The Commonwealth pays employees on a semi-monthly basis with a scheduled pay day on the 15th and 30th of each month. The two monthly pay periods are from the 1st to the 15th of the month and the 16th through the last day of the month. Pay check distribution is delayed by one pay period to allow for system processing. For example work performed during the 1st to the 15th day of the month is paid to the employee on the 30th of the month. Accordingly the cost accounting charges for labor costs posting in eMARS to operating accounts and highway projects are also delayed by approximately one pay period.
A good rule of measure is that the cost accounting charges for the pay period ending on the 15th of the month will post to eMARS by the 25th and those for the pay period ending on the last day of the month will post to eMARS by the 10th of the following month.

x close panel
Detailed Project Expenditure Report
Total E-MARS Expenditures for 8768801C = $14,075,292.88
Click here for Labor Costs Information
Year Month PBU Charge District Object Phase Program Code County Date ACT Activity Name Trans ID Reference # Vendor Name Expenditure Line Description
2024 11 FD52 00 E111 C 8768801C 009 5/14/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR051O1062412903876 $488.19 000001084244-3562500610
2024 11 FD52 00 E111 C 8768801C 009 5/14/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903876 $34.87 000001084244-3562500610
2024 11 FD52 00 E121 C 8768801C 009 5/14/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR051O1062412903876 $34.07 000001084244-3562500610
2024 11 FD52 00 E121 C 8768801C 009 5/14/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903876 $2.43 000001084244-3562500610
2024 11 FD52 00 E122 C 8768801C 009 5/14/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR051O1062412903876 $323.02 000001084244-3562500610
2024 11 FD52 00 E122 C 8768801C 009 5/14/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903876 $23.07 000001084244-3562500610
2024 11 FD52 00 E123 C 8768801C 009 5/14/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR051O1062412903876 $96.99 000001084244-3562500610
2024 11 FD52 00 E123 C 8768801C 009 5/14/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903876 $6.86 000001084244-3562500610
2024 11 FD52 07 E229 C 8768801C 009 5/13/2024 4010 CONSTRUCTION ENGINEERING IET-XE13A162524131004830 $46.40
2024 11 FD52 07 E229 C 8768801C 009 5/13/2024 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162524131018350 $25.42
2024 11 FD52 07 E111 C 8768801C 009 5/9/2024 4580 CONSTRUCTION CONTRACTS CA-XR051O1062412903933 $6,686.42 10970024-3562507380
2024 11 FD52 07 E111 C 8768801C 009 5/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903933 $477.33 10970024-3562507380
2024 11 FD52 07 E115 C 8768801C 009 5/9/2024 4580 CONSTRUCTION CONTRACTS CA-XR051O1062412903933 $480.53 10970024-3562507380
2024 11 FD52 07 E116 C 8768801C 009 5/9/2024 4580 CONSTRUCTION CONTRACTS CA-XR051O1062412903933 $3.00 10970024-3562507380
2024 11 FD52 07 E121 C 8768801C 009 5/9/2024 4580 CONSTRUCTION CONTRACTS CA-XR051O1062412903933 $532.84 10970024-3562507380
2024 11 FD52 07 E121 C 8768801C 009 5/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903933 $35.29 10970024-3562507380
2024 11 FD52 07 E122 C 8768801C 009 5/9/2024 4580 CONSTRUCTION CONTRACTS CA-XR051O1062412903933 $4,744.35 10970024-3562507380
2024 11 FD52 07 E122 C 8768801C 009 5/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903933 $315.85 10970024-3562507380
2024 11 FD52 07 E123 C 8768801C 009 5/9/2024 4580 CONSTRUCTION CONTRACTS CA-XR051O1062412903933 $949.27 10970024-3562507380
2024 11 FD52 07 E123 C 8768801C 009 5/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903933 $59.51 10970024-3562507380
2024 11 FD52 07 E111 C 8768801C 009 5/9/2024 4010 CONSTRUCTION ENGINEERING CA-XR051O1062412903870 $47.86 000001081053-3562500680
2024 11 FD52 07 E111 C 8768801C 009 5/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903870 $4.31 000001081053-3562500680
2024 11 FD52 07 E121 C 8768801C 009 5/9/2024 4010 CONSTRUCTION ENGINEERING CA-XR051O1062412903870 $3.66 000001081053-3562500680
2024 11 FD52 07 E121 C 8768801C 009 5/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903870 $0.33 000001081053-3562500680
2024 11 FD52 07 E122 C 8768801C 009 5/9/2024 4010 CONSTRUCTION ENGINEERING CA-XR051O1062412903870 $31.65 000001081053-3562500680
2024 11 FD52 07 E122 C 8768801C 009 5/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903870 $2.85 000001081053-3562500680
2024 11 FD52 07 E123 C 8768801C 009 5/9/2024 4010 CONSTRUCTION ENGINEERING CA-XR051O1062412903870 $1.13 000001081053-3562500680
2024 11 FD52 07 E123 C 8768801C 009 5/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051O1062412903870 $0.10 000001081053-3562500680
2024 11 FD52 07 E111 C 8768801C 009 5/9/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR051O1062412903873 $249.07 000001082265-3562507210
2024 11 FD52 07 E121 C 8768801C 009 5/9/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR051O1062412903873 $18.36 000001082265-3562507210
2024 11 FD52 07 E122 C 8768801C 009 5/9/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR051O1062412903873 $164.81 000001082265-3562507210
2024 11 FD52 07 E123 C 8768801C 009 5/9/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR051O1062412903873 $39.55 000001082265-3562507210
2024 11 FD52 07 E797 C 8768801C 009 5/8/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P058K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $149,949.00
2024 10 FD52 07 E111 C 8768801C 009 4/30/2024 4010 CONSTRUCTION ENGINEERING CA-XR042O1062411502733 $544.06 000001081053-3562500680
2024 10 FD52 07 E111 C 8768801C 009 4/30/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502733 $52.87 000001081053-3562500680
2024 10 FD52 07 E121 C 8768801C 009 4/30/2024 4010 CONSTRUCTION ENGINEERING CA-XR042O1062411502733 $41.50 000001081053-3562500680
2024 10 FD52 07 E121 C 8768801C 009 4/30/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502733 $4.01 000001081053-3562500680
2024 10 FD52 07 E122 C 8768801C 009 4/30/2024 4010 CONSTRUCTION ENGINEERING CA-XR042O1062411502733 $360.01 000001081053-3562500680
2024 10 FD52 07 E122 C 8768801C 009 4/30/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502733 $34.98 000001081053-3562500680
2024 10 FD52 07 E123 C 8768801C 009 4/30/2024 4010 CONSTRUCTION ENGINEERING CA-XR042O1062411502733 $35.11 000001081053-3562500680
2024 10 FD52 07 E123 C 8768801C 009 4/30/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502733 $7.12 000001081053-3562500680
2024 10 FD52 07 E124 C 8768801C 009 4/30/2024 4010 CONSTRUCTION ENGINEERING CA-XR042O1062411502733 $0.15 000001081053-3562500680
2024 10 FD52 07 E124 C 8768801C 009 4/30/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502733 $0.01 000001081053-3562500680
2024 10 FD52 00 E122 C 8768801C 009 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502741 $32.54 000001084244-3562500610
2024 10 FD52 00 E123 C 8768801C 009 4/26/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR042O1062411502741 $57.21 000001084244-3562500610
2024 10 FD52 00 E123 C 8768801C 009 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502741 $9.68 000001084244-3562500610
2024 10 FD52 00 E124 C 8768801C 009 4/26/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR042O1062411502741 $0.10 000001084244-3562500610
2024 10 FD52 00 E124 C 8768801C 009 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502741 $0.02 000001084244-3562500610
2024 10 FD52 00 E111 C 8768801C 009 4/26/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR042O1062411502741 $287.56 000001084244-3562500610
2024 10 FD52 00 E111 C 8768801C 009 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502741 $49.17 000001084244-3562500610
2024 10 FD52 00 E121 C 8768801C 009 4/26/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR042O1062411502741 $20.53 000001084244-3562500610
2024 10 FD52 00 E121 C 8768801C 009 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502741 $3.52 000001084244-3562500610
2024 10 FD52 07 E111 C 8768801C 009 4/26/2024 4580 CONSTRUCTION CONTRACTS CA-XR042O1062411502802 $6,184.08 10970024-3562507380
2024 10 FD52 07 E111 C 8768801C 009 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502802 $2,015.86 10970024-3562507380
2024 10 FD52 07 E116 C 8768801C 009 4/26/2024 4580 CONSTRUCTION CONTRACTS CA-XR042O1062411502802 $1.50 10970024-3562507380
2024 10 FD52 07 E121 C 8768801C 009 4/26/2024 4580 CONSTRUCTION CONTRACTS CA-XR042O1062411502802 $464.02 10970024-3562507380
2024 10 FD52 00 E122 C 8768801C 009 4/26/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR042O1062411502741 $190.36 000001084244-3562500610
2024 10 FD52 07 E121 C 8768801C 009 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502802 $151.27 10970024-3562507380
2024 10 FD52 07 E122 C 8768801C 009 4/26/2024 4580 CONSTRUCTION CONTRACTS CA-XR042O1062411502802 $4,092.98 10970024-3562507380
2024 10 FD52 07 E122 C 8768801C 009 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502802 $1,333.91 10970024-3562507380
2024 10 FD52 07 E123 C 8768801C 009 4/26/2024 4580 CONSTRUCTION CONTRACTS CA-XR042O1062411502802 $800.35 10970024-3562507380
2024 10 FD52 07 E123 C 8768801C 009 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502802 $244.36 10970024-3562507380
2024 10 FD52 07 E124 C 8768801C 009 4/26/2024 4580 CONSTRUCTION CONTRACTS CA-XR042O1062411502802 $1.91 10970024-3562507380
2024 10 FD52 07 E124 C 8768801C 009 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502802 $0.66 10970024-3562507380
2024 10 FD52 07 E797 C 8768801C 009 4/25/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P057K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $79,618.71
2024 10 FD52 07 E229 C 8768801C 009 4/17/2024 4010 CONSTRUCTION ENGINEERING IET-XE13A162524101005720 $32.30
2024 10 FD52 07 E111 C 8768801C 009 4/11/2024 4010 CONSTRUCTION ENGINEERING CA-XR041O1062410001620 $628.28 000001081053-3562500680
2024 10 FD52 07 E111 C 8768801C 009 4/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001620 $73.08 000001081053-3562500680
2024 10 FD52 07 E121 C 8768801C 009 4/11/2024 4010 CONSTRUCTION ENGINEERING CA-XR041O1062410001620 $47.68 000001081053-3562500680
2024 10 FD52 07 E121 C 8768801C 009 4/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001620 $5.53 000001081053-3562500680
2024 10 FD52 07 E122 C 8768801C 009 4/11/2024 4010 CONSTRUCTION ENGINEERING CA-XR041O1062410001620 $416.42 000001081053-3562500680
2024 10 FD52 07 E122 C 8768801C 009 4/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001620 $48.36 000001081053-3562500680
2024 10 FD52 07 E123 C 8768801C 009 4/11/2024 4010 CONSTRUCTION ENGINEERING CA-XR041O1062410001620 $51.78 000001081053-3562500680
2024 10 FD52 07 E123 C 8768801C 009 4/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001620 $8.07 000001081053-3562500680
2024 10 FD52 07 E797 C 8768801C 009 4/10/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P056K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $90,523.02
2024 10 FD52 00 E111 C 8768801C 009 4/10/2024 1620 BRIDGE DESIGN & PLANS CA-XR041O1062410001666 $1,748.06 000001091276-3562500610
2024 10 FD52 00 E111 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001666 $97.41 000001091276-3562500610
2024 10 FD52 00 E121 C 8768801C 009 4/10/2024 1620 BRIDGE DESIGN & PLANS CA-XR041O1062410001666 $131.66 000001091276-3562500610
2024 10 FD52 00 E121 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001666 $7.33 000001091276-3562500610
2024 10 FD52 00 E122 C 8768801C 009 4/10/2024 1620 BRIDGE DESIGN & PLANS CA-XR041O1062410001666 $1,156.63 000001091276-3562500610
2024 10 FD52 00 E122 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001666 $64.46 000001091276-3562500610
2024 10 FD52 00 E123 C 8768801C 009 4/10/2024 1620 BRIDGE DESIGN & PLANS CA-XR041O1062410001666 $233.86 000001091276-3562500610
2024 10 FD52 00 E123 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001666 $13.04 000001091276-3562500610
2024 10 FD52 00 E111 C 8768801C 009 4/10/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR041O1062410001626 $1,150.82 000001084244-3562500610
2024 10 FD52 00 E111 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001626 $208.28 000001084244-3562500610
2024 10 FD52 00 E121 C 8768801C 009 4/10/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR041O1062410001626 $80.30 000001084244-3562500610
2024 10 FD52 00 E121 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001626 $14.54 000001084244-3562500610
2024 10 FD52 00 E122 C 8768801C 009 4/10/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR041O1062410001626 $761.43 000001084244-3562500610
2024 10 FD52 00 E122 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001626 $137.82 000001084244-3562500610
2024 10 FD52 00 E123 C 8768801C 009 4/10/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR041O1062410001626 $228.85 000001084244-3562500610
2024 10 FD52 00 E123 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001626 $40.99 000001084244-3562500610
2024 10 FD52 07 E111 C 8768801C 009 4/10/2024 4580 CONSTRUCTION CONTRACTS CA-XR041O1062410001681 $7,039.30 10970024-3562507380
2024 10 FD52 07 E111 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001681 $2,398.15 10970024-3562507380
2024 10 FD52 07 E115 C 8768801C 009 4/10/2024 4580 CONSTRUCTION CONTRACTS CA-XR041O1062410001681 $261.96 10970024-3562507380
2024 10 FD52 07 E116 C 8768801C 009 4/10/2024 4580 CONSTRUCTION CONTRACTS CA-XR041O1062410001681 $2.25 10970024-3562507380
2024 10 FD52 07 E121 C 8768801C 009 4/10/2024 4580 CONSTRUCTION CONTRACTS CA-XR041O1062410001681 $542.71 10970024-3562507380
2024 10 FD52 07 E121 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001681 $177.53 10970024-3562507380
2024 10 FD52 07 E122 C 8768801C 009 4/10/2024 4580 CONSTRUCTION CONTRACTS CA-XR041O1062410001681 $4,832.72 10970024-3562507380
2024 10 FD52 07 E122 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001681 $1,586.86 10970024-3562507380
2024 10 FD52 07 E123 C 8768801C 009 4/10/2024 4580 CONSTRUCTION CONTRACTS CA-XR041O1062410001681 $812.40 10970024-3562507380
2024 10 FD52 07 E123 C 8768801C 009 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001681 $373.86 10970024-3562507380
2024 9 FD52 07 E797 C 8768801C 009 3/27/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P055K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $54,480.45
2024 9 FD52 07 E122 C 8768801C 009 3/11/2024 4580 CONSTRUCTION CONTRACTS CA-XR031O1062406810120 $3,436.50 10970024-3562507380
2024 9 FD52 07 E122 C 8768801C 009 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810120 $866.06 10970024-3562507380
2024 9 FD52 00 E111 C 8768801C 009 3/11/2024 1620 BRIDGE DESIGN & PLANS CA-XR031O1062406810117 $1,380.87 000001091276-3562500610
2024 9 FD52 00 E121 C 8768801C 009 3/11/2024 1620 BRIDGE DESIGN & PLANS CA-XR031O1062406810117 $103.52 000001091276-3562500610
2024 9 FD52 00 E122 C 8768801C 009 3/11/2024 1620 BRIDGE DESIGN & PLANS CA-XR031O1062406810117 $913.72 000001091276-3562500610
2024 9 FD52 00 E123 C 8768801C 009 3/11/2024 1620 BRIDGE DESIGN & PLANS CA-XR031O1062406810117 $227.79 000001091276-3562500610
2024 9 FD52 07 E123 C 8768801C 009 3/11/2024 4580 CONSTRUCTION CONTRACTS CA-XR031O1062406810120 $834.74 10970024-3562507380
2024 9 FD52 07 E123 C 8768801C 009 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810120 $202.41 10970024-3562507380
2024 9 FD52 00 E111 C 8768801C 009 3/11/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR031O1062406810074 $1,100.56 000001084244-3562500610
2024 9 FD52 00 E111 C 8768801C 009 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810074 $187.05 000001084244-3562500610
2024 9 FD52 00 E121 C 8768801C 009 3/11/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR031O1062406810074 $79.43 000001084244-3562500610
2024 9 FD52 00 E121 C 8768801C 009 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810074 $13.08 000001084244-3562500610
2024 9 FD52 00 E122 C 8768801C 009 3/11/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR031O1062406810074 $728.38 000001084244-3562500610
2024 9 FD52 00 E122 C 8768801C 009 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810074 $123.77 000001084244-3562500610
2024 9 FD52 00 E123 C 8768801C 009 3/11/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR031O1062406810074 $171.69 000001084244-3562500610
2024 9 FD52 00 E123 C 8768801C 009 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810074 $36.30 000001084244-3562500610
2024 9 FD52 07 E111 C 8768801C 009 3/11/2024 4580 CONSTRUCTION CONTRACTS CA-XR031O1062406810119 $6,414.66 10970024-3562507380
2024 9 FD52 07 E111 C 8768801C 009 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810119 $1,448.86 10970024-3562507380
2024 9 FD52 07 E115 C 8768801C 009 3/11/2024 4580 CONSTRUCTION CONTRACTS CA-XR031O1062406810119 $136.67 10970024-3562507380
2024 9 FD52 07 E116 C 8768801C 009 3/11/2024 4580 CONSTRUCTION CONTRACTS CA-XR031O1062406810119 $2.25 10970024-3562507380
2024 9 FD52 07 E121 C 8768801C 009 3/11/2024 4580 CONSTRUCTION CONTRACTS CA-XR031O1062406810119 $490.85 10970024-3562507380
2024 9 FD52 07 E121 C 8768801C 009 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810119 $108.14 10970024-3562507380
2024 8 FD52 07 E797 C 8768801C 009 2/28/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P054K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $17,215.00
2024 8 FD52 07 E111 C 8768801C 009 2/26/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR022O1062405408893 $249.07 000001082265-3562507210
2024 8 FD52 07 E121 C 8768801C 009 2/26/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR022O1062405408893 $18.31 000001082265-3562507210
2024 8 FD52 07 E122 C 8768801C 009 2/26/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR022O1062405408893 $164.81 000001082265-3562507210
2024 8 FD52 07 E123 C 8768801C 009 2/26/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR022O1062405408893 $39.55 000001082265-3562507210
2024 8 FD52 07 E111 C 8768801C 009 2/26/2024 4580 CONSTRUCTION CONTRACTS CA-XR022O1062405408953 $6,722.73 10970024-3562507380
2024 8 FD52 07 E124 C 8768801C 009 2/26/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR022O1062405408893 $0.09 000001082265-3562507210
2024 8 FD52 07 E111 C 8768801C 009 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408953 $565.97 10970024-3562507380
2024 8 FD52 07 E121 C 8768801C 009 2/26/2024 4580 CONSTRUCTION CONTRACTS CA-XR022O1062405408953 $502.82 10970024-3562507380
2024 8 FD52 00 E111 C 8768801C 009 2/26/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR022O1062405408897 $313.83 000001084244-3562500610
