 E111 D 9011101D 069 12/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121K1062034310117 $291.91
2021 6 FD52 08 E121 D 9011101D 069 12/14/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121K1062034310117 $98.87
2021 6 FD52 08 E121 D 9011101D 069 12/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121K1062034310117 $21.97
2021 6 FD52 08 E122 D 9011101D 069 12/14/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121K1062034310117 $1,108.74
2021 6 FD52 08 E122 D 9011101D 069 12/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121K1062034310117 $246.46
2021 6 FD52 08 E123 D 9011101D 069 12/14/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121K1062034310117 $212.18
2021 6 FD52 08 E123 D 9011101D 069 12/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121K1062034310117 $46.28
2021 6 FD52 08 E143 D 9011101D 069 12/4/2020 1550 DESIGN CONTRACTS-CONSULTANT PRC-2100090408 PON21900004878 QK4 INC $13,341.95 Lincoln County 8-167
2021 5 FD52 08 E111 D 9011101D 069 11/23/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112K1062032509207 $3,238.29
2021 5 FD52 08 E111 D 9011101D 069 11/23/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112K1062032509207 $809.15
2021 5 FD52 08 E121 D 9011101D 069 11/23/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112K1062032509207 $243.60
2021 5 FD52 08 E121 D 9011101D 069 11/23/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112K1062032509207 $60.87
2021 5 FD52 08 E122 D 9011101D 069 11/23/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112K1062032509207 $2,734.08
2021 5 FD52 08 E122 D 9011101D 069 11/23/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112K1062032509207 $683.16
2021 5 FD52 08 E123 D 9011101D 069 11/23/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112K1062032509207 $458.90
2021 5 FD52 08 E123 D 9011101D 069 11/23/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112K1062032509207 $112.58
2021 5 FD52 08 E124 D 9011101D 069 11/23/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112K1062032509207 $1.30
2021 5 FD52 08 E124 D 9011101D 069 11/23/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112K1062032509207 $0.31
2021 5 FD52 08 E111 D 9011101D 069 11/12/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111K1062031108244 $2,747.19
2021 5 FD52 08 E121 D 9011101D 069 11/12/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111K1062031108244 $201.72
2021 5 FD52 08 E122 D 9011101D 069 11/12/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111K1062031108244 $2,319.46
2021 5 FD52 08 E123 D 9011101D 069 11/12/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111K1062031108244 $479.98
2021 5 FD52 08 E143 D 9011101D 069 11/9/2020 1550 DESIGN CONTRACTS-CONSULTANT PRC-2100071774 PON21900004878 QK4 INC $3,722.57 Lincoln County 8-167
2021 4 FD52 08 E111 D 9011101D 069 10/29/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102K1062029707266 $2,477.82
2021 4 FD52 08 E111 D 9011101D 069 10/29/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102K1062029707266 $241.79
2021 4 FD52 08 E121 D 9011101D 069 10/29/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102K1062029707266 $184.07
2021 4 FD52 08 E121 D 9011101D 069 10/29/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102K1062029707266 $18.31
2021 4 FD52 08 E122 D 9011101D 069 10/29/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102K1062029707266 $2,092.03
2021 4 FD52 08 E122 D 9011101D 069 10/29/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102K1062029707266 $204.14
2021 4 FD52 08 E123 D 9011101D 069 10/29/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102K1062029707266 $398.63
2021 4 FD52 08 E123 D 9011101D 069 10/29/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102K1062029707266 $25.88
2021 4 FD52 08 E124 D 9011101D 069 10/29/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102K1062029707266 $1.00
2021 4 FD52 08 E124 D 9011101D 069 10/29/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102K1062029707266 $0.08
2021 4 FD52 08 E229 D 9011101D 069 10/26/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162520299001330 $80.00
2021 4 FD52 08 E229 D 9011101D 069 10/15/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162520289002010 $74.50
2021 4 FD52 08 E111 D 9011101D 069 10/12/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101K1062028206183 $150.70
2021 4 FD52 08 E115 D 9011101D 069 10/12/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101K1062028206183 $124.45
2021 4 FD52 08 E121 D 9011101D 069 10/12/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101K1062028206183 $292.79
2021 4 FD52 08 E121 D 9011101D 069 10/12/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101K1062028206183 $11.28
2021 4 FD52 08 E122 D 9011101D 069 10/12/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101K1062028206183 $3,313.67
2021 4 FD52 08 E122 D 9011101D 069 10/12/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101K1062028206183 $127.24
2021 4 FD52 08 E123 D 9011101D 069 10/12/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101K1062028206183 $551.52
2021 4 FD52 08 E123 D 9011101D 069 10/12/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101K1062028206183 $24.51
2021 4 FD52 08 E111 D 9011101D 069 10/12/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101K1062028206182 $3,800.32
2021 3 FD52 08 E143 D 9011101D 069 9/24/2020 1550 DESIGN CONTRACTS-CONSULTANT PRC-2100048383 PON21900004878 QK4 INC $25,267.36 Lincoln County 8-167
2021 3 FD52 08 E111 D 9011101D 069 9/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092K1062026705196 $3,764.80
2021 3 FD52 08 E111 D 9011101D 069 9/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092K1062026705196 $376.48
2021 3 FD52 08 E121 D 9011101D 069 9/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092K1062026705196 $281.38
2021 3 FD52 08 E121 D 9011101D 069 9/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092K1062026705196 $28.15
2021 3 FD52 08 E122 D 9011101D 069 9/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092K1062026705196 $3,178.63
2021 3 FD52 08 E122 D 9011101D 069 9/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092K1062026705196 $317.87
2021 3 FD52 08 E123 D 9011101D 069 9/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092K1062026705196 $550.08
2021 3 FD52 08 E123 D 9011101D 069 9/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092K1062026705196 $54.19
2021 3 FD52 08 E124 D 9011101D 069 9/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092K1062026705196 $1.45
2021 3 FD52 08 E124 D 9011101D 069 9/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092K1062026705196 $0.15
2021 3 FD52 08 E122 D 9011101D 069 9/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091K1062025304070 $943.90
2021 3 FD52 08 E123 D 9011101D 069 9/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091K1062025304070 $121.86
2021 3 FD52 08 E111 D 9011101D 069 9/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091K1062025304069 $1,117.97
2021 3 FD52 08 E121 D 9011101D 069 9/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091K1062025304069 $84.82
2021 2 FD52 00 E111 D 9011101D 069 8/24/2020 0070 ENV STUDIES-HIST/CULTURAL CA-XR082K1062023402539 $250.29 000001073064-3562500061
2021 2 FD52 00 E111 D 9011101D 069 8/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082K1062023402539 $5.01 000001073064-3562500061
2021 2 FD52 00 E121 D 9011101D 069 8/24/2020 0070 ENV STUDIES-HIST/CULTURAL CA-XR082K1062023402539 $18.47 000001073064-3562500061
2021 2 FD52 00 E121 D 9011101D 069 8/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082K1062023402539 $0.37 000001073064-3562500061
2021 2 FD52 00 E122 D 9011101D 069 8/24/2020 0070 ENV STUDIES-HIST/CULTURAL CA-XR082K1062023402539 $211.29 000001073064-3562500061
2021 2 FD52 00 E122 D 9011101D 069 8/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082K1062023402539 $4.23 000001073064-3562500061
2021 2 FD52 00 E123 D 9011101D 069 8/24/2020 0070 ENV STUDIES-HIST/CULTURAL CA-XR082K1062023402539 $33.52 000001073064-3562500061
2021 2 FD52 00 E123 D 9011101D 069 8/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082K1062023402539 $0.66 000001073064-3562500061
2021 2 FD52 00 E124 D 9011101D 069 8/24/2020 0070 ENV STUDIES-HIST/CULTURAL CA-XR082K1062023402539 $0.10 000001073064-3562500061
2021 2 FD52 08 E111 D 9011101D 069 8/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082K1062023403114 $1,441.71
2021 2 FD52 08 E121 D 9011101D 069 8/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082K1062023403114 $109.31
2021 2 FD52 08 E122 D 9011101D 069 8/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082K1062023403114 $1,217.23
2021 2 FD52 08 E123 D 9011101D 069 8/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082K1062023403114 $167.55
2021 2 FD52 08 E124 D 9011101D 069 8/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082K1062023403114 $0.50
2021 2 FD52 00 E111 D 9011101D 069 8/13/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081K1062022001420 $316.23 000001047876-3562500636
2021 2 FD52 00 E111 D 9011101D 069 8/13/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081K1062022001420 $139.14 000001047876-3562500636
2021 2 FD52 00 E121 D 9011101D 069 8/13/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081K1062022001420 $22.50 000001047876-3562500636
2021 2 FD52 00 E121 D 9011101D 069 8/13/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081K1062022001420 $9.90 000001047876-3562500636
2021 2 FD52 00 E122 D 9011101D 069 8/13/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081K1062022001420 $266.99 000001047876-3562500636
2021 2 FD52 00 E122 D 9011101D 069 8/13/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081K1062022001420 $117.47 000001047876-3562500636
2021 2 FD52 00 E123 D 9011101D 069 8/13/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081K1062022001420 $47.76 000001047876-3562500636
2021 2 FD52 00 E123 D 9011101D 069 8/13/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081K1062022001420 $20.75 000001047876-3562500636
2021 2 FD52 08 E143 D 9011101D 069 8/12/2020 1550 DESIGN CONTRACTS-CONSULTANT PRC-2100021802 PON21900004878 QK4 INC $32,341.77 Lincoln County 8-167
2021 2 FD52 08 E111 D 9011101D 069 8/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081K1062022001970 $2,532.81
2021 2 FD52 08 E111 D 9011101D 069 8/10/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081K1062022001970 $30.06
2021 2 FD52 08 E121 D 9011101D 069 8/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081K1062022001970 $190.27
2021 2 FD52 08 E121 D 9011101D 069 8/10/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081K1062022001970 $2.25
2021 2 FD52 08 E122 D 9011101D 069 8/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081K1062022001970 $2,138.45
2021 2 FD52 08 E122 D 9011101D 069 8/10/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081K1062022001970 $25.38
2021 2 FD52 08 E123 D 9011101D 069 8/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081K1062022001970 $353.74
2021 2 FD52 08 E123 D 9011101D 069 8/10/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081K1062022001970 $4.89
2021 2 FD52 08 E124 D 9011101D 069 8/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081K1062022001970 ($0.01)
2021 1 FD52 08 E229 D 9011101D 069 7/28/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162520207001840 $68.50
2021 1 FD52 00 E111 D 9011101D 069 7/27/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR072K1062020600319 $344.77 000001047876-3562500636
2021 1 FD52 00 E111 D 9011101D 069 7/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072K1062020600319 $53.36 000001047876-3562500636
2021 1 FD52 00 E121 D 9011101D 069 7/27/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR072K1062020600319 $25.11 000001047876-3562500636
2021 1 FD52 00 E121 D 9011101D 069 7/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072K1062020600319 $3.87 000001047876-3562500636
2021 1 FD52 00 E122 D 9011101D 069 7/27/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR072K1062020600319 $291.27 000001047876-3562500636
2021 1 FD52 00 E122 D 9011101D 069 7/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072K1062020600319 $45.05 000001047876-3562500636
2021 1 FD52 00 E123 D 9011101D 069 7/27/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR072K1062020600319 $51.97 000001047876-3562500636
2021 1 FD52 00 E123 D 9011101D 069 7/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072K1062020600319 $7.96 000001047876-3562500636
2021 1 FD52 00 E124 D 9011101D 069 7/27/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR072K1062020600319 $0.09 000001047876-3562500636
2021 1 FD52 00 E124 D 9011101D 069 7/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072K1062020600319 $0.01 000001047876-3562500636
2021 1 FD52 08 E111 D 9011101D 069 7/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072K1062020600943 $1,684.19
2021 1 FD52 08 E111 D 9011101D 069 7/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072K1062020600943 $218.09
2021 1 FD52 08 E121 D 9011101D 069 7/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072K1062020600943 $127.49
2021 1 FD52 08 E121 D 9011101D 069 7/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072K1062020600943 $16.47
2021 1 FD52 08 E122 D 9011101D 069 7/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072K1062020600943 $1,422.14
2021 1 FD52 08 E122 D 9011101D 069 7/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072K1062020600943 $184.13
2021 1 FD52 08 E123 D 9011101D 069 7/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072K1062020600943 $213.10
2021 1 FD52 08 E123 D 9011101D 069 7/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072K1062020600943 $29.02
2021 1 FD52 08 E124 D 9011101D 069 7/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072K1062020600943 $0.66
2021 1 FD52 08 E124 D 9011101D 069 7/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072K1062020600943 $0.09
2021 1 FD52 08 E123 D 9011101D 069 7/14/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071K1062019009816 $264.67
2021 1 FD52 08 E123 D 9011101D 069 7/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071K1062019009816 $6.09
2021 1 FD52 08 E111 D 9011101D 069 7/14/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071K1062019009816 $1,888.52
2021 1 FD52 08 E111 D 9011101D 069 7/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071K1062019009816 $56.45
2021 1 FD52 08 E121 D 9011101D 069 7/14/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071K1062019009816 $141.47
2021 1 FD52 00 E111 D 9011101D 069 7/14/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071K1062019009301 $344.80 000001047876-3562500636
2021 1 FD52 08 E121 D 9011101D 069 7/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071K1062019009816 $4.28
2021 1 FD52 00 E111 D 9011101D 069 7/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071K1062019009301 $32.20 000001047876-3562500636
2021 1 FD52 00 E121 D 9011101D 069 7/14/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071K1062019009301 $24.55 000001047876-3562500636
2021 1 FD52 00 E121 D 9011101D 069 7/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071K1062019009301 $2.30 000001047876-3562500636
2021 1 FD52 00 E122 D 9011101D 069 7/14/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071K1062019009301 $287.82 000001047876-3562500636
2021 1 FD52 00 E122 D 9011101D 069 7/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071K1062019009301 $26.86 000001047876-3562500636
2021 1 FD52 00 E123 D 9011101D 069 7/14/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071K1062019009301 $51.94 000001047876-3562500636
2021 1 FD52 00 E123 D 9011101D 069 7/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071K1062019009301 $4.80 000001047876-3562500636
2021 1 FD52 08 E122 D 9011101D 069 7/14/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071K1062019009816 $1,575.53
2021 1 FD52 08 E122 D 9011101D 069 7/14/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071K1062019009816 $47.09
2021 1 FD52 08 E111 D 9011101D 069 7/8/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062K1062017108813 $1,876.61
2021 1 FD52 08 E121 D 9011101D 069 7/8/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062K1062017108813 $140.81
2021 1 FD52 08 E122 D 9011101D 069 7/8/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062K1062017108813 $1,565.66
2021 1 FD52 08 E123 D 9011101D 069 7/8/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062K1062017108813 $263.95
2021 1 FD52 08 E124 D 9011101D 069 7/8/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062K1062017108813 $0.72
2021 1 FD52 08 E123 D 9011101D 069 7/2/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061K1062016107790P $372.18
2021 1 FD52 08 E123 D 9011101D 069 7/2/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061K1062016107790P $40.79
2020 12 FD52 08 E229 D 9011101D 069 6/29/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162520178005360 $120.00
2020 12 FD52 08 E111 D 9011101D 069 6/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061K1062016107790 $2,314.64
2020 12 FD52 08 E111 D 9011101D 069 6/10/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061K1062016107790 $257.19
2020 12 FD52 08 E121 D 9011101D 069 6/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061K1062016107790 $170.41
2020 12 FD52 08 E121 D 9011101D 069 6/10/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061K1062016107790 $18.94
2020 12 FD52 08 E122 D 9011101D 069 6/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061K1062016107790 $1,931.20
2020 12 FD52 08 E122 D 9011101D 069 6/10/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061K1062016107790 $214.57
2020 11 FD52 08 E143 D 9011101D 069 5/29/2020 1550 DESIGN CONTRACTS-CONSULTANT PRC-2000200971 PON21900004878 QK4 INC $10,245.31 Lincoln County 8-167
2020 11 FD52 00 E111 D 9011101D 069 5/26/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR052K1062014306382 $136.49 000001053089-3562500610
2020 11 FD52 00 E111 D 9011101D 069 5/26/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052K1062014306382 $13.65 000001053089-3562500610
2020 11 FD52 00 E121 D 9011101D 069 5/26/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR052K1062014306382 $10.44 000001053089-3562500610
2020 11 FD52 00 E121 D 9011101D 069 5/26/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052K1062014306382 $1.05 000001053089-3562500610
2020 11 FD52 00 E122 D 9011101D 069 5/26/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR052K1062014306382 $113.87 000001053089-3562500610
2020 11 FD52 00 E122 D 9011101D 069 5/26/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052K1062014306382 $11.39 000001053089-3562500610
2020 11 FD52 00 E123 D 9011101D 069 5/26/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR052K1062014306382 $5.64 000001053089-3562500610
2020 11 FD52 00 E123 D 9011101D 069 5/26/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052K1062014306382 $0.53 000001053089-3562500610
2020 11 FD52 00 E124 D 9011101D 069 5/26/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR052K1062014306382 $0.06 000001053089-3562500610
2020 11 FD52 00 E124 D 9011101D 069 5/26/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052K1062014306382 $0.01 000001053089-3562500610
2020 11 FD52 08 E111 D 9011101D 069 5/26/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052K1062014306892 $1,749.02
2020 11 FD52 08 E121 D 9011101D 069 5/26/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052K1062014306892 $130.93
2020 11 FD52 08 E122 D 9011101D 069 5/26/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052K1062014306892 $1,459.21
2020 11 FD52 08 E123 D 9011101D 069 5/26/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052K1062014306892 $263.35
2020 11 FD52 08 E124 D 9011101D 069 5/26/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052K1062014306892 $0.72
2020 11 FD52 00 E111 D 9011101D 069 5/26/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052K1062014306379 $345.06 000001047876-3562500636
2020 11 FD52 00 E111 D 9011101D 069 5/26/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052K1062014306379 $15.18 000001047876-3562500636
2020 11 FD52 00 E121 D 9011101D 069 5/26/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052K1062014306379 $25.11 000001047876-3562500636
2020 11 FD52 00 E121 D 9011101D 069 5/26/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052K1062014306379 $1.11 000001047876-3562500636
2020 11 FD52 00 E122 D 9011101D 069 5/26/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052K1062014306379 $287.82 000001047876-3562500636
2020 11 FD52 00 E122 D 9011101D 069 5/26/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052K1062014306379 $12.66 000001047876-3562500636
2020 11 FD52 00 E123 D 9011101D 069 5/26/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052K1062014306379 $51.92 000001047876-3562500636
2020 11 FD52 00 E123 D 9011101D 069 5/26/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052K1062014306379 $2.26 000001047876-3562500636
2020 11 FD52 00 E124 D 9011101D 069 5/26/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR052K1062014306379 $0.09 000001047876-3562500636
2020 11 FD52 08 E229 D 9011101D 069 5/11/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162520131009670 $1.05
2020 11 FD52 00 E111 D 9011101D 069 5/11/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR051K1062012905477 $344.98 000001047876-3562500636
2020 11 FD52 00 E121 D 9011101D 069 5/11/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR051K1062012905477 $24.55 000001047876-3562500636
2020 11 FD52 00 E122 D 9011101D 069 5/11/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR051K1062012905477 $287.81 000001047876-3562500636
2020 11 FD52 00 E123 D 9011101D 069 5/11/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR051K1062012905477 $51.90 000001047876-3562500636
2020 11 FD52 00 E111 D 9011101D 069 5/11/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR051K1062012905479 $1,058.23 000001053089-3562500610
2020 11 FD52 00 E111 D 9011101D 069 5/11/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051K1062012905479 $38.06 000001053089-3562500610
2020 11 FD52 00 E121 D 9011101D 069 5/11/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR051K1062012905479 $78.75 000001053089-3562500610
2020 11 FD52 00 E121 D 9011101D 069 5/11/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051K1062012905479 $2.88 000001053089-3562500610
2020 11 FD52 00 E122 D 9011101D 069 5/11/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR051K1062012905479 $882.87 000001053089-3562500610