2024 8 FD52 07 E121 C 8768801C 009 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408953 $42.64 10970024-3562507380
2024 8 FD52 00 E111 C 8768801C 009 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408897 $31.38 000001084244-3562500610
2024 8 FD52 07 E122 C 8768801C 009 2/26/2024 4580 CONSTRUCTION CONTRACTS CA-XR022O1062405408953 $4,448.43 10970024-3562507380
2024 8 FD52 00 E121 C 8768801C 009 2/26/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR022O1062405408897 $22.40 000001084244-3562500610
2024 8 FD52 07 E122 C 8768801C 009 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408953 $374.50 10970024-3562507380
2024 8 FD52 00 E121 C 8768801C 009 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408897 $2.23 000001084244-3562500610
2024 8 FD52 07 E123 C 8768801C 009 2/26/2024 4580 CONSTRUCTION CONTRACTS CA-XR022O1062405408953 $949.55 10970024-3562507380
2024 8 FD52 00 E122 C 8768801C 009 2/26/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR022O1062405408897 $207.66 000001084244-3562500610
2024 8 FD52 07 E123 C 8768801C 009 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408953 $63.59 10970024-3562507380
2024 8 FD52 00 E122 C 8768801C 009 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408897 $20.76 000001084244-3562500610
2024 8 FD52 07 E124 C 8768801C 009 2/26/2024 4580 CONSTRUCTION CONTRACTS CA-XR022O1062405408953 $2.06 10970024-3562507380
2024 8 FD52 00 E123 C 8768801C 009 2/26/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR022O1062405408897 $62.37 000001084244-3562500610
2024 8 FD52 07 E124 C 8768801C 009 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408953 $0.17 10970024-3562507380
2024 8 FD52 00 E123 C 8768801C 009 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408897 $6.18 000001084244-3562500610
2024 8 FD52 00 E124 C 8768801C 009 2/26/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR022O1062405408897 $0.11 000001084244-3562500610
2024 8 FD52 00 E124 C 8768801C 009 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408897 $0.01 000001084244-3562500610
2024 8 FD52 07 E797 C 8768801C 009 2/14/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P053K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $7,751.00
2024 8 FD52 07 E111 C 8768801C 009 2/9/2024 4580 CONSTRUCTION CONTRACTS CA-XR021O1062403907716 $5,404.48 10970024-3562507380
2024 8 FD52 07 E111 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907716 $172.65 10970024-3562507380
2024 8 FD52 07 E121 C 8768801C 009 2/9/2024 4580 CONSTRUCTION CONTRACTS CA-XR021O1062403907716 $400.94 10970024-3562507380
2024 8 FD52 07 E121 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907716 $12.92 10970024-3562507380
2024 8 FD52 07 E122 C 8768801C 009 2/9/2024 4580 CONSTRUCTION CONTRACTS CA-XR021O1062403907716 $3,576.15 10970024-3562507380
2024 8 FD52 07 E122 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907716 $114.24 10970024-3562507380
2024 8 FD52 07 E123 C 8768801C 009 2/9/2024 4580 CONSTRUCTION CONTRACTS CA-XR021O1062403907716 $772.03 10970024-3562507380
2024 8 FD52 07 E123 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907716 $19.63 10970024-3562507380
2024 8 FD52 07 E124 C 8768801C 009 2/9/2024 4580 CONSTRUCTION CONTRACTS CA-XR021O1062403907716 $0.01 10970024-3562507380
2024 8 FD52 07 E124 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907716 $0.01 10970024-3562507380
2024 8 FD52 07 E111 C 8768801C 009 2/9/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR021O1062403907661 $684.96 000001082265-3562507210
2024 8 FD52 07 E111 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907661 $153.73 000001082265-3562507210
2024 8 FD52 07 E121 C 8768801C 009 2/9/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR021O1062403907661 $50.36 000001082265-3562507210
2024 8 FD52 07 E121 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907661 $11.30 000001082265-3562507210
2024 8 FD52 07 E122 C 8768801C 009 2/9/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR021O1062403907661 $453.23 000001082265-3562507210
2024 8 FD52 07 E122 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907661 $101.72 000001082265-3562507210
2024 8 FD52 07 E123 C 8768801C 009 2/9/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR021O1062403907661 $109.05 000001082265-3562507210
2024 8 FD52 07 E123 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907661 $24.12 000001082265-3562507210
2024 8 FD52 00 E111 C 8768801C 009 2/9/2024 1620 BRIDGE DESIGN & PLANS CA-XR021O1062403907714 $1,285.22 000001091001-3562500610
2024 8 FD52 00 E111 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907714 $257.04 000001091001-3562500610
2024 8 FD52 00 E121 C 8768801C 009 2/9/2024 1620 BRIDGE DESIGN & PLANS CA-XR021O1062403907714 $96.34 000001091001-3562500610
2024 8 FD52 00 E121 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907714 $19.28 000001091001-3562500610
2024 8 FD52 00 E122 C 8768801C 009 2/9/2024 1620 BRIDGE DESIGN & PLANS CA-XR021O1062403907714 $850.43 000001091001-3562500610
2024 8 FD52 00 E122 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907714 $170.08 000001091001-3562500610
2024 8 FD52 00 E123 C 8768801C 009 2/9/2024 1620 BRIDGE DESIGN & PLANS CA-XR021O1062403907714 $212.50 000001091001-3562500610
2024 8 FD52 00 E123 C 8768801C 009 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907714 $41.92 000001091001-3562500610
2024 7 FD52 07 E797 C 8768801C 009 1/31/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P052K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $19,898.21
2024 7 FD52 07 E229 C 8768801C 009 1/29/2024 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162524025013560 $13.02
2024 7 FD52 07 E121 C 8768801C 009 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306583 $38.14 000001082265-3562507210
2024 7 FD52 07 E122 C 8768801C 009 1/24/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR012O1062402306583 $723.99 000001082265-3562507210
2024 7 FD52 07 E122 C 8768801C 009 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306583 $368.76 000001082265-3562507210
2024 7 FD52 07 E123 C 8768801C 009 1/24/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR012O1062402306583 $275.47 000001082265-3562507210
2024 7 FD52 07 E123 C 8768801C 009 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306583 $139.82 000001082265-3562507210
2024 7 FD52 07 E124 C 8768801C 009 1/24/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR012O1062402306583 $0.45 000001082265-3562507210
2024 7 FD52 07 E124 C 8768801C 009 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306583 $0.23 000001082265-3562507210
2024 7 FD52 07 E111 C 8768801C 009 1/24/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR012O1062402306583 $1,093.97 000001082265-3562507210
2024 7 FD52 07 E111 C 8768801C 009 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306583 $557.29 000001082265-3562507210
2024 7 FD52 07 E111 C 8768801C 009 1/24/2024 4580 CONSTRUCTION CONTRACTS CA-XR012O1062402306651 $5,719.69 10970024-3562507380
2024 7 FD52 07 E111 C 8768801C 009 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306651 $3,630.85 10970024-3562507380
2024 7 FD52 07 E116 C 8768801C 009 1/24/2024 4580 CONSTRUCTION CONTRACTS CA-XR012O1062402306651 $6.00 10970024-3562507380
2024 7 FD52 07 E121 C 8768801C 009 1/24/2024 4580 CONSTRUCTION CONTRACTS CA-XR012O1062402306651 $429.61 10970024-3562507380
2024 7 FD52 07 E121 C 8768801C 009 1/24/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR012O1062402306583 $75.08 000001082265-3562507210
2024 7 FD52 07 E121 C 8768801C 009 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306651 $274.01 10970024-3562507380
2024 7 FD52 07 E122 C 8768801C 009 1/24/2024 4580 CONSTRUCTION CONTRACTS CA-XR012O1062402306651 $3,788.68 10970024-3562507380
2024 7 FD52 07 E122 C 8768801C 009 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306651 $2,402.53 10970024-3562507380
2024 7 FD52 07 E123 C 8768801C 009 1/24/2024 4580 CONSTRUCTION CONTRACTS CA-XR012O1062402306651 $716.83 10970024-3562507380
2024 7 FD52 07 E123 C 8768801C 009 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306651 $365.25 10970024-3562507380
2024 7 FD52 07 E124 C 8768801C 009 1/24/2024 4580 CONSTRUCTION CONTRACTS CA-XR012O1062402306651 $1.84 10970024-3562507380
2024 7 FD52 07 E124 C 8768801C 009 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306651 $1.13 10970024-3562507380
2024 7 FD52 07 E797 C 8768801C 009 1/18/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P051K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $86,027.84
2024 7 FD52 00 E229 C 8768801C 009 1/11/2024 5341 GEOTECHNICAL INVEST (CONST) IET-XE13A162524010014150 $880.00
2024 7 FD52 07 E111 C 8768801C 009 1/11/2024 4580 CONSTRUCTION CONTRACTS CA-XR011O1062400505754 $4,127.03 10970024-3562507380
2024 7 FD52 07 E111 C 8768801C 009 1/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505754 $4,980.53 10970024-3562507380
2024 7 FD52 07 E115 C 8768801C 009 1/11/2024 4580 CONSTRUCTION CONTRACTS CA-XR011O1062400505754 $356.76 10970024-3562507380
2024 7 FD52 07 E121 C 8768801C 009 1/11/2024 4580 CONSTRUCTION CONTRACTS CA-XR011O1062400505754 $333.92 10970024-3562507380
2024 7 FD52 07 E121 C 8768801C 009 1/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505754 $370.60 10970024-3562507380
2024 7 FD52 07 E122 C 8768801C 009 1/8/2024 4580 CONSTRUCTION CONTRACTS CA-XR011O1062400505755 $2,966.92 10970024-3562507380
2024 7 FD52 07 E122 C 8768801C 009 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505755 $3,295.62 10970024-3562507380
2024 7 FD52 07 E123 C 8768801C 009 1/8/2024 4580 CONSTRUCTION CONTRACTS CA-XR011O1062400505755 $518.34 10970024-3562507380
2024 7 FD52 07 E123 C 8768801C 009 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505755 $566.28 10970024-3562507380
2024 7 FD52 07 E124 C 8768801C 009 1/8/2024 4580 CONSTRUCTION CONTRACTS CA-XR011O1062400505755 $0.01 10970024-3562507380
2024 7 FD52 07 E111 C 8768801C 009 1/8/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR011O1062400505717 $572.48 000001082265-3562507210
2024 7 FD52 07 E111 C 8768801C 009 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505717 $245.24 000001082265-3562507210
2024 7 FD52 07 E121 C 8768801C 009 1/8/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR011O1062400505717 $39.31 000001082265-3562507210
2024 7 FD52 07 E121 C 8768801C 009 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505717 $16.84 000001082265-3562507210
2024 7 FD52 07 E122 C 8768801C 009 1/8/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR011O1062400505717 $378.92 000001082265-3562507210
2024 7 FD52 07 E122 C 8768801C 009 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505717 $162.28 000001082265-3562507210
2024 7 FD52 07 E123 C 8768801C 009 1/8/2024 5182 INSP-MISCELLANEOUS MATERIALS CA-XR011O1062400505717 $133.83 000001082265-3562507210
2024 7 FD52 07 E123 C 8768801C 009 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505717 $56.38 000001082265-3562507210
2024 7 FD52 00 E111 C 8768801C 009 1/8/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR011O1062400505720 $346.20 000001084244-3562500610
2024 7 FD52 00 E111 C 8768801C 009 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505720 $2,423.40 000001084244-3562500610
2024 7 FD52 00 E121 C 8768801C 009 1/8/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR011O1062400505720 $25.80 000001084244-3562500610
2024 7 FD52 00 E121 C 8768801C 009 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505720 $179.27 000001084244-3562500610
2024 7 FD52 00 E122 C 8768801C 009 1/8/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR011O1062400505720 $229.08 000001084244-3562500610
2024 7 FD52 00 E122 C 8768801C 009 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505720 $1,603.56 000001084244-3562500610
2024 7 FD52 00 E123 C 8768801C 009 1/8/2024 5341 GEOTECHNICAL INVEST (CONST) CA-XR011O1062400505720 $56.34 000001084244-3562500610
2024 7 FD52 00 E123 C 8768801C 009 1/8/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505720 $358.71 000001084244-3562500610
2024 7 FD52 07 E797 C 8768801C 009 1/4/2024 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P050K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $464,804.46
2024 7 FD52 07 E111 C 8768801C 009 1/3/2024 4580 CONSTRUCTION CONTRACTS CA-XR121N1062334203665 $5,287.45 10970024-3562507380
2024 7 FD52 07 E111 C 8768801C 009 1/3/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203665 $2,239.94 10970024-3562507380
2024 7 FD52 07 E115 C 8768801C 009 1/3/2024 4580 CONSTRUCTION CONTRACTS CA-XR121N1062334203665 $910.47 10970024-3562507380
2024 7 FD52 07 E121 C 8768801C 009 1/3/2024 4580 CONSTRUCTION CONTRACTS CA-XR121N1062334203665 $452.38 10970024-3562507380
2024 7 FD52 07 E121 C 8768801C 009 1/3/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203665 $161.63 10970024-3562507380
2024 7 FD52 07 E122 C 8768801C 009 1/3/2024 4580 CONSTRUCTION CONTRACTS CA-XR121N1062334203665 $4,101.17 10970024-3562507380
2024 7 FD52 07 E122 C 8768801C 009 1/3/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203665 $1,482.16 10970024-3562507380
2024 7 FD52 07 E123 C 8768801C 009 1/3/2024 4580 CONSTRUCTION CONTRACTS CA-XR121N1062334203665 $933.34 10970024-3562507380
2024 7 FD52 07 E123 C 8768801C 009 1/3/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203665 $423.21 10970024-3562507380
2024 6 FD52 00 E229 C 8768801C 009 12/27/2023 5341 GEOTECHNICAL INVEST (CONST) IET-XE13A162523359013720 $880.00
2024 6 FD52 07 E123 C 8768801C 009 12/22/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR122N1062335504606 $90.56 000001082265-3562507210
2024 6 FD52 07 E115 C 8768801C 009 12/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR122N1062335504674 $404.75 10970024-3562507380
2024 6 FD52 07 E123 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504606 $42.29 000001082265-3562507210
2024 6 FD52 07 E116 C 8768801C 009 12/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR122N1062335504674 $4.50 10970024-3562507380
2024 6 FD52 07 E124 C 8768801C 009 12/22/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR122N1062335504606 $0.20 000001082265-3562507210
2024 6 FD52 07 E121 C 8768801C 009 12/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR122N1062335504674 $343.90 10970024-3562507380
2024 6 FD52 07 E124 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504606 $0.07 000001082265-3562507210
2024 6 FD52 07 E121 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504674 $33.48 10970024-3562507380
2024 6 FD52 07 E122 C 8768801C 009 12/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR122N1062335504674 $3,048.40 10970024-3562507380
2024 6 FD52 07 E122 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504674 $297.77 10970024-3562507380
2024 6 FD52 07 E123 C 8768801C 009 12/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR122N1062335504674 $506.19 10970024-3562507380
2024 6 FD52 07 E123 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504674 $57.45 10970024-3562507380
2024 6 FD52 07 E124 C 8768801C 009 12/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR122N1062335504674 $1.54 10970024-3562507380
2024 6 FD52 00 E111 C 8768801C 009 12/22/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR122N1062335504612 $5,211.86 000001084244-3562500610
2024 6 FD52 07 E124 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504674 $0.16 10970024-3562507380
2024 6 FD52 00 E111 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504612 $1,925.52 000001084244-3562500610
2024 6 FD52 00 E115 C 8768801C 009 12/22/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR122N1062335504612 $845.43 000001084244-3562500610
2024 6 FD52 00 E121 C 8768801C 009 12/22/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR122N1062335504612 $456.68 000001084244-3562500610
2024 6 FD52 00 E121 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504612 $144.92 000001084244-3562500610
2024 6 FD52 00 E122 C 8768801C 009 12/22/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR122N1062335504612 $4,008.16 000001084244-3562500610
2024 6 FD52 00 E122 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504612 $1,274.12 000001084244-3562500610
2024 6 FD52 00 E123 C 8768801C 009 12/22/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR122N1062335504612 $472.71 000001084244-3562500610
2024 6 FD52 00 E123 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504612 $193.43 000001084244-3562500610
2024 6 FD52 00 E124 C 8768801C 009 12/22/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR122N1062335504612 $1.39 000001084244-3562500610
2024 6 FD52 00 E124 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504612 $0.58 000001084244-3562500610
2024 6 FD52 07 E111 C 8768801C 009 12/22/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR122N1062335504606 $498.04 000001082265-3562507210
2024 6 FD52 07 E111 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504606 $199.59 000001082265-3562507210
2024 6 FD52 07 E111 C 8768801C 009 12/22/2023 4010 CONSTRUCTION ENGINEERING CA-XR122N1062335504602 $95.70 000001081053-3562500680
2024 6 FD52 07 E111 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504602 $9.57 000001081053-3562500680
2024 6 FD52 07 E121 C 8768801C 009 12/22/2023 4010 CONSTRUCTION ENGINEERING CA-XR122N1062335504602 $7.32 000001081053-3562500680
2024 6 FD52 07 E121 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504602 $0.73 000001081053-3562500680
2024 6 FD52 07 E122 C 8768801C 009 12/22/2023 4010 CONSTRUCTION ENGINEERING CA-XR122N1062335504602 $63.31 000001081053-3562500680
2024 6 FD52 07 E122 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504602 $6.33 000001081053-3562500680
2024 6 FD52 07 E123 C 8768801C 009 12/22/2023 4010 CONSTRUCTION ENGINEERING CA-XR122N1062335504602 $0.14 000001081053-3562500680
2024 6 FD52 07 E121 C 8768801C 009 12/22/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR122N1062335504606 $35.20 000001082265-3562507210
2024 6 FD52 07 E124 C 8768801C 009 12/22/2023 4010 CONSTRUCTION ENGINEERING CA-XR122N1062335504602 $0.02 000001081053-3562500680
2024 6 FD52 07 E121 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504606 $13.68 000001082265-3562507210
2024 6 FD52 07 E122 C 8768801C 009 12/22/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR122N1062335504606 $329.42 000001082265-3562507210
2024 6 FD52 07 E111 C 8768801C 009 12/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR122N1062335504674 $4,197.67 10970024-3562507380
2024 6 FD52 07 E122 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504606 $132.06 000001082265-3562507210