2020 11 FD52 00 E122 D 9011101D 069 5/11/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051K1062012905479 $31.75 000001053089-3562500610
2020 11 FD52 00 E123 D 9011101D 069 5/11/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR051K1062012905479 $164.50 000001053089-3562500610
2020 11 FD52 00 E123 D 9011101D 069 5/11/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051K1062012905479 $2.39 000001053089-3562500610
2020 11 FD52 08 E111 D 9011101D 069 5/11/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051K1062012905897 $2,548.83
2020 11 FD52 08 E121 D 9011101D 069 5/11/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051K1062012905897 $191.34
2020 11 FD52 08 E122 D 9011101D 069 5/11/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051K1062012905897 $2,126.48
2020 11 FD52 08 E123 D 9011101D 069 5/11/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051K1062012905897 $354.77
2020 11 FD52 08 E143 D 9011101D 069 5/6/2020 1550 DESIGN CONTRACTS-CONSULTANT PRC-2000189228 PON21900004878 QK4 INC $117,989.70 Lincoln County 8-167
2020 10 FD52 08 E229 D 9011101D 069 4/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162520116001230 $320.00
2020 10 FD52 00 E111 D 9011101D 069 4/27/2020 0093 ENV STUDIES-PERMITTING MITIGA CA-XR042K1062011504482 $321.04 000001073120-3562500061
2020 10 FD52 00 E111 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011504482 $15.41 000001073120-3562500061
2020 10 FD52 00 E121 D 9011101D 069 4/27/2020 0093 ENV STUDIES-PERMITTING MITIGA CA-XR042K1062011504482 $23.79 000001073120-3562500061
2020 10 FD52 00 E121 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011504482 $1.15 000001073120-3562500061
2020 10 FD52 00 E122 D 9011101D 069 4/27/2020 0093 ENV STUDIES-PERMITTING MITIGA CA-XR042K1062011504482 $267.81 000001073120-3562500061
2020 10 FD52 00 E122 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011504482 $12.86 000001073120-3562500061
2020 10 FD52 00 E123 D 9011101D 069 4/27/2020 0093 ENV STUDIES-PERMITTING MITIGA CA-XR042K1062011504482 $45.73 000001073120-3562500061
2020 10 FD52 00 E123 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011504482 $2.16 000001073120-3562500061
2020 10 FD52 00 E124 D 9011101D 069 4/27/2020 0093 ENV STUDIES-PERMITTING MITIGA CA-XR042K1062011504482 $0.14 000001073120-3562500061
2020 10 FD52 00 E124 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011504482 $0.01 000001073120-3562500061
2020 10 FD52 08 E111 D 9011101D 069 4/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042K1062011505011 $3,274.77
2020 10 FD52 00 E111 D 9011101D 069 4/27/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR042K1062011504431 $537.06 000001053089-3562500610
2020 10 FD52 08 E111 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011505011 $155.77
2020 10 FD52 00 E111 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011504431 $42.36 000001053089-3562500610
2020 10 FD52 08 E115 D 9011101D 069 4/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042K1062011505011 $117.38
2020 10 FD52 00 E121 D 9011101D 069 4/27/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR042K1062011504431 $40.24 000001053089-3562500610
2020 10 FD52 08 E121 D 9011101D 069 4/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042K1062011505011 $255.12
2020 10 FD52 00 E121 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011504431 $3.17 000001053089-3562500610
2020 10 FD52 08 E121 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011505011 $11.72
2020 10 FD52 00 E122 D 9011101D 069 4/27/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR042K1062011504431 $448.07 000001053089-3562500610
2020 10 FD52 08 E122 D 9011101D 069 4/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042K1062011505011 $2,830.38
2020 10 FD52 00 E122 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011504431 $35.34 000001053089-3562500610
2020 10 FD52 08 E122 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011505011 $129.96
2020 10 FD52 00 E123 D 9011101D 069 4/27/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR042K1062011504431 $75.46 000001053089-3562500610
2020 10 FD52 08 E123 D 9011101D 069 4/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042K1062011505011 $507.17
2020 10 FD52 00 E123 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011504431 $6.04 000001053089-3562500610
2020 10 FD52 08 E123 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011505011 $23.77
2020 10 FD52 00 E124 D 9011101D 069 4/27/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR042K1062011504431 $0.19 000001053089-3562500610
2020 10 FD52 08 E124 D 9011101D 069 4/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042K1062011505011 $1.45
2020 10 FD52 00 E124 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011504431 $0.02 000001053089-3562500610
2020 10 FD52 08 E124 D 9011101D 069 4/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042K1062011505011 $0.07
2020 10 FD52 08 E229 D 9011101D 069 4/13/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162520101002920 $86.50
2020 10 FD52 08 E229 D 9011101D 069 4/13/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162520101023840 $0.76
2020 10 FD52 08 E111 D 9011101D 069 4/9/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041K1062009903926 $2,416.06
2020 10 FD52 08 E121 D 9011101D 069 4/9/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041K1062009903926 $182.66
2020 10 FD52 08 E122 D 9011101D 069 4/9/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041K1062009903926 $2,015.71
2020 10 FD52 08 E123 D 9011101D 069 4/9/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041K1062009903926 $334.01
2020 9 FD52 08 E111 D 9011101D 069 3/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032K1062008402982 $1,585.03
2020 9 FD52 08 E111 D 9011101D 069 3/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032K1062008402982 $273.81
2020 9 FD52 08 E121 D 9011101D 069 3/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032K1062008402982 $119.61
2020 9 FD52 08 E121 D 9011101D 069 3/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032K1062008402982 $20.59
2020 9 FD52 08 E122 D 9011101D 069 3/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032K1062008402982 $1,322.48
2020 9 FD52 08 E122 D 9011101D 069 3/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032K1062008402982 $228.44
2020 9 FD52 08 E123 D 9011101D 069 3/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032K1062008402982 $233.96
2020 9 FD52 08 E123 D 9011101D 069 3/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032K1062008402982 $41.41
2020 9 FD52 08 E124 D 9011101D 069 3/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032K1062008402982 $0.70
2020 9 FD52 08 E124 D 9011101D 069 3/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032K1062008402982 $0.12
2020 9 FD52 00 E111 D 9011101D 069 3/25/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032K1062008402458 $379.47 000001047876-3562500636
2020 9 FD52 00 E121 D 9011101D 069 3/25/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032K1062008402458 $27.61 000001047876-3562500636
2020 9 FD52 00 E122 D 9011101D 069 3/25/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032K1062008402458 $316.59 000001047876-3562500636
2020 9 FD52 00 E123 D 9011101D 069 3/25/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032K1062008402458 $57.09 000001047876-3562500636
2020 9 FD52 00 E124 D 9011101D 069 3/25/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032K1062008402458 $0.10 000001047876-3562500636
2020 9 FD52 00 E123 D 9011101D 069 3/12/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR031K1062006601505 $259.15 000001053089-3562500610
2020 9 FD52 00 E123 D 9011101D 069 3/12/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601505 $46.28 000001053089-3562500610
2020 9 FD52 08 E143 D 9011101D 069 3/11/2020 1550 DESIGN CONTRACTS-CONSULTANT PRC-2000154976 PON21900004878 QK4 INC $49,892.21 Lincoln County 8-167
2020 9 FD52 00 E111 D 9011101D 069 3/9/2020 0093 ENV STUDIES-PERMITTING MITIGA CA-XR031K1062006601551 $1,412.39 000001073120-3562500061
2020 9 FD52 08 E111 D 9011101D 069 3/9/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031K1062006601961 $2,363.07
2020 9 FD52 00 E111 D 9011101D 069 3/9/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601551 $156.93 000001073120-3562500061
2020 9 FD52 08 E111 D 9011101D 069 3/9/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601961 $34.22
2020 9 FD52 00 E121 D 9011101D 069 3/9/2020 0093 ENV STUDIES-PERMITTING MITIGA CA-XR031K1062006601551 $104.67 000001073120-3562500061
2020 9 FD52 08 E121 D 9011101D 069 3/9/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031K1062006601961 $177.13
2020 9 FD52 00 E121 D 9011101D 069 3/9/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601551 $11.63 000001073120-3562500061
2020 9 FD52 08 E121 D 9011101D 069 3/9/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601961 $2.56
2020 9 FD52 00 E122 D 9011101D 069 3/9/2020 0093 ENV STUDIES-PERMITTING MITIGA CA-XR031K1062006601551 $1,178.36 000001073120-3562500061
2020 9 FD52 08 E122 D 9011101D 069 3/9/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031K1062006601961 $1,971.56
2020 9 FD52 00 E122 D 9011101D 069 3/9/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601551 $130.93 000001073120-3562500061
2020 9 FD52 08 E122 D 9011101D 069 3/9/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601961 $28.55
2020 9 FD52 00 E123 D 9011101D 069 3/9/2020 0093 ENV STUDIES-PERMITTING MITIGA CA-XR031K1062006601551 $201.40 000001073120-3562500061
2020 9 FD52 08 E123 D 9011101D 069 3/9/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031K1062006601961 $358.12
2020 9 FD52 00 E123 D 9011101D 069 3/9/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601551 $22.00 000001073120-3562500061
2020 9 FD52 08 E123 D 9011101D 069 3/9/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601961 $5.57
2020 9 FD52 00 E111 D 9011101D 069 3/9/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR031K1062006601504 $1,602.51 000001053089-3562500610
2020 9 FD52 00 E111 D 9011101D 069 3/9/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601504 $297.48 000001053089-3562500610
2020 9 FD52 00 E121 D 9011101D 069 3/9/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR031K1062006601504 $115.90 000001053089-3562500610
2020 9 FD52 00 E121 D 9011101D 069 3/9/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601504 $21.57 000001053089-3562500610
2020 9 FD52 00 E122 D 9011101D 069 3/9/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR031K1062006601504 $1,336.97 000001053089-3562500610
2020 9 FD52 00 E122 D 9011101D 069 3/9/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031K1062006601504 $248.18 000001053089-3562500610
2020 8 FD52 00 E111 D 9011101D 069 2/27/2020 0070 ENV STUDIES-HIST/CULTURAL CA-XR022K1062005200459 $79.41 000001073064-3562500061
2020 8 FD52 00 E111 D 9011101D 069 2/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005200459 $8.90 000001073064-3562500061
2020 8 FD52 00 E121 D 9011101D 069 2/27/2020 0070 ENV STUDIES-HIST/CULTURAL CA-XR022K1062005200459 $5.85 000001073064-3562500061
2020 8 FD52 00 E121 D 9011101D 069 2/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005200459 $0.65 000001073064-3562500061