2024 6 FD52 07 E111 C 8768801C 009 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504674 $450.00 10970024-3562507380
2024 6 FD52 07 E797 C 8768801C 009 12/20/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P049K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $158,626.58
2024 6 FD52 07 E154 C 8768801C 009 12/18/2023 4010 CONSTRUCTION ENGINEERING ITA-5202400000066 $4,762.43
2024 6 FD52 07 E111 C 8768801C 009 12/14/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR121N1062334203617 $981.83 000001082265-3562507210
2024 6 FD52 07 E111 C 8768801C 009 12/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203617 $512.59 000001082265-3562507210
2024 6 FD52 07 E121 C 8768801C 009 12/14/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR121N1062334203617 $72.91 000001082265-3562507210
2024 6 FD52 07 E121 C 8768801C 009 12/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203617 $37.86 000001082265-3562507210
2024 6 FD52 07 E122 C 8768801C 009 12/14/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR121N1062334203617 $649.82 000001082265-3562507210
2024 6 FD52 07 E122 C 8768801C 009 12/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203617 $339.19 000001082265-3562507210
2024 6 FD52 07 E123 C 8768801C 009 12/14/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR121N1062334203617 $120.52 000001082265-3562507210
2024 6 FD52 07 E123 C 8768801C 009 12/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203617 $66.21 000001082265-3562507210
2024 6 FD52 07 E229 C 8768801C 009 12/13/2023 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162523344015320 $29.45
2024 6 FD52 00 E111 C 8768801C 009 12/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR121N1062334203622 $3,889.75 000001084244-3562500610
2024 6 FD52 00 E111 C 8768801C 009 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203622 $2,211.85 000001084244-3562500610
2024 6 FD52 00 E121 C 8768801C 009 12/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR121N1062334203622 $290.70 000001084244-3562500610
2024 6 FD52 00 E121 C 8768801C 009 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203622 $162.92 000001084244-3562500610
2024 6 FD52 00 E122 C 8768801C 009 12/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR121N1062334203622 $2,573.86 000001084244-3562500610
2024 6 FD52 00 E122 C 8768801C 009 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203622 $1,463.58 000001084244-3562500610
2024 6 FD52 00 E123 C 8768801C 009 12/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR121N1062334203622 $340.70 000001084244-3562500610
2024 6 FD52 00 E123 C 8768801C 009 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203622 $299.26 000001084244-3562500610
2024 6 FD52 00 E361 C 8768801C 009 12/8/2023 5341 GEOTECHNICAL INVEST (CONST) TP-2400027329 $187.83
2024 6 FD52 07 E797 C 8768801C 009 12/6/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P048K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $263,259.83
2024 6 FD52 00 E361 C 8768801C 009 12/4/2023 5341 GEOTECHNICAL INVEST (CONST) TP-2400026781 $455.06
2024 5 FD52 07 E797 C 8768801C 009 11/22/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P047K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $589,668.39
2024 5 FD52 07 E111 C 8768801C 009 11/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR112N1062332502576 $7,006.53 10970024-3562507380
2024 5 FD52 07 E111 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502576 $1,597.45 10970024-3562507380
2024 5 FD52 07 E116 C 8768801C 009 11/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR112N1062332502576 $2.25 10970024-3562507380
2024 5 FD52 07 E121 C 8768801C 009 11/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR112N1062332502576 $514.75 10970024-3562507380
2024 5 FD52 07 E121 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502576 $116.98 10970024-3562507380
2024 5 FD52 07 E122 C 8768801C 009 11/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR112N1062332502576 $4,637.70 10970024-3562507380
2024 5 FD52 07 E122 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502576 $1,057.03 10970024-3562507380
2024 5 FD52 07 E123 C 8768801C 009 11/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR112N1062332502576 $1,065.06 10970024-3562507380
2024 5 FD52 07 E123 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502576 $239.56 10970024-3562507380
2024 5 FD52 07 E124 C 8768801C 009 11/22/2023 4580 CONSTRUCTION CONTRACTS CA-XR112N1062332502576 $2.35 10970024-3562507380
2024 5 FD52 07 E124 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502576 $0.56 10970024-3562507380
2024 5 FD52 07 E111 C 8768801C 009 11/22/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR112N1062332502510 $863.03 000001082265-3562507210
2024 5 FD52 07 E111 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502510 $457.96 000001082265-3562507210
2024 5 FD52 07 E121 C 8768801C 009 11/22/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR112N1062332502510 $63.10 000001082265-3562507210
2024 5 FD52 07 E121 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502510 $33.57 000001082265-3562507210
2024 5 FD52 07 E122 C 8768801C 009 11/22/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR112N1062332502510 $571.23 000001082265-3562507210
2024 5 FD52 07 E122 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502510 $303.04 000001082265-3562507210
2024 5 FD52 07 E123 C 8768801C 009 11/22/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR112N1062332502510 $127.16 000001082265-3562507210
2024 5 FD52 07 E123 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502510 $64.19 000001082265-3562507210
2024 5 FD52 07 E124 C 8768801C 009 11/22/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR112N1062332502510 $0.35 000001082265-3562507210
2024 5 FD52 07 E124 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502510 $0.17 000001082265-3562507210
2024 5 FD52 07 E111 C 8768801C 009 11/22/2023 4010 CONSTRUCTION ENGINEERING CA-XR112N1062332502506 $167.42 000001081053-3562500680
2024 5 FD52 07 E111 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502506 $53.57 000001081053-3562500680
2024 5 FD52 07 E121 C 8768801C 009 11/22/2023 4010 CONSTRUCTION ENGINEERING CA-XR112N1062332502506 $12.81 000001081053-3562500680
2024 5 FD52 07 E121 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502506 $4.09 000001081053-3562500680
2024 5 FD52 07 E122 C 8768801C 009 11/22/2023 4010 CONSTRUCTION ENGINEERING CA-XR112N1062332502506 $110.78 000001081053-3562500680
2024 5 FD52 07 E122 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502506 $35.44 000001081053-3562500680
2024 5 FD52 07 E123 C 8768801C 009 11/22/2023 4010 CONSTRUCTION ENGINEERING CA-XR112N1062332502506 $0.29 000001081053-3562500680
2024 5 FD52 07 E124 C 8768801C 009 11/22/2023 4010 CONSTRUCTION ENGINEERING CA-XR112N1062332502506 $0.04 000001081053-3562500680
2024 5 FD52 07 E124 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502506 $0.02 000001081053-3562500680
2024 5 FD52 00 E111 C 8768801C 009 11/22/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR112N1062332502516 $1,351.00 000001084244-3562500610
2024 5 FD52 00 E111 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502516 $219.19 000001084244-3562500610
2024 5 FD52 00 E121 C 8768801C 009 11/22/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR112N1062332502516 $102.60 000001084244-3562500610
2024 5 FD52 00 E121 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502516 $16.65 000001084244-3562500610
2024 5 FD52 00 E122 C 8768801C 009 11/22/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR112N1062332502516 $894.09 000001084244-3562500610
2024 5 FD52 00 E122 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502516 $145.04 000001084244-3562500610
2024 5 FD52 00 E123 C 8768801C 009 11/22/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR112N1062332502516 $105.20 000001084244-3562500610
2024 5 FD52 00 E123 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502516 $16.81 000001084244-3562500610
2024 5 FD52 00 E124 C 8768801C 009 11/22/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR112N1062332502516 $0.27 000001084244-3562500610
2024 5 FD52 00 E124 C 8768801C 009 11/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112N1062332502516 $0.05 000001084244-3562500610
2024 5 FD52 07 E111 C 8768801C 009 11/20/2023 4580 CONSTRUCTION CONTRACTS CA-XR111N1062331201531 $5,239.17 10970024-3562507380
2024 5 FD52 07 E111 C 8768801C 009 11/20/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201531 $1,344.98 10970024-3562507380
2024 5 FD52 07 E115 C 8768801C 009 11/20/2023 4580 CONSTRUCTION CONTRACTS CA-XR111N1062331201531 $556.40 10970024-3562507380
2024 5 FD52 07 E121 C 8768801C 009 11/20/2023 4580 CONSTRUCTION CONTRACTS CA-XR111N1062331201531 $425.31 10970024-3562507380
2024 5 FD52 07 E121 C 8768801C 009 11/20/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201531 $99.19 10970024-3562507380
2024 5 FD52 07 E122 C 8768801C 009 11/20/2023 4580 CONSTRUCTION CONTRACTS CA-XR111N1062331201531 $3,834.94 10970024-3562507380
2024 5 FD52 07 E122 C 8768801C 009 11/20/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201531 $889.97 10970024-3562507380
2024 5 FD52 07 E123 C 8768801C 009 11/20/2023 4580 CONSTRUCTION CONTRACTS CA-XR111N1062331201531 $845.05 10970024-3562507380
2024 5 FD52 07 E123 C 8768801C 009 11/20/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201531 $169.61 10970024-3562507380
2024 5 FD52 07 E111 C 8768801C 009 11/9/2023 4010 CONSTRUCTION ENGINEERING CA-XR111N1062331201473 $164.37 000001081053-3562500680
2024 5 FD52 07 E111 C 8768801C 009 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201473 $60.07 000001081053-3562500680
2024 5 FD52 07 E121 C 8768801C 009 11/9/2023 4010 CONSTRUCTION ENGINEERING CA-XR111N1062331201473 $12.57 000001081053-3562500680
2024 5 FD52 00 E111 C 8768801C 009 11/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR111N1062331201481 $877.29 000001084244-3562500610
2024 5 FD52 07 E121 C 8768801C 009 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201473 $4.59 000001081053-3562500680
2024 5 FD52 00 E111 C 8768801C 009 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201481 $20.40 000001084244-3562500610
2024 5 FD52 07 E122 C 8768801C 009 11/9/2023 4010 CONSTRUCTION ENGINEERING CA-XR111N1062331201473 $108.80 000001081053-3562500680
2024 5 FD52 00 E121 C 8768801C 009 11/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR111N1062331201481 $61.18 000001084244-3562500610
2024 5 FD52 07 E122 C 8768801C 009 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201473 $39.75 000001081053-3562500680
2024 5 FD52 00 E121 C 8768801C 009 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201481 $1.41 000001084244-3562500610
2024 5 FD52 07 E123 C 8768801C 009 11/9/2023 4010 CONSTRUCTION ENGINEERING CA-XR111N1062331201473 $0.29 000001081053-3562500680
2024 5 FD52 00 E122 C 8768801C 009 11/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR111N1062331201481 $580.55 000001084244-3562500610
2024 5 FD52 00 E122 C 8768801C 009 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201481 $13.50 000001084244-3562500610
2024 5 FD52 00 E123 C 8768801C 009 11/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR111N1062331201481 $156.27 000001084244-3562500610
2024 5 FD52 00 E123 C 8768801C 009 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201481 $3.65 000001084244-3562500610
2024 5 FD52 07 E797 C 8768801C 009 11/8/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P046K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $168,574.89
2024 4 FD52 07 E111 C 8768801C 009 10/30/2023 4580 CONSTRUCTION CONTRACTS CA-XR102N1062329600471 $5,023.85 10970024-3562507380
2024 4 FD52 07 E111 C 8768801C 009 10/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102N1062329600471 $961.71 10970024-3562507380
2024 4 FD52 07 E115 C 8768801C 009 10/30/2023 4580 CONSTRUCTION CONTRACTS CA-XR102N1062329600471 $25.29 10970024-3562507380
2024 4 FD52 07 E797 C 8768801C 009 10/25/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P045K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $37,770.71
2024 4 FD52 07 E154 C 8768801C 009 10/25/2023 4010 CONSTRUCTION ENGINEERING ITA-5202400000057 $5,841.58 July 2023 Work Zone Reimbursement Request
2024 4 FD52 07 E797 C 8768801C 009 10/11/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P044K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $115,461.56
2024 4 FD52 00 E111 C 8768801C 009 10/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR101N1062328009695 $347.04 000001084244-3562500610
2024 4 FD52 00 E111 C 8768801C 009 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009695 $168.41 000001084244-3562500610
2024 4 FD52 00 E121 C 8768801C 009 10/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR101N1062328009695 $24.16 000001084244-3562500610
2024 4 FD52 00 E121 C 8768801C 009 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009695 $11.72 000001084244-3562500610
2024 4 FD52 00 E122 C 8768801C 009 10/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR101N1062328009695 $229.64 000001084244-3562500610
2024 4 FD52 00 E122 C 8768801C 009 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009695 $111.44 000001084244-3562500610
2024 4 FD52 00 E123 C 8768801C 009 10/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR101N1062328009695 $63.04 000001084244-3562500610
2024 4 FD52 07 E111 C 8768801C 009 10/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR101N1062328009740 $6,198.54 10970024-3562507380
2024 4 FD52 00 E123 C 8768801C 009 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009695 $30.13 000001084244-3562500610
2024 4 FD52 07 E111 C 8768801C 009 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009740 $273.98 10970024-3562507380
2024 4 FD52 07 E115 C 8768801C 009 10/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR101N1062328009740 $518.47 10970024-3562507380
2024 4 FD52 07 E121 C 8768801C 009 10/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR101N1062328009740 $495.44 10970024-3562507380
2024 4 FD52 07 E121 C 8768801C 009 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009740 $20.72 10970024-3562507380
2024 4 FD52 07 E122 C 8768801C 009 10/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR101N1062328009740 $4,444.65 10970024-3562507380
2024 4 FD52 07 E122 C 8768801C 009 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009740 $181.29 10970024-3562507380
2024 4 FD52 07 E123 C 8768801C 009 10/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR101N1062328009740 $997.07 10970024-3562507380
2024 4 FD52 07 E123 C 8768801C 009 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009740 $42.50 10970024-3562507380
2024 4 FD52 00 E111 C 8768801C 009 10/2/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR092N1062327208415 $900.80 000001084244-3562500610
2024 4 FD52 00 E111 C 8768801C 009 10/2/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208415 $110.50 000001084244-3562500610
2024 4 FD52 00 E121 C 8768801C 009 10/2/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR092N1062327208415 $68.41 000001084244-3562500610
2024 3 FD52 00 E121 C 8768801C 009 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208416 $8.39 000001084244-3562500610
2024 3 FD52 07 E121 C 8768801C 009 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208470 $127.69 10970024-3562507380
2024 3 FD52 07 E122 C 8768801C 009 9/29/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062327208470 $2,853.34 10970024-3562507380
2024 3 FD52 07 E122 C 8768801C 009 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208470 $1,159.68 10970024-3562507380
2024 3 FD52 07 E123 C 8768801C 009 9/29/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062327208470 $835.65 10970024-3562507380
2024 3 FD52 07 E123 C 8768801C 009 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208470 $308.69 10970024-3562507380
2024 3 FD52 07 E124 C 8768801C 009 9/29/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062327208470 $1.47 10970024-3562507380
2024 3 FD52 07 E124 C 8768801C 009 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208470 $0.62 10970024-3562507380
2024 3 FD52 00 E122 C 8768801C 009 9/29/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR092N1062327208416 $596.06 000001084244-3562500610
2024 3 FD52 00 E122 C 8768801C 009 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208416 $73.12 000001084244-3562500610
2024 3 FD52 00 E123 C 8768801C 009 9/29/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR092N1062327208416 $70.09 000001084244-3562500610
2024 3 FD52 00 E123 C 8768801C 009 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208416 $8.47 000001084244-3562500610
2024 3 FD52 00 E124 C 8768801C 009 9/29/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR092N1062327208416 $0.18 000001084244-3562500610
2024 3 FD52 07 E111 C 8768801C 009 9/29/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062327208470 $4,236.26 10970024-3562507380
2024 3 FD52 00 E124 C 8768801C 009 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208416 $0.02 000001084244-3562500610
2024 3 FD52 07 E111 C 8768801C 009 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208470 $1,752.58 10970024-3562507380
2024 3 FD52 07 E115 C 8768801C 009 9/29/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062327208470 $75.87 10970024-3562507380
2024 3 FD52 07 E121 C 8768801C 009 9/29/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062327208470 $310.07 10970024-3562507380
2024 3 FD52 00 E121 C 8768801C 009 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507065 ($8.39) 000001084244-3562500610
2024 3 FD52 07 E121 C 8768801C 009 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507119 ($127.69) 10970024-3562507380
2024 3 FD52 07 E122 C 8768801C 009 9/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 ($2,853.34) 10970024-3562507380
2024 3 FD52 07 E122 C 8768801C 009 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507119 ($1,159.68) 10970024-3562507380
2024 3 FD52 07 E123 C 8768801C 009 9/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 ($835.65) 10970024-3562507380
2024 3 FD52 07 E123 C 8768801C 009 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507119 ($308.69) 10970024-3562507380
2024 3 FD52 07 E124 C 8768801C 009 9/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 ($1.47) 10970024-3562507380
2024 3 FD52 07 E124 C 8768801C 009 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507119 ($0.62) 10970024-3562507380
2024 3 FD52 00 E122 C 8768801C 009 9/28/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR092N1062326507065 ($596.06) 000001084244-3562500610