2020 8 FD52 00 E122 D 9011101D 069 2/27/2020 0070 ENV STUDIES-HIST/CULTURAL CA-XR022K1062005200459 $66.02 000001073064-3562500061
2020 8 FD52 00 E122 D 9011101D 069 2/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005200459 $7.42 000001073064-3562500061
2020 8 FD52 00 E123 D 9011101D 069 2/24/2020 0070 ENV STUDIES-HIST/CULTURAL CA-XR022K1062005200460 $11.15 000001073064-3562500061
2020 8 FD52 08 E111 D 9011101D 069 2/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022K1062005201024 $2,565.97
2020 8 FD52 08 E111 D 9011101D 069 2/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005201024 $610.01
2020 8 FD52 08 E121 D 9011101D 069 2/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022K1062005201024 $191.17
2020 8 FD52 08 E121 D 9011101D 069 2/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005201024 $46.37
2020 8 FD52 08 E122 D 9011101D 069 2/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022K1062005201024 $2,140.98
2020 8 FD52 08 E122 D 9011101D 069 2/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005201024 $508.93
2020 8 FD52 08 E123 D 9011101D 069 2/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022K1062005201024 $439.45
2020 8 FD52 00 E123 D 9011101D 069 2/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005200460 $1.23 000001073064-3562500061
2020 8 FD52 08 E123 D 9011101D 069 2/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005201024 $99.02
2020 8 FD52 08 E124 D 9011101D 069 2/24/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022K1062005201024 $1.10
2020 8 FD52 08 E124 D 9011101D 069 2/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005201024 $0.28
2020 8 FD52 00 E124 D 9011101D 069 2/24/2020 0070 ENV STUDIES-HIST/CULTURAL CA-XR022K1062005200460 $0.03 000001073064-3562500061
2020 8 FD52 00 E111 D 9011101D 069 2/24/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR022K1062005200400 $815.02 000001053089-3562500610
2020 8 FD52 00 E111 D 9011101D 069 2/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005200400 $230.10 000001053089-3562500610
2020 8 FD52 00 E121 D 9011101D 069 2/24/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR022K1062005200400 $60.91 000001053089-3562500610
2020 8 FD52 00 E121 D 9011101D 069 2/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005200400 $17.20 000001053089-3562500610
2020 8 FD52 00 E122 D 9011101D 069 2/24/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR022K1062005200400 $679.97 000001053089-3562500610
2020 8 FD52 00 E122 D 9011101D 069 2/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005200400 $191.97 000001053089-3562500610
2020 8 FD52 00 E123 D 9011101D 069 2/24/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR022K1062005200400 $123.97 000001053089-3562500610
2020 8 FD52 00 E123 D 9011101D 069 2/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005200400 $34.47 000001053089-3562500610
2020 8 FD52 00 E124 D 9011101D 069 2/24/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR022K1062005200400 $0.29 000001053089-3562500610
2020 8 FD52 00 E124 D 9011101D 069 2/24/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022K1062005200400 $0.08 000001053089-3562500610
2020 8 FD52 08 E111 D 9011101D 069 2/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021K1062003810412 $2,640.07
2020 8 FD52 08 E111 D 9011101D 069 2/10/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021K1062003810412 $760.07
2020 8 FD52 08 E115 D 9011101D 069 2/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021K1062003810412 $39.51
2020 8 FD52 08 E121 D 9011101D 069 2/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021K1062003810412 $198.67
2020 8 FD52 08 E121 D 9011101D 069 2/10/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021K1062003810412 $53.83
2020 8 FD52 08 E122 D 9011101D 069 2/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021K1062003810412 $2,235.49
2020 8 FD52 08 E122 D 9011101D 069 2/10/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021K1062003810412 $634.13
2020 8 FD52 08 E123 D 9011101D 069 2/10/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021K1062003810412 $445.98
2020 8 FD52 08 E123 D 9011101D 069 2/10/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021K1062003810412 $173.88
2020 7 FD52 08 E143 D 9011101D 069 1/31/2020 1550 DESIGN CONTRACTS-CONSULTANT PRC-2000132193 PON21900004878 QK4 INC $3,755.52 Lincoln County 8-167
2020 7 FD52 00 E111 D 9011101D 069 1/27/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR012K1062002308806 $379.62 000001053089-3562500610
2020 7 FD52 00 E111 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002308806 $120.63 000001053089-3562500610
2020 7 FD52 00 E121 D 9011101D 069 1/27/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR012K1062002308806 $28.87 000001053089-3562500610
2020 7 FD52 00 E121 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002308806 $9.16 000001053089-3562500610
2020 7 FD52 00 E122 D 9011101D 069 1/27/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR012K1062002308806 $316.82 000001053089-3562500610
2020 7 FD52 00 E122 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002308806 $100.64 000001053089-3562500610
2020 7 FD52 00 E123 D 9011101D 069 1/27/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR012K1062002308806 $39.17 000001053089-3562500610
2020 7 FD52 00 E123 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002308806 $10.47 000001053089-3562500610
2020 7 FD52 00 E124 D 9011101D 069 1/27/2020 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR012K1062002308806 $0.19 000001053089-3562500610
2020 7 FD52 00 E124 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002308806 $0.05 000001053089-3562500610
2020 7 FD52 08 E111 D 9011101D 069 1/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012K1062002309375 $2,381.66
2020 7 FD52 08 E111 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002309375 $522.62
2020 7 FD52 08 E121 D 9011101D 069 1/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012K1062002309375 $178.10
2020 7 FD52 08 E121 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002309375 $39.03
2020 7 FD52 08 E122 D 9011101D 069 1/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012K1062002309375 $1,987.05
2020 7 FD52 08 E122 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002309375 $436.02
2020 7 FD52 08 E123 D 9011101D 069 1/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012K1062002309375 $348.01
2020 7 FD52 08 E123 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002309375 $79.88
2020 7 FD52 08 E124 D 9011101D 069 1/27/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012K1062002309375 $0.90
2020 7 FD52 08 E124 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002309375 $0.21
2020 7 FD52 00 E111 D 9011101D 069 1/27/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012K1062002308802 $344.97 000001047876-3562500636
2020 7 FD52 00 E111 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002308802 $34.50 000001047876-3562500636
2020 7 FD52 00 E121 D 9011101D 069 1/27/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012K1062002308802 $25.10 000001047876-3562500636
2020 7 FD52 00 E121 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002308802 $2.51 000001047876-3562500636
2020 7 FD52 00 E122 D 9011101D 069 1/27/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012K1062002308802 $287.81 000001047876-3562500636
2020 7 FD52 00 E122 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002308802 $28.78 000001047876-3562500636
2020 7 FD52 00 E123 D 9011101D 069 1/27/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012K1062002308802 $51.95 000001047876-3562500636
2020 7 FD52 00 E123 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002308802 $5.14 000001047876-3562500636
2020 7 FD52 00 E124 D 9011101D 069 1/27/2020 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR012K1062002308802 $0.09 000001047876-3562500636
2020 7 FD52 00 E124 D 9011101D 069 1/27/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012K1062002308802 $0.01 000001047876-3562500636
2020 7 FD52 08 E123 D 9011101D 069 1/15/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011K1062000808275 $284.88
2020 7 FD52 08 E111 D 9011101D 069 1/15/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011K1062000808274 $2,435.71
2020 7 FD52 08 E111 D 9011101D 069 1/15/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011K1062000808274 $1,782.22
2020 7 FD52 08 E121 D 9011101D 069 1/15/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011K1062000808274 $180.20
2020 7 FD52 08 E121 D 9011101D 069 1/15/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011K1062000808274 $131.95
2020 7 FD52 08 E122 D 9011101D 069 1/15/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011K1062000808274 $2,032.26
2020 7 FD52 08 E122 D 9011101D 069 1/15/2020 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011K1062000808274 $1,486.90
2020 7 FD52 08 E123 D 9011101D 069 1/15/2020 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011K1062000808274 $403.54
2020 7 FD52 08 E143 D 9011101D 069 1/13/2020 1550 DESIGN CONTRACTS-CONSULTANT PRC-2000114970 PON21900004878 QK4 INC $15,022.05 Lincoln County 8-167
2020 6 FD52 08 E121 D 9011101D 069 12/23/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122J1061935407379 $59.09
2020 6 FD52 08 E122 D 9011101D 069 12/23/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122J1061935407379 $2,268.93
2020 6 FD52 08 E122 D 9011101D 069 12/23/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122J1061935407379 $650.50
2020 6 FD52 08 E123 D 9011101D 069 12/23/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122J1061935407379 $269.56
2020 6 FD52 08 E123 D 9011101D 069 12/23/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122J1061935407379 $95.46
2020 6 FD52 08 E124 D 9011101D 069 12/23/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122J1061935407379 $0.80
2020 6 FD52 08 E124 D 9011101D 069 12/23/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122J1061935407379 $0.29
2020 6 FD52 08 E111 D 9011101D 069 12/23/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122J1061935407378 $2,719.43
2020 6 FD52 08 E111 D 9011101D 069 12/23/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122J1061935407378 $779.69
2020 6 FD52 08 E121 D 9011101D 069 12/23/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122J1061935407378 $206.54
2020 6 FD52 08 E111 D 9011101D 069 12/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121J1061934006308 $1,683.12
2020 6 FD52 08 E111 D 9011101D 069 12/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121J1061934006308 $921.33
2020 6 FD52 08 E121 D 9011101D 069 12/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121J1061934006308 $127.59
2020 6 FD52 08 E121 D 9011101D 069 12/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121J1061934006308 $69.76
2020 6 FD52 08 E122 D 9011101D 069 12/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121J1061934006308 $1,404.23
2020 6 FD52 08 E122 D 9011101D 069 12/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121J1061934006308 $768.66
2020 6 FD52 08 E123 D 9011101D 069 12/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121J1061934006308 $186.35
2020 6 FD52 08 E123 D 9011101D 069 12/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121J1061934006308 $101.60