2024 3 FD52 00 E122 C 8768801C 009 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507065 ($73.12) 000001084244-3562500610
2024 3 FD52 00 E123 C 8768801C 009 9/28/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR092N1062326507065 ($70.09) 000001084244-3562500610
2024 3 FD52 00 E123 C 8768801C 009 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507065 ($8.47) 000001084244-3562500610
2024 3 FD52 00 E124 C 8768801C 009 9/28/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR092N1062326507065 ($0.18) 000001084244-3562500610
2024 3 FD52 07 E111 C 8768801C 009 9/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 ($4,236.26) 10970024-3562507380
2024 3 FD52 00 E124 C 8768801C 009 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507065 ($0.02) 000001084244-3562500610
2024 3 FD52 07 E111 C 8768801C 009 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507119 ($1,752.58) 10970024-3562507380
2024 3 FD52 07 E115 C 8768801C 009 9/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 ($75.87) 10970024-3562507380
2024 3 FD52 07 E121 C 8768801C 009 9/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 ($310.07) 10970024-3562507380
2024 3 FD52 07 E797 C 8768801C 009 9/27/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P043K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $173,997.59
2024 3 FD52 00 E121 C 8768801C 009 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507065 $8.39 000001084244-3562500610
2024 3 FD52 07 E121 C 8768801C 009 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507119 $127.69 10970024-3562507380
2024 3 FD52 07 E122 C 8768801C 009 9/25/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 $2,853.34 10970024-3562507380
2024 3 FD52 07 E122 C 8768801C 009 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507119 $1,159.68 10970024-3562507380
2024 3 FD52 07 E123 C 8768801C 009 9/25/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 $835.65 10970024-3562507380
2024 3 FD52 07 E123 C 8768801C 009 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507119 $308.69 10970024-3562507380
2024 3 FD52 07 E124 C 8768801C 009 9/25/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 $1.47 10970024-3562507380
2024 3 FD52 07 E124 C 8768801C 009 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507119 $0.62 10970024-3562507380
2024 3 FD52 00 E122 C 8768801C 009 9/25/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR092N1062326507065 $596.06 000001084244-3562500610
2024 3 FD52 00 E122 C 8768801C 009 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507065 $73.12 000001084244-3562500610
2024 3 FD52 00 E123 C 8768801C 009 9/25/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR092N1062326507065 $70.09 000001084244-3562500610
2024 3 FD52 00 E123 C 8768801C 009 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507065 $8.47 000001084244-3562500610
2024 3 FD52 00 E124 C 8768801C 009 9/25/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR092N1062326507065 $0.18 000001084244-3562500610
2024 3 FD52 07 E111 C 8768801C 009 9/25/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 $4,236.26 10970024-3562507380
2024 3 FD52 00 E124 C 8768801C 009 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507065 $0.02 000001084244-3562500610
2024 3 FD52 07 E111 C 8768801C 009 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507119 $1,752.58 10970024-3562507380
2024 3 FD52 07 E115 C 8768801C 009 9/25/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 $75.87 10970024-3562507380
2024 3 FD52 07 E121 C 8768801C 009 9/25/2023 4580 CONSTRUCTION CONTRACTS CA-XR092N1062326507119 $310.07 10970024-3562507380
2024 3 FD52 07 E111 C 8768801C 009 9/19/2023 4580 CONSTRUCTION CONTRACTS CA-XR091N1062325106142 $6,261.41 10970024-3562507380
2024 3 FD52 07 E111 C 8768801C 009 9/19/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106142 $538.49 10970024-3562507380
2024 3 FD52 07 E115 C 8768801C 009 9/19/2023 4580 CONSTRUCTION CONTRACTS CA-XR091N1062325106142 $518.46 10970024-3562507380
2024 3 FD52 07 E121 C 8768801C 009 9/19/2023 4580 CONSTRUCTION CONTRACTS CA-XR091N1062325106142 $494.23 10970024-3562507380
2024 3 FD52 07 E121 C 8768801C 009 9/19/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106142 $39.97 10970024-3562507380
2024 3 FD52 07 E122 C 8768801C 009 9/19/2023 4580 CONSTRUCTION CONTRACTS CA-XR091N1062325106142 $4,486.24 10970024-3562507380
2024 3 FD52 07 E797 C 8768801C 009 9/13/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P042K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $44,573.13
2024 3 FD52 07 E122 C 8768801C 009 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106143 $356.32 10970024-3562507380
2024 3 FD52 07 E123 C 8768801C 009 9/11/2023 4580 CONSTRUCTION CONTRACTS CA-XR091N1062325106143 $1,133.76 10970024-3562507380
2024 3 FD52 07 E123 C 8768801C 009 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106143 $76.08 10970024-3562507380
2024 3 FD52 00 E111 C 8768801C 009 9/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR091N1062325106095 $437.94 000001084244-3562500610
2024 3 FD52 00 E111 C 8768801C 009 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106095 $39.70 000001084244-3562500610
2024 3 FD52 00 E121 C 8768801C 009 9/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR091N1062325106095 $32.78 000001084244-3562500610
2024 3 FD52 00 E121 C 8768801C 009 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106095 $2.97 000001084244-3562500610
2024 3 FD52 00 E122 C 8768801C 009 9/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR091N1062325106095 $289.71 000001084244-3562500610
2024 3 FD52 00 E122 C 8768801C 009 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106095 $26.27 000001084244-3562500610
2024 3 FD52 00 E123 C 8768801C 009 9/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR091N1062325106095 $41.30 000001084244-3562500610
2024 3 FD52 00 E123 C 8768801C 009 9/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106095 $3.70 000001084244-3562500610
2024 3 FD52 07 E797 C 8768801C 009 9/6/2023 4580 CONSTRUCTION CONTRACTS PRC-2400008781 PON22200004165-1 Johnson, Mirmiran & Thompson Inc $9,071.00 SW HWY & Bridge Construction Inspection Region 1
2024 3 FD52 07 E111 C 8768801C 009 9/5/2023 4010 CONSTRUCTION ENGINEERING CA-XR082N1062323504933 $358.78 000001081053-3562500680
2024 3 FD52 07 E111 C 8768801C 009 9/5/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504933 $9.09 000001081053-3562500680
2024 3 FD52 07 E121 C 8768801C 009 9/5/2023 4010 CONSTRUCTION ENGINEERING CA-XR082N1062323504933 $27.44 000001081053-3562500680
2024 3 FD52 07 E121 C 8768801C 009 9/5/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504933 $0.69 000001081053-3562500680
2024 3 FD52 07 E122 C 8768801C 009 9/5/2023 4010 CONSTRUCTION ENGINEERING CA-XR082N1062323504933 $237.67 000001081053-3562500680
2024 3 FD52 07 E122 C 8768801C 009 9/5/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504933 $6.01 000001081053-3562500680
2024 3 FD52 07 E123 C 8768801C 009 9/5/2023 4010 CONSTRUCTION ENGINEERING CA-XR082N1062323504933 $0.46 000001081053-3562500680
2024 3 FD52 07 E124 C 8768801C 009 9/5/2023 4010 CONSTRUCTION ENGINEERING CA-XR082N1062323504933 $0.09 000001081053-3562500680
2024 2 FD52 07 E797 C 8768801C 009 8/30/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P041K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $130,885.19
2024 2 FD52 07 E111 C 8768801C 009 8/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR082N1062323504997 $5,415.20 10970024-3562507380
2024 2 FD52 07 E111 C 8768801C 009 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504997 $1,229.97 10970024-3562507380
2024 2 FD52 07 E115 C 8768801C 009 8/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR082N1062323504997 $404.65 10970024-3562507380
2024 2 FD52 07 E121 C 8768801C 009 8/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR082N1062323504997 $424.12 10970024-3562507380
2024 2 FD52 07 E121 C 8768801C 009 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504997 $87.07 10970024-3562507380
2024 2 FD52 00 E111 C 8768801C 009 8/24/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR082N1062323504943 $2,445.06 000001084244-3562500610
2024 2 FD52 07 E122 C 8768801C 009 8/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR082N1062323504997 $3,850.99 10970024-3562507380
2024 2 FD52 00 E111 C 8768801C 009 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504943 $318.05 000001084244-3562500610
2024 2 FD52 07 E122 C 8768801C 009 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504997 $813.88 10970024-3562507380
2024 2 FD52 00 E121 C 8768801C 009 8/24/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR082N1062323504943 $184.40 000001084244-3562500610
2024 2 FD52 07 E123 C 8768801C 009 8/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR082N1062323504997 $1,005.50 10970024-3562507380
2024 2 FD52 00 E121 C 8768801C 009 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504943 $23.65 000001084244-3562500610
2024 2 FD52 07 E123 C 8768801C 009 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504997 $286.59 10970024-3562507380
2024 2 FD52 00 E122 C 8768801C 009 8/24/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR082N1062323504943 $1,618.04 000001084244-3562500610
2024 2 FD52 07 E124 C 8768801C 009 8/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR082N1062323504997 $1.89 10970024-3562507380
2024 2 FD52 00 E122 C 8768801C 009 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504943 $210.45 000001084244-3562500610
2024 2 FD52 07 E124 C 8768801C 009 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504997 $0.43 10970024-3562507380
2024 2 FD52 00 E123 C 8768801C 009 8/24/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR082N1062323504943 $215.34 000001084244-3562500610
2024 2 FD52 00 E123 C 8768801C 009 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504943 $33.51 000001084244-3562500610
2024 2 FD52 00 E124 C 8768801C 009 8/24/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR082N1062323504943 $0.52 000001084244-3562500610
2024 2 FD52 00 E124 C 8768801C 009 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504943 $0.06 000001084244-3562500610
2024 2 FD52 07 E797 C 8768801C 009 8/16/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P040K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $124,225.47
2024 2 FD52 07 E121 C 8768801C 009 8/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR081N1062322003904 $0.90 10776817-3562507380
2024 2 FD52 07 E121 C 8768801C 009 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003904 $0.01 10776817-3562507380
2024 2 FD52 00 E111 C 8768801C 009 8/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR081N1062322003862 $215.78 000001084244-3562500610
2024 2 FD52 00 E111 C 8768801C 009 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003862 $140.48 000001084244-3562500610
2024 2 FD52 00 E121 C 8768801C 009 8/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR081N1062322003862 $15.03 000001084244-3562500610
2024 2 FD52 00 E121 C 8768801C 009 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003862 $9.78 000001084244-3562500610
2024 2 FD52 00 E122 C 8768801C 009 8/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR081N1062322003862 $142.63 000001084244-3562500610
2024 2 FD52 00 E122 C 8768801C 009 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003862 $92.95 000001084244-3562500610
2024 2 FD52 07 E111 C 8768801C 009 8/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR081N1062322003909 $8,324.92 10970024-3562507380
2024 2 FD52 00 E123 C 8768801C 009 8/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR081N1062322003862 $39.23 000001084244-3562500610
2024 2 FD52 07 E111 C 8768801C 009 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003909 $1,814.20 10970024-3562507380
2024 2 FD52 00 E123 C 8768801C 009 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003862 $25.13 000001084244-3562500610
2024 2 FD52 07 E115 C 8768801C 009 8/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR081N1062322003909 $606.98 10970024-3562507380
2024 2 FD52 07 E121 C 8768801C 009 8/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR081N1062322003909 $649.26 10970024-3562507380
2024 2 FD52 07 E121 C 8768801C 009 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003909 $128.46 10970024-3562507380
2024 2 FD52 07 E122 C 8768801C 009 8/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR081N1062322003909 $5,910.32 10970024-3562507380
2024 2 FD52 07 E122 C 8768801C 009 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003909 $1,200.45 10970024-3562507380
2024 2 FD52 07 E123 C 8768801C 009 8/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR081N1062322003909 $1,444.10 10970024-3562507380
2024 2 FD52 07 E123 C 8768801C 009 8/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081N1062322003909 $338.79 10970024-3562507380
2024 2 FD52 07 E797 C 8768801C 009 8/2/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P039K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $182,982.85
2024 1 FD52 00 E111 C 8768801C 009 7/28/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR072N1062320202682 $525.56 000001084244-3562500610
2024 1 FD52 00 E111 C 8768801C 009 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202682 $71.45 000001084244-3562500610
2024 1 FD52 00 E121 C 8768801C 009 7/28/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR072N1062320202682 $39.35 000001084244-3562500610
2024 1 FD52 00 E121 C 8768801C 009 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202682 $5.35 000001084244-3562500610
2024 1 FD52 00 E122 C 8768801C 009 7/28/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR072N1062320202682 $347.66 000001084244-3562500610
2024 1 FD52 00 E122 C 8768801C 009 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202682 $47.28 000001084244-3562500610
2024 1 FD52 00 E123 C 8768801C 009 7/28/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR072N1062320202682 $49.59 000001084244-3562500610
2024 1 FD52 00 E123 C 8768801C 009 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202682 $6.66 000001084244-3562500610
2024 1 FD52 00 E124 C 8768801C 009 7/28/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR072N1062320202682 $0.10 000001084244-3562500610
2024 1 FD52 00 E124 C 8768801C 009 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202682 $0.01 000001084244-3562500610
2024 1 FD52 07 E111 C 8768801C 009 7/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR072N1062320202843 $7,952.02 10970024-3562507380
2024 1 FD52 07 E111 C 8768801C 009 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202843 $3,460.06 10970024-3562507380
2024 1 FD52 07 E115 C 8768801C 009 7/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR072N1062320202843 $126.46 10970024-3562507380
2024 1 FD52 07 E121 C 8768801C 009 7/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR072N1062320202843 $583.95 10970024-3562507380
2024 1 FD52 07 E121 C 8768801C 009 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202843 $249.97 10970024-3562507380
2024 1 FD52 07 E122 C 8768801C 009 7/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR072N1062320202843 $5,345.53 10970024-3562507380
2024 1 FD52 07 E122 C 8768801C 009 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202843 $2,289.50 10970024-3562507380
2024 1 FD52 07 E123 C 8768801C 009 7/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR072N1062320202843 $1,485.91 10970024-3562507380
2024 1 FD52 07 E123 C 8768801C 009 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202843 $629.39 10970024-3562507380
2024 1 FD52 07 E124 C 8768801C 009 7/28/2023 4580 CONSTRUCTION CONTRACTS CA-XR072N1062320202843 $2.63 10970024-3562507380
2024 1 FD52 07 E124 C 8768801C 009 7/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202843 $1.19 10970024-3562507380
2024 1 FD52 00 E229 C 8768801C 009 7/26/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523206002250 $15.17
2024 1 FD52 07 E115 C 8768801C 009 7/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR072N1062320202732 $918.57 10776817-3562507380
2024 1 FD52 07 E121 C 8768801C 009 7/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR072N1062320202732 $58.35 10776817-3562507380
2024 1 FD52 07 E121 C 8768801C 009 7/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202732 ($0.11) 10776817-3562507380
2024 1 FD52 07 E122 C 8768801C 009 7/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR072N1062320202732 $716.48 10776817-3562507380
2024 1 FD52 07 E123 C 8768801C 009 7/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR072N1062320202732 $277.37 10776817-3562507380
2024 1 FD52 07 E123 C 8768801C 009 7/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072N1062320202732 $5.11 10776817-3562507380
2024 1 FD52 07 E797 C 8768801C 009 7/19/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P038K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $169,952.53
2024 1 FD52 07 E111 C 8768801C 009 7/14/2023 4580 CONSTRUCTION CONTRACTS CA-XR071N1062319101586 $9,558.40 10776817-3562507380
2024 1 FD52 07 E111 C 8768801C 009 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101586 $893.80 10776817-3562507380
2024 1 FD52 07 E115 C 8768801C 009 7/14/2023 4580 CONSTRUCTION CONTRACTS CA-XR071N1062319101586 $810.14 10776817-3562507380
2024 1 FD52 07 E121 C 8768801C 009 7/14/2023 4580 CONSTRUCTION CONTRACTS CA-XR071N1062319101586 $756.59 10776817-3562507380
2024 1 FD52 07 E121 C 8768801C 009 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101586 $66.72 10776817-3562507380
2024 1 FD52 07 E122 C 8768801C 009 7/14/2023 4580 CONSTRUCTION CONTRACTS CA-XR071N1062319101586 $8,087.64 10776817-3562507380
2024 1 FD52 07 E122 C 8768801C 009 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101586 $697.15 10776817-3562507380
2024 1 FD52 07 E123 C 8768801C 009 7/14/2023 4580 CONSTRUCTION CONTRACTS CA-XR071N1062319101586 $1,575.66 10776817-3562507380
2024 1 FD52 07 E123 C 8768801C 009 7/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101586 $108.50 10776817-3562507380
2024 1 FD52 07 E797 C 8768801C 009 7/13/2023 4580 CONSTRUCTION CONTRACTS PRC-2400003885 PON22200004165-1 Johnson, Mirmiran & Thompson Inc $916.50 SW HWY & Bridge Construction Inspection Region 1
2024 1 FD52 00 E229 C 8768801C 009 7/12/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523191008610 $15.17
2024 1 FD52 07 E797 C 8768801C 009 7/12/2023 4580 CONSTRUCTION CONTRACTS PRC-2400003496 PON22200004165-1 Johnson, Mirmiran & Thompson Inc $7,807.00 SW HWY & Bridge Construction Inspection Region 1
2024 1 FD52 07 E121 C 8768801C 009 7/11/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR071N1062319101544 $0.13 000001082265-3562507210