2020 6 FD52 08 E143 D 9011101D 069 12/4/2019 1550 DESIGN CONTRACTS-CONSULTANT PRC-2000095153 PON21900004878 QK4 INC $9,125.24 Lincoln County 8-167
2020 5 FD52 08 E111 D 9011101D 069 11/26/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112J1061932505358 $2,601.02
2020 5 FD52 08 E111 D 9011101D 069 11/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112J1061932505358 $723.54
2020 5 FD52 08 E121 D 9011101D 069 11/26/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112J1061932505358 $197.47
2020 5 FD52 08 E121 D 9011101D 069 11/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112J1061932505358 $54.81
2020 5 FD52 08 E122 D 9011101D 069 11/26/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112J1061932505358 $2,169.97
2020 5 FD52 08 E122 D 9011101D 069 11/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112J1061932505358 $603.67
2020 5 FD52 08 E123 D 9011101D 069 11/26/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112J1061932505358 $250.54
2020 5 FD52 08 E123 D 9011101D 069 11/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112J1061932505358 $85.99
2020 5 FD52 08 E124 D 9011101D 069 11/26/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112J1061932505358 $0.74
2020 5 FD52 08 E124 D 9011101D 069 11/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112J1061932505358 $0.27
2020 5 FD52 08 E143 D 9011101D 069 11/13/2019 1550 DESIGN CONTRACTS-CONSULTANT PRC-2000085046 PON21900004878 QK4 INC $11,793.63 Lincoln County 8-167
2020 5 FD52 08 E143 D 9011101D 069 11/13/2019 1550 DESIGN CONTRACTS-CONSULTANT PRC-2000085091 PON21900004878 QK4 INC $22,170.70 Lincoln County 8-167
2020 5 FD52 08 E111 D 9011101D 069 11/12/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111J1061931104211 $1,524.97
2020 5 FD52 08 E111 D 9011101D 069 11/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111J1061931104211 $1,309.25
2020 5 FD52 08 E121 D 9011101D 069 11/12/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111J1061931104211 $115.46
2020 5 FD52 08 E121 D 9011101D 069 11/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111J1061931104211 $99.37
2020 5 FD52 08 E122 D 9011101D 069 11/12/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111J1061931104211 $1,272.30
2020 5 FD52 08 E122 D 9011101D 069 11/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111J1061931104211 $1,092.31
2020 5 FD52 08 E123 D 9011101D 069 11/12/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111J1061931104211 $195.14
2020 5 FD52 08 E123 D 9011101D 069 11/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111J1061931104211 $134.52
2020 4 FD52 08 E111 D 9011101D 069 10/31/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102J1061929703146 $1,271.79
2020 4 FD52 08 E111 D 9011101D 069 10/31/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102J1061929703146 $584.13
2020 4 FD52 08 E115 D 9011101D 069 10/31/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102J1061929703146 $19.56
2020 4 FD52 08 E121 D 9011101D 069 10/31/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102J1061929703146 $97.76
2020 4 FD52 08 E121 D 9011101D 069 10/31/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102J1061929703146 $44.30
2020 4 FD52 08 E122 D 9011101D 069 10/31/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102J1061929703146 $1,077.38
2020 4 FD52 08 E122 D 9011101D 069 10/31/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102J1061929703146 $487.34
2020 4 FD52 08 E123 D 9011101D 069 10/31/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102J1061929703146 $183.85
2020 4 FD52 08 E123 D 9011101D 069 10/31/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102J1061929703146 $69.32
2020 4 FD52 08 E124 D 9011101D 069 10/31/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102J1061929703146 $0.54
2020 4 FD52 08 E124 D 9011101D 069 10/31/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102J1061929703146 $0.21
2020 4 FD52 00 E111 D 9011101D 069 10/28/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR102J1061929702495 $345.13 000001047876-3562500636
2020 4 FD52 00 E111 D 9011101D 069 10/28/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102J1061929702495 $96.14 000001047876-3562500636
2020 4 FD52 00 E121 D 9011101D 069 10/28/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR102J1061929702495 $25.15 000001047876-3562500636
2020 4 FD52 00 E121 D 9011101D 069 10/28/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102J1061929702495 $7.01 000001047876-3562500636
2020 4 FD52 00 E122 D 9011101D 069 10/28/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR102J1061929702495 $287.82 000001047876-3562500636
2020 4 FD52 00 E122 D 9011101D 069 10/28/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102J1061929702495 $80.21 000001047876-3562500636
2020 4 FD52 00 E123 D 9011101D 069 10/28/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR102J1061929702495 $52.03 000001047876-3562500636
2020 4 FD52 00 E123 D 9011101D 069 10/28/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102J1061929702495 $14.34 000001047876-3562500636
2020 4 FD52 00 E124 D 9011101D 069 10/28/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR102J1061929702495 $0.09 000001047876-3562500636
2020 4 FD52 00 E124 D 9011101D 069 10/28/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102J1061929702495 $0.02 000001047876-3562500636
2020 4 FD52 08 E111 D 9011101D 069 10/15/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101J1061928101982 $1,580.29
2020 4 FD52 08 E111 D 9011101D 069 10/15/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101J1061928101982 $142.86
2020 4 FD52 08 E121 D 9011101D 069 10/15/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101J1061928101982 $119.69
2020 4 FD52 08 E121 D 9011101D 069 10/15/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101J1061928101982 $10.84
2020 4 FD52 08 E122 D 9011101D 069 10/15/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101J1061928101982 $1,318.39
2020 4 FD52 08 E122 D 9011101D 069 10/15/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101J1061928101982 $119.19
2020 4 FD52 08 E123 D 9011101D 069 10/15/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101J1061928101982 $213.46
2020 4 FD52 08 E123 D 9011101D 069 10/15/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101J1061928101982 $14.24
2020 4 FD52 08 E143 D 9011101D 069 10/4/2019 1550 DESIGN CONTRACTS-CONSULTANT PRC-2000043093 PON21900004878 QK4 INC $4,842.64 Lincoln County 8-167
2020 3 FD52 08 E111 D 9011101D 069 9/27/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092J1061926700974 $1,314.14
2020 3 FD52 08 E111 D 9011101D 069 9/27/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092J1061926700974 $1,290.25
2020 3 FD52 08 E121 D 9011101D 069 9/27/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092J1061926700974 $99.61
2020 3 FD52 08 E121 D 9011101D 069 9/27/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092J1061926700974 $97.89
2020 3 FD52 08 E122 D 9011101D 069 9/27/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092J1061926700974 $1,096.59
2020 3 FD52 08 E122 D 9011101D 069 9/27/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092J1061926700974 $1,076.45
2020 3 FD52 08 E123 D 9011101D 069 9/27/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092J1061926700974 $169.73
2020 3 FD52 08 E123 D 9011101D 069 9/27/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092J1061926700974 $141.42
2020 3 FD52 08 E124 D 9011101D 069 9/27/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092J1061926700974 $0.50
2020 3 FD52 08 E124 D 9011101D 069 9/27/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092J1061926700974 $0.43
2020 3 FD52 00 E111 D 9011101D 069 9/25/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092J1061926700377 $379.47 000001047876-3562500636
2020 3 FD52 00 E111 D 9011101D 069 9/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092J1061926700377 $252.99 000001047876-3562500636
2020 3 FD52 00 E121 D 9011101D 069 9/25/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092J1061926700377 $27.66 000001047876-3562500636
2020 3 FD52 00 E121 D 9011101D 069 9/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092J1061926700377 $18.44 000001047876-3562500636
2020 3 FD52 00 E122 D 9011101D 069 9/25/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092J1061926700377 $316.60 000001047876-3562500636
2020 3 FD52 00 E122 D 9011101D 069 9/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092J1061926700377 $211.07 000001047876-3562500636
2020 3 FD52 00 E123 D 9011101D 069 9/25/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092J1061926700377 $57.43 000001047876-3562500636
2020 3 FD52 00 E123 D 9011101D 069 9/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092J1061926700377 $37.72 000001047876-3562500636
2020 3 FD52 00 E124 D 9011101D 069 9/25/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR092J1061926700377 $0.10 000001047876-3562500636
2020 3 FD52 00 E124 D 9011101D 069 9/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092J1061926700377 $0.07 000001047876-3562500636
2020 3 FD52 08 E111 D 9011101D 069 9/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091J1061924909888 $1,452.71
2020 3 FD52 08 E111 D 9011101D 069 9/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091J1061924909888 $605.77
2020 3 FD52 08 E121 D 9011101D 069 9/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091J1061924909888 $109.93
2020 3 FD52 08 E121 D 9011101D 069 9/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091J1061924909888 $45.79
2020 3 FD52 08 E122 D 9011101D 069 9/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091J1061924909888 $1,211.57
2020 3 FD52 08 E122 D 9011101D 069 9/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091J1061924909888 $505.39
2020 3 FD52 08 E123 D 9011101D 069 9/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091J1061924909888 $195.61
2020 3 FD52 08 E123 D 9011101D 069 9/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091J1061924909888 $84.65
2020 2 FD52 00 E229 D 9011101D 069 8/30/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF IET-XE13A162519241001720 $91.50
2020 2 FD52 08 E229 D 9011101D 069 8/30/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162519241001620 $170.50
2020 2 FD52 08 E111 D 9011101D 069 8/26/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082J1061923508780 $1,787.81
2020 2 FD52 08 E111 D 9011101D 069 8/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082J1061923508780 $394.58
2020 2 FD52 08 E121 D 9011101D 069 8/26/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082J1061923508780 $135.37
2020 2 FD52 08 E121 D 9011101D 069 8/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082J1061923508780 $29.92
2020 2 FD52 08 E122 D 9011101D 069 8/26/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082J1061923508780 $1,491.41
2020 2 FD52 08 E122 D 9011101D 069 8/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082J1061923508780 $329.20
2020 2 FD52 08 E123 D 9011101D 069 8/26/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082J1061923508780 $212.60
2020 2 FD52 08 E123 D 9011101D 069 8/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082J1061923508780 $40.84
2020 2 FD52 08 E124 D 9011101D 069 8/26/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082J1061923508780 $0.63
2020 2 FD52 08 E124 D 9011101D 069 8/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082J1061923508780 $0.12
2020 2 FD52 00 E111 D 9011101D 069 8/26/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR082J1061923508064 $689.78 000001047876-3562500636
2020 2 FD52 00 E111 D 9011101D 069 8/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082J1061923508064 $159.61 000001047876-3562500636
2020 2 FD52 00 E121 D 9011101D 069 8/26/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR082J1061923508064 $50.28 000001047876-3562500636
2020 2 FD52 00 E121 D 9011101D 069 8/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082J1061923508064 $11.63 000001047876-3562500636
2020 2 FD52 00 E122 D 9011101D 069 8/26/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR082J1061923508064 $575.63 000001047876-3562500636
2020 2 FD52 00 E122 D 9011101D 069 8/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082J1061923508064 $133.16 000001047876-3562500636
2020 2 FD52 00 E123 D 9011101D 069 8/26/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR082J1061923508064 $104.02 000001047876-3562500636
2020 2 FD52 00 E123 D 9011101D 069 8/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082J1061923508064 $23.80 000001047876-3562500636
2020 2 FD52 00 E124 D 9011101D 069 8/26/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR082J1061923508064 $0.18 000001047876-3562500636
2020 2 FD52 00 E124 D 9011101D 069 8/26/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082J1061923508064 $0.04 000001047876-3562500636
2020 2 FD52 00 E123 D 9011101D 069 8/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081J1061922106902 $6.92 000001047876-3562500636
2020 2 FD52 08 E111 D 9011101D 069 8/12/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081J1061922107527 $1,649.99
2020 2 FD52 08 E111 D 9011101D 069 8/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081J1061922107527 $91.98
2020 2 FD52 08 E121 D 9011101D 069 8/12/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081J1061922107527 $125.03
2020 2 FD52 08 E121 D 9011101D 069 8/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081J1061922107527 $6.93
2020 2 FD52 08 E122 D 9011101D 069 8/12/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081J1061922107527 $1,376.55
2020 2 FD52 08 E122 D 9011101D 069 8/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081J1061922107527 $76.74
2020 2 FD52 08 E123 D 9011101D 069 8/12/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR081J1061922107527 $195.15
2020 2 FD52 08 E123 D 9011101D 069 8/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081J1061922107527 $14.43
2020 2 FD52 00 E111 D 9011101D 069 8/12/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081J1061922106901 $316.19 000001047876-3562500636
2020 2 FD52 00 E111 D 9011101D 069 8/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081J1061922106901 $46.38 000001047876-3562500636
2020 2 FD52 00 E121 D 9011101D 069 8/12/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081J1061922106901 $23.05 000001047876-3562500636
2020 2 FD52 00 E121 D 9011101D 069 8/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081J1061922106901 $3.38 000001047876-3562500636
2020 2 FD52 00 E122 D 9011101D 069 8/12/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081J1061922106901 $263.82 000001047876-3562500636
2020 2 FD52 00 E122 D 9011101D 069 8/12/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081J1061922106901 $38.69 000001047876-3562500636
2020 2 FD52 00 E123 D 9011101D 069 8/12/2019 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081J1061922106901 $47.64 000001047876-3562500636
2020 1 FD52 08 E111 D 9011101D 069 7/24/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072J1061920406421 $908.02
2020 1 FD52 08 E111 D 9011101D 069 7/24/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072J1061920406421 $369.13
2020 1 FD52 08 E121 D 9011101D 069 7/24/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072J1061920406421 $68.73
2020 1 FD52 08 E121 D 9011101D 069 7/24/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072J1061920406421 $27.88
2020 1 FD52 08 E122 D 9011101D 069 7/24/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072J1061920406421 $757.68
2020 1 FD52 08 E122 D 9011101D 069 7/24/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072J1061920406421 $307.97
2020 1 FD52 08 E123 D 9011101D 069 7/24/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072J1061920406421 $113.93
2020 1 FD52 08 E123 D 9011101D 069 7/24/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072J1061920406421 $53.87
2020 1 FD52 08 E124 D 9011101D 069 7/24/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR072J1061920406421 $0.39
2020 1 FD52 08 E124 D 9011101D 069 7/24/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072J1061920406421 $0.16
2020 1 FD52 08 E229 D 9011101D 069 7/16/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162519165016600 $42.24
2020 1 FD52 08 E111 D 9011101D 069 7/10/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071J1061919005288 $1,880.72
2020 1 FD52 08 E111 D 9011101D 069 7/10/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071J1061919005288 $763.86
2020 1 FD52 08 E121 D 9011101D 069 7/10/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071J1061919005288 $142.40
2020 1 FD52 08 E121 D 9011101D 069 7/10/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071J1061919005288 $57.96
2020 1 FD52 08 E122 D 9011101D 069 7/10/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071J1061919005288 $1,569.18
2020 1 FD52 08 E122 D 9011101D 069 7/10/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071J1061919005288 $637.29
2020 1 FD52 08 E123 D 9011101D 069 7/10/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR071J1061919005288 $239.61
2020 1 FD52 08 E123 D 9011101D 069 7/10/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071J1061919005288 $79.43
2020 1 FD52 08 E123 D 9011101D 069 7/1/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061J1061915803116P $167.43
2020 1 FD52 08 E123 D 9011101D 069 7/1/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061J1061915803116P $155.94
2020 1 FD52 08 E111 D 9011101D 069 7/1/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062J1061917104260 $1,428.59
2020 1 FD52 08 E111 D 9011101D 069 7/1/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062J1061917104260 $39.19
2020 1 FD52 08 E121 D 9011101D 069 7/1/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062J1061917104260 $108.22
2020 1 FD52 08 E121 D 9011101D 069 7/1/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062J1061917104260 $2.97
2020 1 FD52 08 E122 D 9011101D 069 7/1/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062J1061917104260 $1,191.95
2020 1 FD52 08 E122 D 9011101D 069 7/1/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062J1061917104260 $32.69
2020 1 FD52 08 E123 D 9011101D 069 7/1/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062J1061917104260 $166.98
2020 1 FD52 08 E123 D 9011101D 069 7/1/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062J1061917104260 $4.54
2020 1 FD52 08 E124 D 9011101D 069 7/1/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR062J1061917104260 $0.49
2020 1 FD52 08 E124 D 9011101D 069 7/1/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062J1061917104260 $0.02
2019 12 FD52 08 E111 D 9011101D 069 6/10/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061J1061915803116 $1,192.48
2019 12 FD52 08 E111 D 9011101D 069 6/10/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061J1061915803116 $1,132.59
2019 12 FD52 08 E121 D 9011101D 069 6/10/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061J1061915803116 $90.21
2019 12 FD52 08 E121 D 9011101D 069 6/10/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061J1061915803116 $85.73
2019 12 FD52 08 E122 D 9011101D 069 6/10/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR061J1061915803116 $994.38
2019 12 FD52 08 E122 D 9011101D 069 6/10/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061J1061915803116 $944.94
2019 11 FD52 08 E229 D 9011101D 069 5/29/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162519145001650 $118.50
2019 11 FD52 08 E123 D 9011101D 069 5/23/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052J1061914202014 $59.38
2019 11 FD52 08 E124 D 9011101D 069 5/23/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052J1061914202014 $0.62
2019 11 FD52 08 E124 D 9011101D 069 5/23/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052J1061914202014 $0.18
2019 11 FD52 08 E111 D 9011101D 069 5/23/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052J1061914202014 $1,404.60
2019 11 FD52 08 E111 D 9011101D 069 5/23/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052J1061914202014 $372.44
2019 11 FD52 08 E121 D 9011101D 069 5/23/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052J1061914202014 $106.07
2019 11 FD52 08 E121 D 9011101D 069 5/23/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052J1061914202014 $28.02
2019 11 FD52 08 E122 D 9011101D 069 5/23/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052J1061914202014 $1,171.87
2019 11 FD52 08 E122 D 9011101D 069 5/23/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052J1061914202014 $310.73
2019 11 FD52 08 E123 D 9011101D 069 5/23/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR052J1061914202014 $207.00
2019 11 FD52 08 E111 D 9011101D 069 5/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051J1061912800786 $1,196.60
2019 11 FD52 08 E111 D 9011101D 069 5/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051J1061912800786 $123.81
2019 11 FD52 08 E121 D 9011101D 069 5/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051J1061912800786 $90.59
2019 11 FD52 08 E121 D 9011101D 069 5/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051J1061912800786 $9.33
2019 11 FD52 08 E122 D 9011101D 069 5/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051J1061912800786 $998.29
2019 11 FD52 08 E122 D 9011101D 069 5/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051J1061912800786 $103.29
2019 11 FD52 08 E123 D 9011101D 069 5/9/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR051J1061912800786 $136.47
2019 11 FD52 08 E123 D 9011101D 069 5/9/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051J1061912800786 $17.26
2019 11 FD52 08 E229 D 9011101D 069 5/3/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF IET-XE13A162519123007860 $148.00
2019 10 FD52 08 E111 D 9011101D 069 4/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042J1061911410639 $2,045.98
2019 10 FD52 08 E111 D 9011101D 069 4/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042J1061911410639 $314.39
2019 10 FD52 08 E121 D 9011101D 069 4/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042J1061911410639 $154.62
2019 10 FD52 08 E121 D 9011101D 069 4/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042J1061911410639 $23.78
2019 10 FD52 08 E122 D 9011101D 069 4/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042J1061911410639 $1,706.84
2019 10 FD52 08 E122 D 9011101D 069 4/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042J1061911410639 $262.29