2024 1 FD52 00 E111 C 8768801C 009 7/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR071N1062319101550 $450.38 000001084244-3562500610
2024 1 FD52 00 E111 C 8768801C 009 7/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101550 $11.42 000001084244-3562500610
2024 1 FD52 00 E121 C 8768801C 009 7/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR071N1062319101550 $33.70 000001084244-3562500610
2024 1 FD52 00 E121 C 8768801C 009 7/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101550 $0.85 000001084244-3562500610
2024 1 FD52 00 E122 C 8768801C 009 7/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR071N1062319101550 $351.46 000001084244-3562500610
2024 1 FD52 00 E122 C 8768801C 009 7/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101550 $8.91 000001084244-3562500610
2024 1 FD52 00 E123 C 8768801C 009 7/11/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR071N1062319101550 $45.04 000001084244-3562500610
2024 1 FD52 00 E123 C 8768801C 009 7/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071N1062319101550 $1.13 000001084244-3562500610
2024 1 FD52 07 E797 C 8768801C 009 7/6/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P037K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $208,272.03
2023 12 FD52 00 E229 C 8768801C 009 6/26/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523176006800 $15.17
2023 12 FD52 07 E122 C 8768801C 009 6/26/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR062N1062317400431 $168.87 000001082265-3562507210
2023 12 FD52 07 E123 C 8768801C 009 6/26/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR062N1062317400431 $34.30 000001082265-3562507210
2023 12 FD52 07 E111 C 8768801C 009 6/26/2023 4580 CONSTRUCTION CONTRACTS CA-XR062N1062317400485 $4,765.29 10776817-3562507380
2023 12 FD52 07 E124 C 8768801C 009 6/26/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR062N1062317400431 $0.09 000001082265-3562507210
2023 12 FD52 07 E111 C 8768801C 009 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317400485 $589.22 10776817-3562507380
2023 12 FD52 07 E115 C 8768801C 009 6/26/2023 4580 CONSTRUCTION CONTRACTS CA-XR062N1062317400485 $989.21 10776817-3562507380
2023 12 FD52 07 E121 C 8768801C 009 6/26/2023 4580 CONSTRUCTION CONTRACTS CA-XR062N1062317400485 $420.70 10776817-3562507380
2023 12 FD52 07 E121 C 8768801C 009 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317400485 $43.82 10776817-3562507380
2023 12 FD52 07 E122 C 8768801C 009 6/26/2023 4580 CONSTRUCTION CONTRACTS CA-XR062N1062317400485 $4,488.52 10776817-3562507380
2023 12 FD52 07 E122 C 8768801C 009 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317400485 $459.59 10776817-3562507380
2023 12 FD52 07 E123 C 8768801C 009 6/26/2023 4580 CONSTRUCTION CONTRACTS CA-XR062N1062317400485 $948.42 10776817-3562507380
2023 12 FD52 07 E123 C 8768801C 009 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317400485 $83.75 10776817-3562507380
2023 12 FD52 07 E124 C 8768801C 009 6/26/2023 4580 CONSTRUCTION CONTRACTS CA-XR062N1062317400485 $1.87 10776817-3562507380
2023 12 FD52 07 E124 C 8768801C 009 6/26/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062N1062317400485 $0.18 10776817-3562507380
2023 12 FD52 07 E111 C 8768801C 009 6/26/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR062N1062317400430 $216.50 000001082265-3562507210
2023 12 FD52 07 E121 C 8768801C 009 6/26/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR062N1062317400430 $16.00 000001082265-3562507210
2023 12 FD52 07 E797 C 8768801C 009 6/21/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P036K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $793,533.11
2023 12 FD52 00 E229 C 8768801C 009 6/13/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A262523161000380 $15.17
2023 12 FD52 07 E121 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810182 $81.22 10776817-3562507380
2023 12 FD52 07 E122 C 8768801C 009 6/8/2023 4580 CONSTRUCTION CONTRACTS CA-XR061N1062315810182 $2,860.59 10776817-3562507380
2023 12 FD52 07 E122 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810182 $857.93 10776817-3562507380
2023 12 FD52 07 E123 C 8768801C 009 6/8/2023 4580 CONSTRUCTION CONTRACTS CA-XR061N1062315810182 $551.59 10776817-3562507380
2023 12 FD52 07 E123 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810182 $168.35 10776817-3562507380
2023 12 FD52 00 E111 C 8768801C 009 6/8/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR061N1062315810145 $131.35 000001084244-3562500610
2023 12 FD52 00 E111 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810145 $48.78 000001084244-3562500610
2023 12 FD52 00 E121 C 8768801C 009 6/8/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR061N1062315810145 $10.04 000001084244-3562500610
2023 12 FD52 00 E121 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810145 $3.73 000001084244-3562500610
2023 12 FD52 00 E122 C 8768801C 009 6/8/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR061N1062315810145 $102.44 000001084244-3562500610
2023 12 FD52 00 E122 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810145 $38.06 000001084244-3562500610
2023 12 FD52 00 E123 C 8768801C 009 6/8/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR061N1062315810145 $3.67 000001084244-3562500610
2023 12 FD52 00 E123 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810145 $1.26 000001084244-3562500610
2023 12 FD52 07 E111 C 8768801C 009 6/8/2023 4580 CONSTRUCTION CONTRACTS CA-XR061N1062315810182 $3,557.51 10776817-3562507380
2023 12 FD52 07 E111 C 8768801C 009 6/8/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR061N1062315810136 $289.20 000001082265-3562507210
2023 12 FD52 07 E111 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810136 $42.39 000001082265-3562507210
2023 12 FD52 07 E121 C 8768801C 009 6/8/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR061N1062315810136 $21.78 000001082265-3562507210
2023 12 FD52 07 E121 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810136 $3.19 000001082265-3562507210
2023 12 FD52 07 E122 C 8768801C 009 6/8/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR061N1062315810136 $225.45 000001082265-3562507210
2023 12 FD52 07 E122 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810136 $33.07 000001082265-3562507210
2023 12 FD52 07 E123 C 8768801C 009 6/8/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR061N1062315810136 $32.14 000001082265-3562507210
2023 12 FD52 07 E123 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810136 $4.64 000001082265-3562507210
2023 12 FD52 07 E111 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810182 $1,099.91 10776817-3562507380
2023 12 FD52 07 E115 C 8768801C 009 6/8/2023 4580 CONSTRUCTION CONTRACTS CA-XR061N1062315810182 $109.91 10776817-3562507380
2023 12 FD52 07 E111 C 8768801C 009 6/8/2023 4010 CONSTRUCTION ENGINEERING CA-XR061N1062315810132 $183.39 000001081053-3562500620
2023 12 FD52 07 E111 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810132 $92.65 000001081053-3562500620
2023 12 FD52 07 E121 C 8768801C 009 6/8/2023 4010 CONSTRUCTION ENGINEERING CA-XR061N1062315810132 $13.57 000001081053-3562500620
2023 12 FD52 07 E121 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810132 $6.85 000001081053-3562500620
2023 12 FD52 07 E121 C 8768801C 009 6/8/2023 4580 CONSTRUCTION CONTRACTS CA-XR061N1062315810182 $270.78 10776817-3562507380
2023 12 FD52 07 E122 C 8768801C 009 6/8/2023 4010 CONSTRUCTION ENGINEERING CA-XR061N1062315810132 $143.00 000001081053-3562500620
2023 12 FD52 07 E122 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810132 $72.26 000001081053-3562500620
2023 12 FD52 07 E123 C 8768801C 009 6/8/2023 4010 CONSTRUCTION ENGINEERING CA-XR061N1062315810132 $31.66 000001081053-3562500620
2023 12 FD52 07 E123 C 8768801C 009 6/8/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810132 $15.68 000001081053-3562500620
2023 12 FD52 07 E797 C 8768801C 009 6/7/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P035K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $602,716.37
2023 12 FD52 07 E111 C 8768801C 009 6/1/2023 4580 CONSTRUCTION CONTRACTS CA-XS052N1062315109806 $2,395.98 10776817-3562507380
2023 12 FD52 07 E115 C 8768801C 009 6/1/2023 4580 CONSTRUCTION CONTRACTS CA-XS052N1062315109806 $653.46 10776817-3562507380
2023 12 FD52 07 E116 C 8768801C 009 6/1/2023 4580 CONSTRUCTION CONTRACTS CA-XS052N1062315109806 $41.63 10776817-3562507380
2023 12 FD52 07 E121 C 8768801C 009 6/1/2023 4580 CONSTRUCTION CONTRACTS CA-XS052N1062315109806 $229.16 10776817-3562507380
2023 12 FD52 07 E122 C 8768801C 009 6/1/2023 4580 CONSTRUCTION CONTRACTS CA-XS052N1062315109806 $2,411.03 10776817-3562507380
2023 12 FD52 07 E123 C 8768801C 009 6/1/2023 4580 CONSTRUCTION CONTRACTS CA-XS052N1062315109806 $430.10 10776817-3562507380
2023 12 FD52 07 E124 C 8768801C 009 6/1/2023 4580 CONSTRUCTION CONTRACTS CA-XS052N1062315109806 $1.00 10776817-3562507380
2023 11 FD52 07 E111 C 8768801C 009 5/30/2023 4010 CONSTRUCTION ENGINEERING CA-XR052N1062314309036 $279.11 000001081053-3562500680
2023 11 FD52 07 E111 C 8768801C 009 5/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309036 $5.21 000001081053-3562500680
2023 11 FD52 07 E121 C 8768801C 009 5/30/2023 4010 CONSTRUCTION ENGINEERING CA-XR052N1062314309036 $21.16 000001081053-3562500680
2023 11 FD52 07 E121 C 8768801C 009 5/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309036 $0.39 000001081053-3562500680
2023 11 FD52 07 E122 C 8768801C 009 5/30/2023 4010 CONSTRUCTION ENGINEERING CA-XR052N1062314309036 $217.73 000001081053-3562500680
2023 11 FD52 07 E122 C 8768801C 009 5/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309036 $4.06 000001081053-3562500680
2023 11 FD52 07 E123 C 8768801C 009 5/30/2023 4010 CONSTRUCTION ENGINEERING CA-XR052N1062314309036 $35.00 000001081053-3562500680
2023 11 FD52 07 E123 C 8768801C 009 5/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309036 $0.64 000001081053-3562500680
2023 11 FD52 07 E124 C 8768801C 009 5/30/2023 4010 CONSTRUCTION ENGINEERING CA-XR052N1062314309036 $0.09 000001081053-3562500680
2023 11 FD52 07 E111 C 8768801C 009 5/30/2023 4580 CONSTRUCTION CONTRACTS CA-XR052N1062314309090 $2,117.73 10776817-3562507380
2023 11 FD52 07 E111 C 8768801C 009 5/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309090 $428.16 10776817-3562507380
2023 11 FD52 07 E115 C 8768801C 009 5/30/2023 4580 CONSTRUCTION CONTRACTS CA-XR052N1062314309090 $190.77 10776817-3562507380
2023 11 FD52 07 E121 C 8768801C 009 5/30/2023 4580 CONSTRUCTION CONTRACTS CA-XR052N1062314309090 $173.97 10776817-3562507380
2023 11 FD52 07 E121 C 8768801C 009 5/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309090 $32.17 10776817-3562507380
2023 11 FD52 07 E122 C 8768801C 009 5/30/2023 4580 CONSTRUCTION CONTRACTS CA-XR052N1062314309090 $1,800.63 10776817-3562507380
2023 11 FD52 07 E122 C 8768801C 009 5/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309090 $333.97 10776817-3562507380
2023 11 FD52 07 E123 C 8768801C 009 5/30/2023 4580 CONSTRUCTION CONTRACTS CA-XR052N1062314309090 $247.62 10776817-3562507380
2023 11 FD52 07 E123 C 8768801C 009 5/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309090 $52.30 10776817-3562507380
2023 11 FD52 07 E124 C 8768801C 009 5/30/2023 4580 CONSTRUCTION CONTRACTS CA-XR052N1062314309090 $0.68 10776817-3562507380
2023 11 FD52 07 E124 C 8768801C 009 5/30/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052N1062314309090 $0.13 10776817-3562507380
2023 11 FD52 00 E229 C 8768801C 009 5/26/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523145004400 $15.17
2023 11 FD52 07 E797 C 8768801C 009 5/24/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P034K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $340,459.47
2023 11 FD52 00 E229 C 8768801C 009 5/15/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523130005220 $15.17
2023 11 FD52 07 E797 C 8768801C 009 5/10/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P033K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $476,938.34
2023 11 FD52 07 E154 C 8768801C 009 5/10/2023 4010 CONSTRUCTION ENGINEERING ITA-5202300000148 $4,944.70 October Workzone 2023
2023 11 FD52 07 E111 C 8768801C 009 5/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR051N1062312808105 $2,178.16 10776817-3562507380
2023 11 FD52 07 E115 C 8768801C 009 5/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR051N1062312808105 $1,017.06 10776817-3562507380
2023 11 FD52 07 E116 C 8768801C 009 5/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR051N1062312808105 $61.88 10776817-3562507380
2023 11 FD52 07 E121 C 8768801C 009 5/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR051N1062312808105 $241.17 10776817-3562507380
2023 11 FD52 07 E122 C 8768801C 009 5/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR051N1062312808105 $2,540.53 10776817-3562507380
2023 11 FD52 07 E123 C 8768801C 009 5/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR051N1062312808105 $430.10 10776817-3562507380
2023 11 FD52 00 E111 C 8768801C 009 5/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR051N1062312808073 $1,079.54 000001084244-3562500610
2023 11 FD52 00 E111 C 8768801C 009 5/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808073 $70.78 000001084244-3562500610
2023 11 FD52 00 E121 C 8768801C 009 5/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR051N1062312808073 $79.91 000001084244-3562500610
2023 11 FD52 00 E121 C 8768801C 009 5/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808073 $5.22 000001084244-3562500610
2023 11 FD52 00 E122 C 8768801C 009 5/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR051N1062312808073 $842.22 000001084244-3562500610
2023 11 FD52 00 E122 C 8768801C 009 5/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808073 $55.21 000001084244-3562500610
2023 11 FD52 00 E123 C 8768801C 009 5/9/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR051N1062312808073 $154.75 000001084244-3562500610
2023 11 FD52 00 E123 C 8768801C 009 5/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808073 $10.78 000001084244-3562500610
2023 10 FD52 07 E121 C 8768801C 009 4/28/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR042N1062311106935 $22.46 000001082265-3562507210
2023 10 FD52 07 E121 C 8768801C 009 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106935 $12.94 000001082265-3562507210
2023 10 FD52 07 E122 C 8768801C 009 4/28/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR042N1062311106935 $242.10 000001082265-3562507210
2023 10 FD52 07 E122 C 8768801C 009 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106935 $138.76 000001082265-3562507210
2023 10 FD52 07 E123 C 8768801C 009 4/28/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR042N1062311106935 $53.55 000001082265-3562507210
2023 10 FD52 07 E123 C 8768801C 009 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106935 $28.87 000001082265-3562507210
2023 10 FD52 07 E124 C 8768801C 009 4/28/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR042N1062311106935 $0.14 000001082265-3562507210
2023 10 FD52 07 E124 C 8768801C 009 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106935 $0.08 000001082265-3562507210
2023 10 FD52 07 E111 C 8768801C 009 4/28/2023 4010 CONSTRUCTION ENGINEERING CA-XR042N1062311106929 $306.85 000001081053-3562500680
2023 10 FD52 07 E111 C 8768801C 009 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106929 $76.97 000001081053-3562500680
2023 10 FD52 07 E121 C 8768801C 009 4/28/2023 4010 CONSTRUCTION ENGINEERING CA-XR042N1062311106929 $23.29 000001081053-3562500680
2023 10 FD52 07 E121 C 8768801C 009 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106929 $5.84 000001081053-3562500680
2023 10 FD52 07 E111 C 8768801C 009 4/28/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR042N1062311106935 $310.21 000001082265-3562507210
2023 10 FD52 07 E122 C 8768801C 009 4/28/2023 4010 CONSTRUCTION ENGINEERING CA-XR042N1062311106929 $239.51 000001081053-3562500680
2023 10 FD52 07 E122 C 8768801C 009 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106929 $60.04 000001081053-3562500680
2023 10 FD52 07 E123 C 8768801C 009 4/28/2023 4010 CONSTRUCTION ENGINEERING CA-XR042N1062311106929 $38.62 000001081053-3562500680
2023 10 FD52 07 E123 C 8768801C 009 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106929 $9.52 000001081053-3562500680
2023 10 FD52 07 E124 C 8768801C 009 4/28/2023 4010 CONSTRUCTION ENGINEERING CA-XR042N1062311106929 $0.10 000001081053-3562500680
2023 10 FD52 07 E124 C 8768801C 009 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106929 $0.03 000001081053-3562500680
2023 10 FD52 07 E111 C 8768801C 009 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106935 $177.89 000001082265-3562507210
2023 10 FD52 00 E229 C 8768801C 009 4/27/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523115004560 $15.17
2023 10 FD52 07 E797 C 8768801C 009 4/26/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P032K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $122,393.43
2023 10 FD52 00 E111 C 8768801C 009 4/24/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR042N1062311106946 $2,119.37 000001084244-3562500610
2023 10 FD52 00 E111 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106946 $271.56 000001084244-3562500610
2023 10 FD52 00 E121 C 8768801C 009 4/24/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR042N1062311106946 $159.13 000001084244-3562500610
2023 10 FD52 00 E121 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106946 $20.35 000001084244-3562500610
2023 10 FD52 00 E122 C 8768801C 009 4/24/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR042N1062311106946 $1,652.87 000001084244-3562500610
2023 10 FD52 00 E122 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106946 $211.82 000001084244-3562500610
2023 10 FD52 00 E123 C 8768801C 009 4/24/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR042N1062311106946 $252.72 000001084244-3562500610
2023 10 FD52 00 E123 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106946 $33.46 000001084244-3562500610
2023 10 FD52 00 E124 C 8768801C 009 4/24/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR042N1062311106946 $0.63 000001084244-3562500610
2023 10 FD52 00 E124 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106946 $0.09 000001084244-3562500610
2023 10 FD52 00 E111 C 8768801C 009 4/24/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR042N1062311106932 $258.47 000001081807-3562500640
2023 10 FD52 00 E111 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106932 $258.48 000001081807-3562500640
2023 10 FD52 00 E121 C 8768801C 009 4/24/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR042N1062311106932 $19.29 000001081807-3562500640
2023 10 FD52 00 E121 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106932 $19.29 000001081807-3562500640
2023 10 FD52 00 E122 C 8768801C 009 4/24/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR042N1062311106932 $201.60 000001081807-3562500640
2023 10 FD52 00 E122 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106932 $201.61 000001081807-3562500640
2023 10 FD52 07 E111 C 8768801C 009 4/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR042N1062311106983 $3,499.82 10776817-3562507380
2023 10 FD52 00 E123 C 8768801C 009 4/24/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR042N1062311106932 $41.52 000001081807-3562500640
2023 10 FD52 07 E111 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106983 $796.71 10776817-3562507380
2023 10 FD52 00 E123 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106932 $40.50 000001081807-3562500640
2023 10 FD52 07 E115 C 8768801C 009 4/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR042N1062311106983 $408.42 10776817-3562507380
2023 10 FD52 00 E124 C 8768801C 009 4/24/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR042N1062311106932 $0.10 000001081807-3562500640
2023 10 FD52 07 E116 C 8768801C 009 4/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR042N1062311106983 $24.00 10776817-3562507380
2023 10 FD52 00 E124 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106932 $0.10 000001081807-3562500640
2023 10 FD52 07 E121 C 8768801C 009 4/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR042N1062311106983 $288.38 10776817-3562507380
2023 10 FD52 07 E121 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106983 $58.50 10776817-3562507380
2023 10 FD52 07 E122 C 8768801C 009 4/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR042N1062311106983 $3,067.15 10776817-3562507380
2023 10 FD52 07 E122 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106983 $621.43 10776817-3562507380
2023 10 FD52 07 E123 C 8768801C 009 4/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR042N1062311106983 $644.24 10776817-3562507380
2023 10 FD52 07 E123 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106983 $148.65 10776817-3562507380
2023 10 FD52 07 E124 C 8768801C 009 4/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR042N1062311106983 $1.45 10776817-3562507380
2023 10 FD52 07 E124 C 8768801C 009 4/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106983 $0.35 10776817-3562507380
2023 10 FD52 00 E229 C 8768801C 009 4/14/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523100003530 $15.17
2023 10 FD52 07 E123 C 8768801C 009 4/14/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR041N1062309605769 $38.91 000001082265-3562507210
2023 10 FD52 07 E123 C 8768801C 009 4/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605769 $1.08 000001082265-3562507210
2023 10 FD52 07 E797 C 8768801C 009 4/12/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P031K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $106,486.51
2023 10 FD52 00 E111 C 8768801C 009 4/10/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR041N1062309605777 $215.39 000001084244-3562500610
2023 10 FD52 00 E111 C 8768801C 009 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605777 $39.63 000001084244-3562500610
2023 10 FD52 00 E121 C 8768801C 009 4/10/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR041N1062309605777 $16.04 000001084244-3562500610
2023 10 FD52 00 E121 C 8768801C 009 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605777 $2.96 000001084244-3562500610
2023 10 FD52 00 E122 C 8768801C 009 4/10/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR041N1062309605777 $168.01 000001084244-3562500610
2023 10 FD52 00 E122 C 8768801C 009 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605777 $30.91 000001084244-3562500610
2023 10 FD52 00 E123 C 8768801C 009 4/10/2023 5341 GEOTECHNICAL INVEST (CONST) CA-XR041N1062309605777 $41.35 000001084244-3562500610
2023 10 FD52 00 E123 C 8768801C 009 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605777 $7.51 000001084244-3562500610
2023 10 FD52 07 E111 C 8768801C 009 4/10/2023 4580 CONSTRUCTION CONTRACTS CA-XR041N1062309605807 $7,581.76 10776817-3562507380
2023 10 FD52 07 E111 C 8768801C 009 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605807 $1,110.02 10776817-3562507380
2023 10 FD52 07 E115 C 8768801C 009 4/10/2023 4580 CONSTRUCTION CONTRACTS CA-XR041N1062309605807 $754.20 10776817-3562507380
2023 10 FD52 07 E116 C 8768801C 009 4/10/2023 4580 CONSTRUCTION CONTRACTS CA-XR041N1062309605807 $12.00 10776817-3562507380
2023 10 FD52 07 E111 C 8768801C 009 4/10/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR041N1062309605768 $198.51 000001082265-3562507210
2023 10 FD52 07 E121 C 8768801C 009 4/10/2023 4580 CONSTRUCTION CONTRACTS CA-XR041N1062309605807 $617.71 10776817-3562507380
2023 10 FD52 07 E111 C 8768801C 009 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605768 $5.56 000001082265-3562507210
2023 10 FD52 07 E121 C 8768801C 009 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605807 $80.77 10776817-3562507380
2023 10 FD52 07 E121 C 8768801C 009 4/10/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR041N1062309605768 $14.18 000001082265-3562507210
2023 10 FD52 07 E122 C 8768801C 009 4/10/2023 4580 CONSTRUCTION CONTRACTS CA-XR041N1062309605807 $6,511.44 10776817-3562507380
2023 10 FD52 07 E121 C 8768801C 009 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605768 $0.40 000001082265-3562507210
2023 10 FD52 07 E122 C 8768801C 009 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605807 $865.81 10776817-3562507380
2023 10 FD52 07 E122 C 8768801C 009 4/10/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR041N1062309605768 $154.80 000001082265-3562507210
2023 10 FD52 07 E123 C 8768801C 009 4/10/2023 4580 CONSTRUCTION CONTRACTS CA-XR041N1062309605807 $1,039.94 10776817-3562507380
2023 10 FD52 07 E122 C 8768801C 009 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605768 $4.34 000001082265-3562507210
2023 10 FD52 07 E123 C 8768801C 009 4/10/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605807 $174.02 10776817-3562507380
2023 9 FD52 07 E111 C 8768801C 009 3/31/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR032N1062308304645 $1,782.85 000001082265-3562507210
2023 9 FD52 07 E111 C 8768801C 009 3/31/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304645 $157.74 000001082265-3562507210
2023 9 FD52 07 E121 C 8768801C 009 3/31/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR032N1062308304645 $128.86 000001082265-3562507210
2023 9 FD52 07 E121 C 8768801C 009 3/31/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304645 $11.19 000001082265-3562507210
2023 9 FD52 07 E122 C 8768801C 009 3/31/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR032N1062308304645 $1,390.77 000001082265-3562507210
2023 9 FD52 07 E122 C 8768801C 009 3/31/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304645 $123.04 000001082265-3562507210
2023 9 FD52 07 E123 C 8768801C 009 3/31/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR032N1062308304645 $312.57 000001082265-3562507210
2023 9 FD52 07 E123 C 8768801C 009 3/31/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304645 $31.02 000001082265-3562507210
2023 9 FD52 07 E124 C 8768801C 009 3/31/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR032N1062308304645 $0.75 000001082265-3562507210
2023 9 FD52 07 E124 C 8768801C 009 3/31/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304645 $0.07 000001082265-3562507210
2023 9 FD52 07 E797 C 8768801C 009 3/30/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P030K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $116,022.87
2023 9 FD52 00 E229 C 8768801C 009 3/29/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523084005070 $15.17
2023 9 FD52 07 E111 C 8768801C 009 3/27/2023 4580 CONSTRUCTION CONTRACTS CA-XR032N1062308304691 $7,125.18 10776817-3562507380
2023 9 FD52 07 E111 C 8768801C 009 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304691 $622.57 10776817-3562507380
2023 9 FD52 07 E115 C 8768801C 009 3/27/2023 4580 CONSTRUCTION CONTRACTS CA-XR032N1062308304691 $329.28 10776817-3562507380
2023 9 FD52 07 E116 C 8768801C 009 3/27/2023 4580 CONSTRUCTION CONTRACTS CA-XR032N1062308304691 $6.00 10776817-3562507380
2023 9 FD52 07 E121 C 8768801C 009 3/27/2023 4580 CONSTRUCTION CONTRACTS CA-XR032N1062308304691 $551.79 10776817-3562507380
2023 9 FD52 07 E121 C 8768801C 009 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304691 $45.81 10776817-3562507380
2023 9 FD52 07 E122 C 8768801C 009 3/27/2023 4580 CONSTRUCTION CONTRACTS CA-XR032N1062308304691 $5,819.16 10776817-3562507380
2023 9 FD52 07 E122 C 8768801C 009 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304691 $485.61 10776817-3562507380
2023 9 FD52 07 E123 C 8768801C 009 3/27/2023 4580 CONSTRUCTION CONTRACTS CA-XR032N1062308304691 $961.00 10776817-3562507380
2023 9 FD52 07 E123 C 8768801C 009 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304691 $97.22 10776817-3562507380
2023 9 FD52 07 E124 C 8768801C 009 3/27/2023 4580 CONSTRUCTION CONTRACTS CA-XR032N1062308304691 $3.00 10776817-3562507380
2023 9 FD52 07 E124 C 8768801C 009 3/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304691 $0.27 10776817-3562507380
2023 9 FD52 00 E229 C 8768801C 009 3/17/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523069004000 $15.17
2023 9 FD52 07 E797 C 8768801C 009 3/16/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P029K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $271,147.27
2023 9 FD52 07 E111 C 8768801C 009 3/14/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR031N1062306703660 $3,760.66 000001082265-3562507210
2023 9 FD52 07 E111 C 8768801C 009 3/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703660 $982.46 000001082265-3562507210
2023 9 FD52 07 E121 C 8768801C 009 3/14/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR031N1062306703660 $271.05 000001082265-3562507210
2023 9 FD52 07 E121 C 8768801C 009 3/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703660 $70.91 000001082265-3562507210
2023 9 FD52 07 E122 C 8768801C 009 3/14/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR031N1062306703660 $2,933.35 000001082265-3562507210
2023 9 FD52 07 E122 C 8768801C 009 3/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703660 $766.32 000001082265-3562507210
2023 9 FD52 07 E123 C 8768801C 009 3/14/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR031N1062306703660 $660.21 000001082265-3562507210
2023 9 FD52 07 E123 C 8768801C 009 3/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703660 $169.91 000001082265-3562507210
2023 9 FD52 07 E121 C 8768801C 009 3/9/2023 4010 CONSTRUCTION ENGINEERING CA-XR031N1062306703657 $25.69 000001081053-3562500680
2023 9 FD52 07 E121 C 8768801C 009 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703692 $58.40 10776817-3562507380
2023 9 FD52 07 E122 C 8768801C 009 3/9/2023 4010 CONSTRUCTION ENGINEERING CA-XR031N1062306703657 $266.12 000001081053-3562500680
2023 9 FD52 07 E122 C 8768801C 009 3/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR031N1062306703692 $5,001.84 10776817-3562507380
2023 9 FD52 07 E123 C 8768801C 009 3/9/2023 4010 CONSTRUCTION ENGINEERING CA-XR031N1062306703657 $42.77 000001081053-3562500680
2023 9 FD52 07 E122 C 8768801C 009 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703692 $622.63 10776817-3562507380
2023 9 FD52 07 E123 C 8768801C 009 3/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR031N1062306703692 $896.94 10776817-3562507380
2023 9 FD52 07 E123 C 8768801C 009 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703692 $121.32 10776817-3562507380
2023 9 FD52 00 E111 C 8768801C 009 3/9/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR031N1062306703659 $574.38 000001081807-3562500640
2023 9 FD52 00 E121 C 8768801C 009 3/9/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR031N1062306703659 $42.19 000001081807-3562500640
2023 9 FD52 00 E122 C 8768801C 009 3/9/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR031N1062306703659 $448.02 000001081807-3562500640
2023 9 FD52 00 E123 C 8768801C 009 3/9/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR031N1062306703659 $91.13 000001081807-3562500640
2023 9 FD52 07 E111 C 8768801C 009 3/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR031N1062306703692 $6,358.13 10776817-3562507380
2023 9 FD52 07 E111 C 8768801C 009 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703692 $798.23 10776817-3562507380
2023 9 FD52 07 E115 C 8768801C 009 3/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR031N1062306703692 $54.50 10776817-3562507380
2023 9 FD52 07 E111 C 8768801C 009 3/9/2023 4010 CONSTRUCTION ENGINEERING CA-XR031N1062306703657 $341.17 000001081053-3562500680
2023 9 FD52 07 E121 C 8768801C 009 3/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR031N1062306703692 $472.99 10776817-3562507380
2023 9 FD52 00 E111 C 8768801C 009 3/9/2023 5352 INSPECTION OF CONCRETE PLANTS CA-XR031N1062306703656 $287.08 000001080990-3562500640
2023 9 FD52 00 E111 C 8768801C 009 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703656 $11.10 000001080990-3562500640
2023 9 FD52 00 E121 C 8768801C 009 3/9/2023 5352 INSPECTION OF CONCRETE PLANTS CA-XR031N1062306703656 $21.97 000001080990-3562500640
2023 9 FD52 00 E121 C 8768801C 009 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703656 $0.85 000001080990-3562500640
2023 9 FD52 00 E122 C 8768801C 009 3/9/2023 5352 INSPECTION OF CONCRETE PLANTS CA-XR031N1062306703656 $223.75 000001080990-3562500640
2023 9 FD52 00 E122 C 8768801C 009 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703656 $8.66 000001080990-3562500640
2023 9 FD52 00 E123 C 8768801C 009 3/9/2023 5352 INSPECTION OF CONCRETE PLANTS CA-XR031N1062306703656 $10.25 000001080990-3562500640
2023 9 FD52 00 E123 C 8768801C 009 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703656 $0.38 000001080990-3562500640
2023 9 FD52 07 E797 C 8768801C 009 3/1/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P028K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $71,655.51
2023 9 FD52 07 E111 C 8768801C 009 3/1/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR022N1062305302448 $3,303.22 000001082265-3562507210
2023 9 FD52 07 E111 C 8768801C 009 3/1/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302448 $338.25 000001082265-3562507210
2023 9 FD52 07 E121 C 8768801C 009 3/1/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR022N1062305302448 $233.93 000001082265-3562507210
2023 9 FD52 07 E121 C 8768801C 009 3/1/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302448 $23.96 000001082265-3562507210
2023 9 FD52 07 E122 C 8768801C 009 3/1/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR022N1062305302448 $2,576.52 000001082265-3562507210
2023 9 FD52 07 E122 C 8768801C 009 3/1/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302448 $263.83 000001082265-3562507210
2023 9 FD52 07 E123 C 8768801C 009 3/1/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR022N1062305302448 $668.59 000001082265-3562507210
2023 9 FD52 07 E123 C 8768801C 009 3/1/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302448 $67.53 000001082265-3562507210
2023 9 FD52 07 E124 C 8768801C 009 3/1/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR022N1062305302448 $1.55 000001082265-3562507210
2023 9 FD52 07 E124 C 8768801C 009 3/1/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302448 $0.15 000001082265-3562507210
2023 8 FD52 00 E229 C 8768801C 009 2/27/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523056003790 $15.17
2023 8 FD52 00 E111 C 8768801C 009 2/23/2023 5352 INSPECTION OF CONCRETE PLANTS CA-XR022N1062305302442 $493.43 000001080990-3562500640
2023 8 FD52 00 E111 C 8768801C 009 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302442 $81.05 000001080990-3562500640
2023 8 FD52 00 E121 C 8768801C 009 2/23/2023 5352 INSPECTION OF CONCRETE PLANTS CA-XR022N1062305302442 $37.44 000001080990-3562500640
2023 8 FD52 00 E121 C 8768801C 009 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302442 $6.13 000001080990-3562500640
2023 8 FD52 00 E122 C 8768801C 009 2/23/2023 5352 INSPECTION OF CONCRETE PLANTS CA-XR022N1062305302442 $384.86 000001080990-3562500640
2023 8 FD52 00 E122 C 8768801C 009 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302442 $63.22 000001080990-3562500640
2023 8 FD52 00 E123 C 8768801C 009 2/23/2023 5352 INSPECTION OF CONCRETE PLANTS CA-XR022N1062305302442 $42.86 000001080990-3562500640
2023 8 FD52 00 E123 C 8768801C 009 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302442 $8.34 000001080990-3562500640
2023 8 FD52 00 E124 C 8768801C 009 2/23/2023 5352 INSPECTION OF CONCRETE PLANTS CA-XR022N1062305302442 $0.18 000001080990-3562500640
2023 8 FD52 00 E124 C 8768801C 009 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302442 $0.03 000001080990-3562500640
2023 8 FD52 07 E111 C 8768801C 009 2/23/2023 4580 CONSTRUCTION CONTRACTS CA-XR022N1062305302493 $6,634.92 10776817-3562507380
2023 8 FD52 07 E111 C 8768801C 009 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302493 $2,224.70 10776817-3562507380
2023 8 FD52 07 E115 C 8768801C 009 2/23/2023 4580 CONSTRUCTION CONTRACTS CA-XR022N1062305302493 $116.64 10776817-3562507380
2023 8 FD52 07 E121 C 8768801C 009 2/23/2023 4580 CONSTRUCTION CONTRACTS CA-XR022N1062305302493 $505.02 10776817-3562507380
2023 8 FD52 07 E121 C 8768801C 009 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302493 $161.46 10776817-3562507380
2023 8 FD52 07 E122 C 8768801C 009 2/23/2023 4580 CONSTRUCTION CONTRACTS CA-XR022N1062305302493 $5,266.19 10776817-3562507380
2023 8 FD52 07 E122 C 8768801C 009 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302493 $1,735.27 10776817-3562507380
2023 8 FD52 07 E123 C 8768801C 009 2/23/2023 4580 CONSTRUCTION CONTRACTS CA-XR022N1062305302493 $829.14 10776817-3562507380
2023 8 FD52 07 E123 C 8768801C 009 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302493 $366.67 10776817-3562507380
2023 8 FD52 07 E124 C 8768801C 009 2/23/2023 4580 CONSTRUCTION CONTRACTS CA-XR022N1062305302493 $2.64 10776817-3562507380
2023 8 FD52 07 E124 C 8768801C 009 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302493 $0.95 10776817-3562507380
2023 8 FD52 07 E797 C 8768801C 009 2/15/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P027K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $177,528.84
2023 8 FD52 07 E111 C 8768801C 009 2/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901420 $410.33 000001082265-3562507210