2019 10 FD52 08 E123 D 9011101D 069 4/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042J1061911410639 $273.02
2019 10 FD52 08 E123 D 9011101D 069 4/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042J1061911410639 $40.83
2019 10 FD52 08 E124 D 9011101D 069 4/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR042J1061911410639 $0.81
2019 10 FD52 08 E124 D 9011101D 069 4/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042J1061911410639 $0.12
2019 10 FD52 08 E111 D 9011101D 069 4/10/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041J1061909909652 $1,653.65
2019 10 FD52 08 E111 D 9011101D 069 4/10/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041J1061909909652 $113.09
2019 10 FD52 08 E121 D 9011101D 069 4/10/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041J1061909909652 $125.36
2019 10 FD52 08 E121 D 9011101D 069 4/10/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041J1061909909652 $8.59
2019 10 FD52 08 E122 D 9011101D 069 4/10/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041J1061909909652 $1,379.65
2019 10 FD52 08 E122 D 9011101D 069 4/10/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041J1061909909652 $94.35
2019 10 FD52 08 E123 D 9011101D 069 4/10/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR041J1061909909652 $201.23
2019 10 FD52 08 E123 D 9011101D 069 4/10/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041J1061909909652 $11.00
2019 9 FD52 08 E111 D 9011101D 069 3/25/2019 7010 OVERHEAD EXCEPT MAIN AND EQUIP CA-XR032J1061908107987 $81.71 000001066964-3562500019
2019 9 FD52 08 E111 D 9011101D 069 3/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032J1061908107987 $11.98 000001066964-3562500019
2019 9 FD52 08 E121 D 9011101D 069 3/25/2019 7010 OVERHEAD EXCEPT MAIN AND EQUIP CA-XR032J1061908107987 $6.13 000001066964-3562500019
2019 9 FD52 08 E121 D 9011101D 069 3/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032J1061908107987 $0.90 000001066964-3562500019
2019 9 FD52 08 E122 D 9011101D 069 3/25/2019 7010 OVERHEAD EXCEPT MAIN AND EQUIP CA-XR032J1061908107987 $68.17 000001066964-3562500019
2019 9 FD52 08 E111 D 9011101D 069 3/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032J1061908108637 $1,233.74
2019 9 FD52 08 E122 D 9011101D 069 3/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032J1061908107987 $9.99 000001066964-3562500019
2019 9 FD52 08 E121 D 9011101D 069 3/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032J1061908108637 $95.67
2019 9 FD52 08 E123 D 9011101D 069 3/25/2019 7010 OVERHEAD EXCEPT MAIN AND EQUIP CA-XR032J1061908107987 $11.97 000001066964-3562500019
2019 9 FD52 08 E122 D 9011101D 069 3/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032J1061908108637 $1,029.31
2019 9 FD52 08 E123 D 9011101D 069 3/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032J1061908107987 $1.72 000001066964-3562500019
2019 9 FD52 08 E123 D 9011101D 069 3/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032J1061908108637 $121.86
2019 9 FD52 08 E124 D 9011101D 069 3/25/2019 7010 OVERHEAD EXCEPT MAIN AND EQUIP CA-XR032J1061908107987 $0.04 000001066964-3562500019
2019 9 FD52 08 E124 D 9011101D 069 3/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR032J1061908108637 $0.36
2019 9 FD52 08 E124 D 9011101D 069 3/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032J1061908107987 $0.01 000001066964-3562500019
2019 9 FD52 08 E111 D 9011101D 069 3/11/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031J1061906707406 $1,369.54
2019 9 FD52 08 E111 D 9011101D 069 3/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031J1061906707406 $36.25
2019 9 FD52 08 E121 D 9011101D 069 3/11/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031J1061906707406 $104.31
2019 9 FD52 08 E121 D 9011101D 069 3/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031J1061906707406 $2.81
2019 9 FD52 08 E122 D 9011101D 069 3/11/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031J1061906707406 $1,142.61
2019 9 FD52 08 E122 D 9011101D 069 3/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031J1061906707406 $30.24
2019 9 FD52 08 E123 D 9011101D 069 3/11/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR031J1061906707406 $182.13
2019 9 FD52 08 E123 D 9011101D 069 3/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031J1061906707406 $2.88
2019 8 FD52 08 E111 D 9011101D 069 2/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022J1061905306361 $807.88
2019 8 FD52 08 E111 D 9011101D 069 2/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022J1061905306361 $16.91
2019 8 FD52 08 E121 D 9011101D 069 2/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022J1061905306361 $60.54
2019 8 FD52 08 E121 D 9011101D 069 2/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022J1061905306361 $1.26
2019 8 FD52 08 E122 D 9011101D 069 2/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022J1061905306361 $673.97
2019 8 FD52 08 E122 D 9011101D 069 2/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022J1061905306361 $14.11
2019 8 FD52 08 E123 D 9011101D 069 2/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022J1061905306361 $129.45
2019 8 FD52 08 E123 D 9011101D 069 2/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022J1061905306361 $3.06
2019 8 FD52 08 E124 D 9011101D 069 2/25/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR022J1061905306361 $0.35
2019 8 FD52 08 E124 D 9011101D 069 2/25/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022J1061905306361 $0.01
2019 8 FD52 00 E122 D 9011101D 069 2/11/2019 0010 ENV STUDIES-UST/HZM CA-XR021J1061903904523 $155.82 000001066266-3562500061
2019 8 FD52 00 E122 D 9011101D 069 2/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021J1061903904523 $78.04 000001066266-3562500061
2019 8 FD52 08 E111 D 9011101D 069 2/11/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021J1061903905083 $789.03
2019 8 FD52 08 E111 D 9011101D 069 2/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021J1061903905083 $78.39
2019 8 FD52 00 E123 D 9011101D 069 2/11/2019 0010 ENV STUDIES-UST/HZM CA-XR021J1061903904523 $40.58 000001066266-3562500061
2019 8 FD52 08 E121 D 9011101D 069 2/11/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021J1061903905083 $59.04
2019 8 FD52 08 E121 D 9011101D 069 2/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021J1061903905083 $5.87
2019 8 FD52 08 E122 D 9011101D 069 2/11/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021J1061903905083 $658.28
2019 8 FD52 08 E122 D 9011101D 069 2/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021J1061903905083 $65.40
2019 8 FD52 08 E123 D 9011101D 069 2/11/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR021J1061903905083 $131.04
2019 8 FD52 08 E123 D 9011101D 069 2/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021J1061903905083 $13.09
2019 8 FD52 00 E123 D 9011101D 069 2/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021J1061903904523 $19.84 000001066266-3562500061
2019 8 FD52 00 E111 D 9011101D 069 2/11/2019 0010 ENV STUDIES-UST/HZM CA-XR021J1061903904522 $186.74 000001066266-3562500061
2019 8 FD52 00 E111 D 9011101D 069 2/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021J1061903904522 $93.55 000001066266-3562500061
2019 8 FD52 00 E121 D 9011101D 069 2/11/2019 0010 ENV STUDIES-UST/HZM CA-XR021J1061903904522 $13.86 000001066266-3562500061
2019 8 FD52 00 E121 D 9011101D 069 2/11/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021J1061903904522 $6.95 000001066266-3562500061
2019 7 FD52 08 E111 D 9011101D 069 1/29/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012J1061902303979 $693.66
2019 7 FD52 08 E111 D 9011101D 069 1/29/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012J1061902303979 $78.82
2019 7 FD52 08 E121 D 9011101D 069 1/29/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012J1061902303979 $52.02
2019 7 FD52 08 E121 D 9011101D 069 1/29/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012J1061902303979 $5.92
2019 7 FD52 08 E122 D 9011101D 069 1/29/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012J1061902303979 $578.19
2019 7 FD52 08 E122 D 9011101D 069 1/29/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012J1061902303979 $65.77
2019 7 FD52 08 E123 D 9011101D 069 1/29/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012J1061902303979 $108.91
2019 7 FD52 08 E123 D 9011101D 069 1/29/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012J1061902303979 $11.66
2019 7 FD52 08 E124 D 9011101D 069 1/29/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR012J1061902303979 $0.27
2019 7 FD52 08 E124 D 9011101D 069 1/29/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012J1061902303979 $0.03
2019 7 FD52 00 E111 D 9011101D 069 1/24/2019 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR012J1061902303371 $1,199.99 000001053089-3562500610
2019 7 FD52 00 E111 D 9011101D 069 1/24/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012J1061902303371 $181.60 000001053089-3562500610
2019 7 FD52 00 E121 D 9011101D 069 1/24/2019 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR012J1061902303371 $87.34 000001053089-3562500610
2019 7 FD52 00 E121 D 9011101D 069 1/24/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012J1061902303371 $13.31 000001053089-3562500610
2019 7 FD52 00 E122 D 9011101D 069 1/24/2019 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR012J1061902303371 $1,001.13 000001053089-3562500610
2019 7 FD52 00 E122 D 9011101D 069 1/24/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012J1061902303371 $151.51 000001053089-3562500610
2019 7 FD52 00 E123 D 9011101D 069 1/24/2019 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR012J1061902303371 $228.27 000001053089-3562500610
2019 7 FD52 00 E123 D 9011101D 069 1/24/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012J1061902303371 $34.81 000001053089-3562500610
2019 7 FD52 00 E124 D 9011101D 069 1/24/2019 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR012J1061902303371 $0.47 000001053089-3562500610
2019 7 FD52 00 E124 D 9011101D 069 1/24/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012J1061902303371 $0.08 000001053089-3562500610
2019 7 FD52 08 E111 D 9011101D 069 1/14/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011J1061900902856 $616.87
2019 7 FD52 08 E111 D 9011101D 069 1/14/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011J1061900902856 $655.52
2019 7 FD52 08 E121 D 9011101D 069 1/14/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011J1061900902856 $46.85
2019 7 FD52 08 E121 D 9011101D 069 1/14/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011J1061900902856 $49.78
2019 7 FD52 08 E122 D 9011101D 069 1/14/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011J1061900902856 $514.65
2019 7 FD52 08 E122 D 9011101D 069 1/14/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011J1061900902856 $546.90
2019 7 FD52 08 E123 D 9011101D 069 1/14/2019 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR011J1061900902856 $61.91
2019 7 FD52 08 E123 D 9011101D 069 1/14/2019 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011J1061900902856 $63.76
2019 6 FD52 08 E111 D 9011101D 069 12/27/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122I1061835402019 $1,102.27
2019 6 FD52 08 E111 D 9011101D 069 12/26/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122I1061835402020 $151.69