2023 8 FD52 07 E121 C 8768801C 009 2/15/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR021N1062303901420 $304.87 000001082265-3562507210
2023 8 FD52 07 E121 C 8768801C 009 2/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901420 $29.36 000001082265-3562507210
2023 8 FD52 07 E122 C 8768801C 009 2/15/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR021N1062303901420 $3,314.31 000001082265-3562507210
2023 8 FD52 07 E122 C 8768801C 009 2/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901420 $320.06 000001082265-3562507210
2023 8 FD52 07 E123 C 8768801C 009 2/15/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR021N1062303901420 $771.59 000001082265-3562507210
2023 8 FD52 07 E123 C 8768801C 009 2/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901420 $74.29 000001082265-3562507210
2023 8 FD52 07 E111 C 8768801C 009 2/15/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR021N1062303901420 $4,249.11 000001082265-3562507210
2023 8 FD52 00 E229 C 8768801C 009 2/14/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523041005900 $15.17
2023 8 FD52 07 E111 C 8768801C 009 2/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR021N1062303901463 $8,069.15 10776817-3562507380
2023 8 FD52 07 E111 C 8768801C 009 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901463 $1,391.85 10776817-3562507380
2023 8 FD52 07 E115 C 8768801C 009 2/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR021N1062303901463 $190.03 10776817-3562507380
2023 8 FD52 07 E116 C 8768801C 009 2/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR021N1062303901463 $26.25 10776817-3562507380
2023 8 FD52 07 E121 C 8768801C 009 2/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR021N1062303901463 $610.96 10776817-3562507380
2023 8 FD52 07 E121 C 8768801C 009 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901463 $102.87 10776817-3562507380
2023 8 FD52 07 E122 C 8768801C 009 2/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR021N1062303901463 $6,462.63 10776817-3562507380
2023 8 FD52 07 E122 C 8768801C 009 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901463 $1,085.65 10776817-3562507380
2023 8 FD52 07 E123 C 8768801C 009 2/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR021N1062303901463 $1,082.85 10776817-3562507380
2023 8 FD52 07 E123 C 8768801C 009 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901463 $188.41 10776817-3562507380
2023 8 FD52 00 E111 C 8768801C 009 2/9/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR021N1062303901417 $205.23 000001081807-3562500640
2023 8 FD52 00 E111 C 8768801C 009 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901417 $31.45 000001081807-3562500640
2023 8 FD52 00 E121 C 8768801C 009 2/9/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR021N1062303901417 $15.04 000001081807-3562500640
2023 8 FD52 00 E121 C 8768801C 009 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901417 $2.30 000001081807-3562500640
2023 8 FD52 00 E122 C 8768801C 009 2/9/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR021N1062303901417 $160.23 000001081807-3562500640
2023 8 FD52 00 E122 C 8768801C 009 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901417 $24.53 000001081807-3562500640
2023 8 FD52 00 E123 C 8768801C 009 2/9/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR021N1062303901417 $34.28 000001081807-3562500640
2023 8 FD52 00 E123 C 8768801C 009 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901417 $5.17 000001081807-3562500640
2023 8 FD52 07 E797 C 8768801C 009 2/2/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P026K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $74,218.51
2023 7 FD52 07 E111 C 8768801C 009 1/27/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR012N1062302300419 $4,286.64 000001082265-3562507210
2023 7 FD52 07 E111 C 8768801C 009 1/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300419 $476.30 000001082265-3562507210
2023 7 FD52 07 E121 C 8768801C 009 1/27/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR012N1062302300419 $308.94 000001082265-3562507210
2023 7 FD52 07 E121 C 8768801C 009 1/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300419 $34.33 000001082265-3562507210
2023 7 FD52 07 E122 C 8768801C 009 1/27/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR012N1062302300419 $3,343.58 000001082265-3562507210
2023 7 FD52 07 E122 C 8768801C 009 1/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300419 $371.52 000001082265-3562507210
2023 7 FD52 07 E123 C 8768801C 009 1/27/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR012N1062302300419 $760.66 000001082265-3562507210
2023 7 FD52 07 E123 C 8768801C 009 1/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300419 $83.39 000001082265-3562507210
2023 7 FD52 07 E124 C 8768801C 009 1/27/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR012N1062302300419 $1.80 000001082265-3562507210
2023 7 FD52 07 E124 C 8768801C 009 1/27/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300419 $0.20 000001082265-3562507210
2023 7 FD52 00 E229 C 8768801C 009 1/26/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523025004380 $15.17
2023 7 FD52 07 E111 C 8768801C 009 1/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR012N1062302300462 $7,649.41 10776817-3562507380
2023 7 FD52 07 E111 C 8768801C 009 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300462 $3,408.60 10776817-3562507380
2023 7 FD52 07 E116 C 8768801C 009 1/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR012N1062302300462 $10.50 10776817-3562507380
2023 7 FD52 07 E121 C 8768801C 009 1/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR012N1062302300462 $568.34 10776817-3562507380
2023 7 FD52 07 E121 C 8768801C 009 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300462 $255.08 10776817-3562507380
2023 7 FD52 07 E122 C 8768801C 009 1/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR012N1062302300462 $5,974.75 10776817-3562507200
2023 7 FD52 07 E122 C 8768801C 009 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300462 $2,658.70 10776817-3562507380
2023 7 FD52 07 E123 C 8768801C 009 1/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR012N1062302300462 $994.31 10776817-3562507200
2023 7 FD52 07 E123 C 8768801C 009 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300462 $317.53 10776817-3562507380
2023 7 FD52 07 E124 C 8768801C 009 1/24/2023 4580 CONSTRUCTION CONTRACTS CA-XR012N1062302300462 $3.17 10776817-3562507200
2023 7 FD52 07 E124 C 8768801C 009 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300462 $1.47 10776817-3562507380
2023 7 FD52 07 E797 C 8768801C 009 1/19/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P025K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $120,787.23
2023 7 FD52 07 E111 C 8768801C 009 1/12/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR011N1062300610253 $3,377.89 000001082265-3562507210
2023 7 FD52 07 E111 C 8768801C 009 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610253 $3,035.93 000001082265-3562507210
2023 7 FD52 07 E121 C 8768801C 009 1/12/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR011N1062300610253 $248.73 000001082265-3562507210
2023 7 FD52 07 E121 C 8768801C 009 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610253 $223.93 000001082265-3562507210
2023 7 FD52 07 E122 C 8768801C 009 1/12/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR011N1062300610253 $2,634.76 000001082265-3562507210
2023 7 FD52 07 E122 C 8768801C 009 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610253 $2,368.02 000001082265-3562507210
2023 7 FD52 07 E123 C 8768801C 009 1/12/2023 5182 INSP-MISCELLANEOUS MATERIALS CA-XR011N1062300610253 $497.29 000001082265-3562507210
2023 7 FD52 07 E123 C 8768801C 009 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610253 $428.74 000001082265-3562507210
2023 7 FD52 00 E121 C 8768801C 009 1/12/2023 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR011N1062300610251 $0.02 000001081807-3562500640
2023 7 FD52 00 E229 C 8768801C 009 1/11/2023 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162523010003810 $15.17
2023 7 FD52 07 E797 C 8768801C 009 1/9/2023 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P024K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $126,857.92
2023 7 FD52 07 E111 C 8768801C 009 1/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR011N1062300610280 $2,311.58 10776817-3562507380
2023 7 FD52 07 E111 C 8768801C 009 1/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610280 $5,776.41 10776817-3562507200
2023 7 FD52 07 E115 C 8768801C 009 1/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR011N1062300610280 $252.76 10776817-3562507380
2023 7 FD52 07 E116 C 8768801C 009 1/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR011N1062300610280 $3.00 10776817-3562507380
2023 7 FD52 07 E121 C 8768801C 009 1/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR011N1062300610280 $194.36 10776817-3562507380
2023 7 FD52 07 E121 C 8768801C 009 1/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610280 $429.25 10776817-3562507380
2023 7 FD52 07 E122 C 8768801C 009 1/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR011N1062300610280 $2,002.52 10776817-3562507380
2023 7 FD52 07 E122 C 8768801C 009 1/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610280 $4,505.61 10776817-3562507380
2023 7 FD52 07 E123 C 8768801C 009 1/9/2023 4580 CONSTRUCTION CONTRACTS CA-XR011N1062300610280 $170.00 10776817-3562507380
2023 7 FD52 07 E123 C 8768801C 009 1/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610280 $677.61 10776817-3562507200
2023 6 FD52 00 E229 C 8768801C 009 12/27/2022 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162522359003920 $15.17
2023 6 FD52 07 E111 C 8768801C 009 12/27/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR122M1062235509166 $4,016.09 000001082265-3562507210
2023 6 FD52 07 E111 C 8768801C 009 12/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509166 $1,158.98 000001082265-3562507210
2023 6 FD52 07 E121 C 8768801C 009 12/27/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR122M1062235509166 $296.12 000001082265-3562507210
2023 6 FD52 07 E121 C 8768801C 009 12/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509166 $87.33 000001082265-3562507210
2023 6 FD52 07 E122 C 8768801C 009 12/27/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR122M1062235509166 $3,132.44 000001082265-3562507210
2023 6 FD52 07 E122 C 8768801C 009 12/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509166 $904.00 000001082265-3562507210
2023 6 FD52 07 E123 C 8768801C 009 12/27/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR122M1062235509166 $564.90 000001082265-3562507210
2023 6 FD52 07 E123 C 8768801C 009 12/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509166 $127.31 000001082265-3562507210
2023 6 FD52 07 E124 C 8768801C 009 12/27/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR122M1062235509166 $1.55 000001082265-3562507210
2023 6 FD52 07 E124 C 8768801C 009 12/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509166 $0.36 000001082265-3562507210
2023 6 FD52 07 E111 C 8768801C 009 12/22/2022 4580 CONSTRUCTION CONTRACTS CA-XR122M1062235509205 $10,565.22 10776817-3562507380
2023 6 FD52 07 E111 C 8768801C 009 12/22/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509205 $784.02 10776817-3562507380
2023 6 FD52 07 E115 C 8768801C 009 12/22/2022 4580 CONSTRUCTION CONTRACTS CA-XR122M1062235509205 $1,019.21 10776817-3562507380
2023 6 FD52 07 E116 C 8768801C 009 12/22/2022 4580 CONSTRUCTION CONTRACTS CA-XR122M1062235509205 $12.00 10776817-3562507380
2023 6 FD52 07 E121 C 8768801C 009 12/22/2022 4580 CONSTRUCTION CONTRACTS CA-XR122M1062235509205 $868.81 10776817-3562507200
2023 6 FD52 07 E121 C 8768801C 009 12/22/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509205 $59.62 10776817-3562507380
2023 6 FD52 07 E122 C 8768801C 009 12/22/2022 4580 CONSTRUCTION CONTRACTS CA-XR122M1062235509205 $9,045.21 10776817-3562507380
2023 6 FD52 07 E122 C 8768801C 009 12/22/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509205 $611.54 10776817-3562507380
2023 6 FD52 07 E123 C 8768801C 009 12/22/2022 4580 CONSTRUCTION CONTRACTS CA-XR122M1062235509205 $1,204.54 10776817-3562507380
2023 6 FD52 07 E123 C 8768801C 009 12/22/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509205 $62.23 10776817-3562507200
2023 6 FD52 07 E124 C 8768801C 009 12/22/2022 4580 CONSTRUCTION CONTRACTS CA-XR122M1062235509205 $4.31 10776817-3562507380
2023 6 FD52 07 E124 C 8768801C 009 12/22/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509205 $0.33 10776817-3562507200
2023 6 FD52 00 E111 C 8768801C 009 12/22/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR122M1062235509163 $671.36 000001081807-3562500640
2023 6 FD52 00 E115 C 8768801C 009 12/22/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR122M1062235509163 $136.34 000001081807-3562500640
2023 6 FD52 00 E121 C 8768801C 009 12/22/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR122M1062235509163 $59.69 000001081807-3562500640
2023 6 FD52 00 E122 C 8768801C 009 12/22/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR122M1062235509163 $630.00 000001081807-3562500640
2023 6 FD52 00 E123 C 8768801C 009 12/22/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR122M1062235509163 $104.10 000001081807-3562500640
2023 6 FD52 00 E124 C 8768801C 009 12/22/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR122M1062235509163 $0.27 000001081807-3562500640
2023 6 FD52 07 E797 C 8768801C 009 12/21/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P023K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $462,785.82
2023 6 FD52 07 E111 C 8768801C 009 12/15/2022 4580 CONSTRUCTION CONTRACTS CA-XR121M1062234208247 $8,437.02 10776817-3562507380
2023 6 FD52 07 E111 C 8768801C 009 12/15/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208247 $3,649.44 10776817-3562507380
2023 6 FD52 07 E115 C 8768801C 009 12/15/2022 4580 CONSTRUCTION CONTRACTS CA-XR121M1062234208247 $218.92 10776817-3562507380
2023 6 FD52 07 E116 C 8768801C 009 12/15/2022 4580 CONSTRUCTION CONTRACTS CA-XR121M1062234208247 $4.50 10776817-3562507380
2023 6 FD52 07 E121 C 8768801C 009 12/15/2022 4580 CONSTRUCTION CONTRACTS CA-XR121M1062234208247 $646.47 10776817-3562507380
2023 6 FD52 07 E121 C 8768801C 009 12/15/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208247 $271.53 10776817-3562507380
2023 6 FD52 07 E122 C 8768801C 009 12/15/2022 4580 CONSTRUCTION CONTRACTS CA-XR121M1062234208247 $6,755.15 10776817-3562507380
2023 6 FD52 07 E122 C 8768801C 009 12/15/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208247 $2,846.57 10776817-3562507380
2023 6 FD52 07 E123 C 8768801C 009 12/15/2022 4580 CONSTRUCTION CONTRACTS CA-XR121M1062234208247 $936.81 10776817-3562507380
2023 6 FD52 07 E123 C 8768801C 009 12/15/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208247 $422.83 10776817-3562507380
2023 6 FD52 07 E111 C 8768801C 009 12/14/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR121M1062234208213 $1,181.30 000001082265-3562507210
2023 6 FD52 07 E111 C 8768801C 009 12/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208213 $504.69 000001082265-3562507210
2023 6 FD52 07 E121 C 8768801C 009 12/14/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR121M1062234208213 $87.31 000001082265-3562507210
2023 6 FD52 07 E121 C 8768801C 009 12/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208213 $37.38 000001082265-3562507210
2023 6 FD52 07 E122 C 8768801C 009 12/14/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR121M1062234208213 $921.43 000001082265-3562507210
2023 6 FD52 07 E122 C 8768801C 009 12/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208213 $393.66 000001082265-3562507210
2023 6 FD52 07 E123 C 8768801C 009 12/14/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR121M1062234208213 $159.14 000001082265-3562507210
2023 6 FD52 07 E123 C 8768801C 009 12/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208213 $64.65 000001082265-3562507210
2023 6 FD52 00 E229 C 8768801C 009 12/13/2022 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162522344004570 $15.17
2023 6 FD52 07 E111 C 8768801C 009 12/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR121M1062234208208 $147.68 000001081053-3562500680
2023 6 FD52 07 E111 C 8768801C 009 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208208 $32.92 000001081053-3562500680
2023 6 FD52 00 E115 C 8768801C 009 12/12/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR121M1062234208224 $92.32 000001084244-3562500610
2023 6 FD52 00 E121 C 8768801C 009 12/12/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR121M1062234208224 $6.34 000001084244-3562500610
2023 6 FD52 00 E122 C 8768801C 009 12/12/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR121M1062234208224 $71.98 000001084244-3562500610
2023 6 FD52 07 E121 C 8768801C 009 12/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR121M1062234208208 $10.67 000001081053-3562500680
2023 6 FD52 07 E121 C 8768801C 009 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208208 $2.38 000001081053-3562500680
2023 6 FD52 07 E122 C 8768801C 009 12/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR121M1062234208208 $115.23 000001081053-3562500680
2023 6 FD52 07 E122 C 8768801C 009 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208208 $25.68 000001081053-3562500680
2023 6 FD52 07 E123 C 8768801C 009 12/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR121M1062234208208 $15.95 000001081053-3562500680
2023 6 FD52 07 E123 C 8768801C 009 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208208 $3.50 000001081053-3562500680
2023 6 FD52 07 E797 C 8768801C 009 12/7/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P022K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $595,262.85
2023 6 FD52 07 E797 C 8768801C 009 12/1/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P021K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $470,951.59
2023 5 FD52 00 E229 C 8768801C 009 11/30/2022 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162522329003190 $15.17
2023 5 FD52 07 E111 C 8768801C 009 11/23/2022 4010 CONSTRUCTION ENGINEERING CA-XR112M1062232607149 $220.00 000001081053-3562500680
2023 5 FD52 07 E111 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607149 $43.48 000001081053-3562500680
2023 5 FD52 07 E121 C 8768801C 009 11/23/2022 4010 CONSTRUCTION ENGINEERING CA-XR112M1062232607149 $16.22 000001081053-3562500620
2023 5 FD52 07 E121 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607149 $3.20 000001081053-3562500620
2023 5 FD52 07 E122 C 8768801C 009 11/23/2022 4010 CONSTRUCTION ENGINEERING CA-XR112M1062232607149 $171.57 000001081053-3562500620