2019 6 FD52 08 E121 D 9011101D 069 12/26/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122I1061835402020 $83.14
2019 6 FD52 08 E121 D 9011101D 069 12/26/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122I1061835402020 $11.46
2019 6 FD52 08 E122 D 9011101D 069 12/26/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122I1061835402020 $919.76
2019 6 FD52 08 E122 D 9011101D 069 12/26/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122I1061835402020 $126.55
2019 6 FD52 08 E123 D 9011101D 069 12/26/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122I1061835402020 $153.48
2019 6 FD52 08 E123 D 9011101D 069 12/26/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122I1061835402020 $19.64
2019 6 FD52 08 E124 D 9011101D 069 12/26/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR122I1061835402020 $0.40
2019 6 FD52 08 E124 D 9011101D 069 12/26/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122I1061835402020 $0.04
2019 6 FD52 08 E111 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100797 $368.01
2019 6 FD52 08 E121 D 9011101D 069 12/13/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121I1061834100797 $45.35
2019 6 FD52 08 E121 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100797 $27.76
2019 6 FD52 08 E122 D 9011101D 069 12/13/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121I1061834100797 $503.80
2019 6 FD52 08 E122 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100797 $307.04
2019 6 FD52 08 E123 D 9011101D 069 12/13/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121I1061834100797 $91.19
2019 6 FD52 08 E123 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100797 $47.31
2019 6 FD52 00 E111 D 9011101D 069 12/13/2018 0060 ENV STUDIES-ARCHAEOLOGY CA-XR121I1061834100376 $62.32 000001065830-3562500061
2019 6 FD52 00 E111 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100376 $24.72 000001065830-3562500061
2019 6 FD52 00 E121 D 9011101D 069 12/13/2018 0060 ENV STUDIES-ARCHAEOLOGY CA-XR121I1061834100376 $4.65 000001065830-3562500061
2019 6 FD52 00 E121 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100376 $1.84 000001065830-3562500061
2019 6 FD52 00 E122 D 9011101D 069 12/13/2018 0060 ENV STUDIES-ARCHAEOLOGY CA-XR121I1061834100376 $52.01 000001065830-3562500061
2019 6 FD52 00 E111 D 9011101D 069 12/13/2018 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR121I1061834100326 $230.69 000001047876-3562500636
2019 6 FD52 00 E122 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100376 $20.62 000001065830-3562500061
2019 6 FD52 00 E111 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100326 $86.67 000001047876-3562500636
2019 6 FD52 00 E121 D 9011101D 069 12/13/2018 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR121I1061834100326 $16.19 000001047876-3562500636
2019 6 FD52 00 E121 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100326 $6.09 000001047876-3562500636
2019 6 FD52 00 E122 D 9011101D 069 12/13/2018 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR121I1061834100326 $192.40 000001047876-3562500636
2019 6 FD52 00 E122 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100326 $72.30 000001047876-3562500636
2019 6 FD52 00 E123 D 9011101D 069 12/13/2018 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR121I1061834100326 $48.54 000001047876-3562500636
2019 6 FD52 00 E123 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100326 $18.03 000001047876-3562500636
2019 6 FD52 00 E123 D 9011101D 069 12/13/2018 0060 ENV STUDIES-ARCHAEOLOGY CA-XR121I1061834100376 $12.00 000001065830-3562500061
2019 6 FD52 00 E123 D 9011101D 069 12/13/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121I1061834100376 $4.67 000001065830-3562500061
2019 6 FD52 08 E111 D 9011101D 069 12/13/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR121I1061834100797 $603.80
2019 5 FD52 08 E111 D 9011101D 069 11/27/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112I1061833010113 $1,067.25
2019 5 FD52 08 E111 D 9011101D 069 11/27/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112I1061833010113 $291.83
2019 5 FD52 08 E121 D 9011101D 069 11/27/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112I1061833010113 $79.97
2019 5 FD52 08 E121 D 9011101D 069 11/27/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112I1061833010113 $21.90
2019 5 FD52 08 E122 D 9011101D 069 11/27/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112I1061833010113 $889.94
2019 5 FD52 08 E122 D 9011101D 069 11/27/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112I1061833010113 $243.48
2019 5 FD52 08 E123 D 9011101D 069 11/27/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112I1061833010113 $179.09
2019 5 FD52 08 E123 D 9011101D 069 11/27/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112I1061833010113 $47.42
2019 5 FD52 08 E124 D 9011101D 069 11/27/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR112I1061833010113 $0.43
2019 5 FD52 08 E124 D 9011101D 069 11/27/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112I1061833010113 $0.14
2019 5 FD52 08 E111 D 9011101D 069 11/15/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111I1061831308940 $1,427.74
2019 5 FD52 08 E111 D 9011101D 069 11/15/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111I1061831308940 $180.71
2019 5 FD52 08 E121 D 9011101D 069 11/15/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111I1061831308940 $107.82
2019 5 FD52 08 E121 D 9011101D 069 11/15/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111I1061831308940 $13.51
2019 5 FD52 08 E122 D 9011101D 069 11/15/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111I1061831308940 $1,191.06
2019 5 FD52 08 E122 D 9011101D 069 11/15/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111I1061831308940 $150.77
2019 5 FD52 08 E123 D 9011101D 069 11/15/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR111I1061831308940 $178.33
2019 5 FD52 08 E123 D 9011101D 069 11/15/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111I1061831308940 $29.78
2019 4 FD52 08 E123 D 9011101D 069 10/25/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102I1061829707837 $131.52
2019 4 FD52 08 E123 D 9011101D 069 10/25/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102I1061829707837 $27.13
2019 4 FD52 08 E124 D 9011101D 069 10/25/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102I1061829707837 $0.34
2019 4 FD52 08 E124 D 9011101D 069 10/25/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102I1061829707837 $0.07
2019 4 FD52 08 E111 D 9011101D 069 10/25/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102I1061829707837 $920.10
2019 4 FD52 08 E111 D 9011101D 069 10/25/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102I1061829707837 $191.19
2019 4 FD52 08 E121 D 9011101D 069 10/25/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102I1061829707837 $69.21
2019 4 FD52 08 E121 D 9011101D 069 10/25/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102I1061829707837 $14.38
2019 4 FD52 08 E122 D 9011101D 069 10/25/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR102I1061829707837 $767.53
2019 4 FD52 08 E122 D 9011101D 069 10/25/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102I1061829707837 $159.50
2019 4 FD52 08 E111 D 9011101D 069 10/10/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101I1061828206666 $622.91
2019 4 FD52 08 E111 D 9011101D 069 10/10/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101I1061828206666 $616.40
2019 4 FD52 08 E121 D 9011101D 069 10/10/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101I1061828206666 $46.48
2019 4 FD52 08 E121 D 9011101D 069 10/10/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101I1061828206666 $46.54
2019 4 FD52 08 E122 D 9011101D 069 10/10/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101I1061828206666 $519.60
2019 4 FD52 08 E122 D 9011101D 069 10/10/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101I1061828206666 $514.27
2019 4 FD52 08 E123 D 9011101D 069 10/10/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR101I1061828206666 $121.28
2019 4 FD52 08 E123 D 9011101D 069 10/10/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101I1061828206666 $103.32
2019 3 FD52 08 E111 D 9011101D 069 9/24/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092I1061826405683 $1,102.25
2019 3 FD52 08 E111 D 9011101D 069 9/24/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092I1061826405683 $686.56
2019 3 FD52 08 E121 D 9011101D 069 9/24/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092I1061826405683 $82.99
2019 3 FD52 08 E121 D 9011101D 069 9/24/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092I1061826405683 $51.92
2019 3 FD52 08 E122 D 9011101D 069 9/24/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092I1061826405683 $919.76
2019 3 FD52 08 E122 D 9011101D 069 9/24/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092I1061826405683 $572.80
2019 3 FD52 08 E123 D 9011101D 069 9/24/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092I1061826405683 $154.37
2019 3 FD52 08 E123 D 9011101D 069 9/24/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092I1061826405683 $81.16
2019 3 FD52 08 E124 D 9011101D 069 9/24/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR092I1061826405683 $0.40
2019 3 FD52 08 E124 D 9011101D 069 9/24/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092I1061826405683 $0.24
2019 3 FD52 08 E111 D 9011101D 069 9/10/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091I1061825004467 $1,175.53
2019 3 FD52 08 E111 D 9011101D 069 9/10/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091I1061825004467 $438.13
2019 3 FD52 08 E121 D 9011101D 069 9/10/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091I1061825004467 $88.47
2019 3 FD52 08 E121 D 9011101D 069 9/10/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091I1061825004467 $33.09
2019 3 FD52 08 E122 D 9011101D 069 9/10/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091I1061825004467 $980.68
2019 3 FD52 08 E122 D 9011101D 069 9/10/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091I1061825004467 $365.54
2019 3 FD52 08 E123 D 9011101D 069 9/10/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR091I1061825004467 $164.89
2019 3 FD52 08 E123 D 9011101D 069 9/10/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091I1061825004467 $54.51
2019 2 FD52 08 E124 D 9011101D 069 8/27/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082I1061823503296 $0.07
2019 2 FD52 08 E111 D 9011101D 069 8/27/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082I1061823503295 $1,699.58
2019 2 FD52 08 E111 D 9011101D 069 8/27/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082I1061823503295 $155.39
2019 2 FD52 08 E121 D 9011101D 069 8/27/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082I1061823503295 $127.67
2019 2 FD52 08 E121 D 9011101D 069 8/27/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082I1061823503295 $11.63
2019 2 FD52 08 E122 D 9011101D 069 8/27/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082I1061823503295 $1,417.90
2019 2 FD52 08 E122 D 9011101D 069 8/27/2018 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082I1061823503295 $129.63
2019 2 FD52 08 E123 D 9011101D 069 8/27/2018 1050 RDWAY PLANS-FINAL-PLANS & PROF CA-XR082I1061823503295 $260.06