2023 5 FD52 07 E122 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607149 $33.91 000001081053-3562500620
2023 5 FD52 07 E123 C 8768801C 009 11/23/2022 4010 CONSTRUCTION ENGINEERING CA-XR112M1062232607149 $28.42 000001081053-3562500620
2023 5 FD52 07 E123 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607149 $5.37 000001081053-3562500620
2023 5 FD52 00 E111 C 8768801C 009 11/23/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR112M1062232607172 $223.78 000001084244-3562500610
2023 5 FD52 07 E124 C 8768801C 009 11/23/2022 4010 CONSTRUCTION ENGINEERING CA-XR112M1062232607149 $0.08 000001081053-3562500680
2023 5 FD52 00 E111 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607172 $86.54 000001084244-3562500610
2023 5 FD52 00 E121 C 8768801C 009 11/23/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR112M1062232607172 $16.52 000001084244-3562500610
2023 5 FD52 00 E121 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607172 $6.39 000001084244-3562500610
2023 5 FD52 00 E122 C 8768801C 009 11/23/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR112M1062232607172 $174.56 000001084244-3562500610
2023 5 FD52 00 E122 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607172 $67.50 000001084244-3562500610
2023 5 FD52 00 E123 C 8768801C 009 11/23/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR112M1062232607172 $35.15 000001084244-3562500610
2023 5 FD52 00 E123 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607172 $13.34 000001084244-3562500610
2023 5 FD52 00 E124 C 8768801C 009 11/23/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR112M1062232607172 $0.09 000001084244-3562500610
2023 5 FD52 00 E124 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607172 $0.03 000001084244-3562500610
2023 5 FD52 07 E111 C 8768801C 009 11/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR112M1062232607206 $7,703.44 10776817-3562507380
2023 5 FD52 07 E111 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607206 $2,953.00 10776817-3562507380
2023 5 FD52 07 E115 C 8768801C 009 11/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR112M1062232607206 $994.24 10776817-3562507380
2023 5 FD52 07 E116 C 8768801C 009 11/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR112M1062232607206 $89.25 10776817-3562507380
2023 5 FD52 07 E121 C 8768801C 009 11/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR112M1062232607206 $656.95 10776817-3562507380
2023 5 FD52 07 E121 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607206 $222.56 10776817-3562507200
2023 5 FD52 07 E122 C 8768801C 009 11/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR112M1062232607206 $6,853.80 10776817-3562507200
2023 5 FD52 07 E122 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607206 $2,303.36 10776817-3562507380
2023 5 FD52 07 E123 C 8768801C 009 11/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR112M1062232607206 $850.69 10776817-3562507380
2023 5 FD52 07 E123 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607206 $256.01 10776817-3562507380
2023 5 FD52 07 E124 C 8768801C 009 11/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR112M1062232607206 $2.63 10776817-3562507200
2023 5 FD52 07 E124 C 8768801C 009 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607206 $0.94 10776817-3562507200
2023 5 FD52 00 E229 C 8768801C 009 11/14/2022 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162522314005910 $15.17
2023 5 FD52 07 E797 C 8768801C 009 11/9/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P020K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $296,823.64
2023 5 FD52 00 E111 C 8768801C 009 11/7/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR111M1062230806172 $660.55 000001084244-3562500610
2023 5 FD52 00 E121 C 8768801C 009 11/7/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR111M1062230806172 $48.53 000001084244-3562500610
2023 5 FD52 00 E122 C 8768801C 009 11/7/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR111M1062230806172 $515.23 000001084244-3562500610
2023 5 FD52 00 E123 C 8768801C 009 11/7/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR111M1062230806172 $104.92 000001084244-3562500610
2023 5 FD52 07 E111 C 8768801C 009 11/7/2022 4580 CONSTRUCTION CONTRACTS CA-XR111M1062230806197 $10,160.35 10776817-3562507380
2023 5 FD52 07 E111 C 8768801C 009 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806197 $1,681.21 10776817-3562507380
2023 5 FD52 07 E115 C 8768801C 009 11/7/2022 4580 CONSTRUCTION CONTRACTS CA-XR111M1062230806197 $1,212.99 10776817-3562507380
2023 5 FD52 07 E116 C 8768801C 009 11/7/2022 4580 CONSTRUCTION CONTRACTS CA-XR111M1062230806197 $36.00 10776817-3562507380
2023 5 FD52 07 E121 C 8768801C 009 11/7/2022 4580 CONSTRUCTION CONTRACTS CA-XR111M1062230806197 $851.77 10776817-3562507380
2023 5 FD52 07 E121 C 8768801C 009 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806197 $128.14 10776817-3562507380
2023 5 FD52 07 E122 C 8768801C 009 11/7/2022 4580 CONSTRUCTION CONTRACTS CA-XR111M1062230806197 $8,899.29 10776817-3562507380
2023 5 FD52 07 E122 C 8768801C 009 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806197 $1,311.35 10776817-3562507380
2023 5 FD52 07 E123 C 8768801C 009 11/7/2022 4580 CONSTRUCTION CONTRACTS CA-XR111M1062230806197 $1,368.38 10776817-3562507200
2023 5 FD52 07 E123 C 8768801C 009 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806197 $79.35 10776817-3562507200
2023 4 FD52 07 E111 C 8768801C 009 10/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR102M1062229405053 $238.15 000001082265-3562507210
2023 4 FD52 07 E115 C 8768801C 009 10/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR102M1062229405053 $791.37 000001082265-3562507210
2023 4 FD52 07 E121 C 8768801C 009 10/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR102M1062229405053 $77.29 000001082265-3562507210
2023 4 FD52 07 E121 C 8768801C 009 10/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405053 $0.02 000001082265-3562507210
2023 4 FD52 07 E122 C 8768801C 009 10/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR102M1062229405053 $803.02 000001082265-3562507210
2023 4 FD52 07 E123 C 8768801C 009 10/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR102M1062229405053 $34.66 000001082265-3562507210
2023 4 FD52 07 E124 C 8768801C 009 10/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR102M1062229405053 $0.10 000001082265-3562507210
2023 4 FD52 00 E229 C 8768801C 009 10/27/2022 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162522298005900 $15.17
2023 4 FD52 07 E797 C 8768801C 009 10/27/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P019K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $641,079.41
2023 4 FD52 07 E111 C 8768801C 009 10/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR102M1062229405097 $5,644.65 10776817-3562507200
2023 4 FD52 07 E111 C 8768801C 009 10/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405097 $1,287.77 10776817-3562507380
2023 4 FD52 07 E115 C 8768801C 009 10/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR102M1062229405097 $1,940.16 10776817-3562507380
2023 4 FD52 07 E116 C 8768801C 009 10/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR102M1062229405097 $160.50 10776817-3562507380
2023 4 FD52 07 E121 C 8768801C 009 10/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR102M1062229405097 $572.26 10776817-3562507380
2023 4 FD52 07 E121 C 8768801C 009 10/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405097 $97.45 10776817-3562507380
2023 4 FD52 07 E122 C 8768801C 009 10/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR102M1062229405097 $6,041.33 10776817-3562507380
2023 4 FD52 07 E122 C 8768801C 009 10/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405097 $1,004.47 10776817-3562507380
2023 4 FD52 07 E123 C 8768801C 009 10/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR102M1062229405097 $837.54 10776817-3562507200
2023 4 FD52 07 E123 C 8768801C 009 10/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405097 $87.64 10776817-3562507380
2023 4 FD52 07 E124 C 8768801C 009 10/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR102M1062229405097 $2.21 10776817-3562507200
2023 4 FD52 07 E124 C 8768801C 009 10/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405097 $0.59 10776817-3562507380
2023 4 FD52 07 E111 C 8768801C 009 10/17/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR101M1062228003941 $865.99 000001082265-3562507210
2023 4 FD52 07 E111 C 8768801C 009 10/17/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003941 $38.39 000001082265-3562507210
2023 4 FD52 07 E121 C 8768801C 009 10/17/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR101M1062228003941 $63.94 000001082265-3562507210
2023 4 FD52 07 E121 C 8768801C 009 10/17/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003941 $2.84 000001082265-3562507210
2023 4 FD52 07 E122 C 8768801C 009 10/17/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR101M1062228003941 $675.47 000001082265-3562507210
2023 4 FD52 07 E122 C 8768801C 009 10/17/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003941 $29.94 000001082265-3562507210
2023 4 FD52 07 E123 C 8768801C 009 10/17/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR101M1062228003941 $126.13 000001082265-3562507210
2023 4 FD52 07 E123 C 8768801C 009 10/17/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003941 $5.51 000001082265-3562507210
2023 4 FD52 07 E797 C 8768801C 009 10/13/2022 4580 CONSTRUCTION CONTRACTS PRC-2300044628 PON22200004165 VAUGHN AND MELTON $3,442.50 SW HWY & Bridge Construction Inspection Region 1
2023 4 FD52 00 E229 C 8768801C 009 10/12/2022 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162522283005460 $15.17
2023 4 FD52 07 E797 C 8768801C 009 10/12/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P018K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $689,402.65
2023 4 FD52 07 E111 C 8768801C 009 10/10/2022 4580 CONSTRUCTION CONTRACTS CA-XR101M1062228003982 $6,427.06 10776817-3562507380
2023 4 FD52 07 E111 C 8768801C 009 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003982 $1,368.58 10776817-3562507200
2023 4 FD52 07 E115 C 8768801C 009 10/10/2022 4580 CONSTRUCTION CONTRACTS CA-XR101M1062228003982 $673.88 10776817-3562507380
2023 4 FD52 07 E116 C 8768801C 009 10/10/2022 4580 CONSTRUCTION CONTRACTS CA-XR101M1062228003982 $30.00 10776817-3562507380
2023 4 FD52 07 E121 C 8768801C 009 10/10/2022 4580 CONSTRUCTION CONTRACTS CA-XR101M1062228003982 $532.51 10776817-3562507380
2023 4 FD52 07 E121 C 8768801C 009 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003982 $102.15 10776817-3562507380
2023 4 FD52 07 E122 C 8768801C 009 10/10/2022 4580 CONSTRUCTION CONTRACTS CA-XR101M1062228003982 $5,562.12 10776817-3562507380
2023 4 FD52 07 E122 C 8768801C 009 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003982 $1,067.50 10776817-3562507380
2023 4 FD52 07 E123 C 8768801C 009 10/10/2022 4580 CONSTRUCTION CONTRACTS CA-XR101M1062228003982 $717.38 10776817-3562507380
2023 4 FD52 07 E123 C 8768801C 009 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003982 $165.24 10776817-3562507200
2023 4 FD52 00 E111 C 8768801C 009 10/10/2022 5352 INSPECTION OF CONCRETE PLANTS CA-XR101M1062228003935 $440.36 000001080990-3562500640
2023 4 FD52 00 E121 C 8768801C 009 10/10/2022 5352 INSPECTION OF CONCRETE PLANTS CA-XR101M1062228003935 $33.69 000001080990-3562500640
2023 4 FD52 00 E122 C 8768801C 009 10/10/2022 5352 INSPECTION OF CONCRETE PLANTS CA-XR101M1062228003935 $343.48 000001080990-3562500640
2023 4 FD52 00 E123 C 8768801C 009 10/10/2022 5352 INSPECTION OF CONCRETE PLANTS CA-XR101M1062228003935 $16.84 000001080990-3562500640
2023 3 FD52 00 E229 C 8768801C 009 9/29/2022 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162522268004960 $15.17
2023 3 FD52 07 E797 C 8768801C 009 9/28/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P017K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $315,272.28
2023 3 FD52 07 E111 C 8768801C 009 9/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR092M1062226602775 $1,891.88 000001082265-3562507210
2023 3 FD52 07 E111 C 8768801C 009 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602775 $189.19 000001082265-3562507210
2023 3 FD52 07 E121 C 8768801C 009 9/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR092M1062226602775 $143.61 000001082265-3562507210
2023 3 FD52 07 E121 C 8768801C 009 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602775 $14.36 000001082265-3562507210
2023 3 FD52 07 E122 C 8768801C 009 9/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR092M1062226602775 $1,475.67 000001082265-3562507210
2023 3 FD52 07 E122 C 8768801C 009 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602775 $147.57 000001082265-3562507210
2023 3 FD52 07 E123 C 8768801C 009 9/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR092M1062226602775 $193.11 000001082265-3562507210
2023 3 FD52 07 E123 C 8768801C 009 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602775 $19.00 000001082265-3562507210
2023 3 FD52 07 E124 C 8768801C 009 9/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR092M1062226602775 $0.55 000001082265-3562507210
2023 3 FD52 07 E124 C 8768801C 009 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602775 $0.05 000001082265-3562507210
2023 3 FD52 07 E121 C 8768801C 009 9/26/2022 4580 CONSTRUCTION CONTRACTS CA-XR092M1062226602823 $474.25 10776817-3562507380
2023 3 FD52 07 E121 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602823 $64.14 10776817-3562507200
2023 3 FD52 07 E122 C 8768801C 009 9/26/2022 4580 CONSTRUCTION CONTRACTS CA-XR092M1062226602823 $4,932.41 10776817-3562507380
2023 3 FD52 07 E122 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602823 $670.66 10776817-3562507380
2023 3 FD52 07 E123 C 8768801C 009 9/26/2022 4580 CONSTRUCTION CONTRACTS CA-XR092M1062226602823 $668.87 10776817-3562507380
2023 3 FD52 07 E123 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602823 $103.92 10776817-3562507380
2023 3 FD52 07 E124 C 8768801C 009 9/26/2022 4580 CONSTRUCTION CONTRACTS CA-XR092M1062226602823 $2.37 10776817-3562507200
2023 3 FD52 07 E124 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602823 $0.33 10776817-3562507200
2023 3 FD52 00 E111 C 8768801C 009 9/26/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR092M1062226602794 $220.18 000001084244-3562500610
2023 3 FD52 00 E111 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602794 $75.15 000001084244-3562500610
2023 3 FD52 00 E121 C 8768801C 009 9/26/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR092M1062226602794 $16.37 000001084244-3562500610
2023 3 FD52 00 E121 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602794 $5.59 000001084244-3562500610
2023 3 FD52 00 E122 C 8768801C 009 9/26/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR092M1062226602794 $171.75 000001084244-3562500610
2023 3 FD52 00 E122 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602794 $58.61 000001084244-3562500610
2023 3 FD52 00 E123 C 8768801C 009 9/26/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR092M1062226602794 $41.50 000001084244-3562500610
2023 3 FD52 00 E123 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602794 $13.95 000001084244-3562500610
2023 3 FD52 00 E124 C 8768801C 009 9/26/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR092M1062226602794 $0.10 000001084244-3562500610
2023 3 FD52 00 E124 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602794 $0.03 000001084244-3562500610
2023 3 FD52 07 E111 C 8768801C 009 9/26/2022 4580 CONSTRUCTION CONTRACTS CA-XR092M1062226602823 $6,165.21 10776817-3562507380
2023 3 FD52 07 E111 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602823 $859.82 10776817-3562507380
2023 3 FD52 07 E111 C 8768801C 009 9/26/2022 4010 CONSTRUCTION ENGINEERING CA-XR092M1062226602767 $265.86 000001081053-3562500680
2023 3 FD52 07 E111 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602767 $26.58 000001081053-3562500680
2023 3 FD52 07 E121 C 8768801C 009 9/26/2022 4010 CONSTRUCTION ENGINEERING CA-XR092M1062226602767 $20.15 000001081053-3562500680
2023 3 FD52 07 E121 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602767 $2.01 000001081053-3562500680
2023 3 FD52 07 E122 C 8768801C 009 9/26/2022 4010 CONSTRUCTION ENGINEERING CA-XR092M1062226602767 $207.36 000001081053-3562500680
2023 3 FD52 07 E115 C 8768801C 009 9/26/2022 4580 CONSTRUCTION CONTRACTS CA-XR092M1062226602823 $132.73 10776817-3562507380
2023 3 FD52 07 E122 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602767 $20.73 000001081053-3562500680
2023 3 FD52 07 E123 C 8768801C 009 9/26/2022 4010 CONSTRUCTION ENGINEERING CA-XR092M1062226602767 $32.18 000001081053-3562500680
2023 3 FD52 07 E123 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602767 $3.17 000001081053-3562500680
2023 3 FD52 07 E124 C 8768801C 009 9/26/2022 4010 CONSTRUCTION ENGINEERING CA-XR092M1062226602767 $0.09 000001081053-3562500680
2023 3 FD52 07 E124 C 8768801C 009 9/26/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602767 $0.01 000001081053-3562500680
2023 3 FD52 07 E116 C 8768801C 009 9/26/2022 4580 CONSTRUCTION CONTRACTS CA-XR092M1062226602823 $25.50 10776817-3562507380
2023 3 FD52 07 E797 C 8768801C 009 9/16/2022 4580 CONSTRUCTION CONTRACTS PRC-2300031659 PON22200004165 VAUGHN AND MELTON $6,345.00 SW HWY & Bridge Construction Inspection Region 1
2023 3 FD52 00 E229 C 8768801C 009 9/14/2022 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162522253004630 $15.17
2023 3 FD52 07 E797 C 8768801C 009 9/14/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P016K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $401,908.31
2023 3 FD52 07 E111 C 8768801C 009 9/14/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR091M1062225101627 $1,445.20 000001082265-3562507210
2023 3 FD52 07 E111 C 8768801C 009 9/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101627 $289.04 000001082265-3562507210
2023 3 FD52 07 E121 C 8768801C 009 9/14/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR091M1062225101627 $108.89 000001082265-3562507210
2023 3 FD52 07 E121 C 8768801C 009 9/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101627 $21.78 000001082265-3562507210
2023 3 FD52 07 E122 C 8768801C 009 9/14/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR091M1062225101627 $1,127.24 000001082265-3562507210
2023 3 FD52 07 E122 C 8768801C 009 9/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101627 $225.45 000001082265-3562507210
2023 3 FD52 07 E123 C 8768801C 009 9/14/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR091M1062225101627 $147.70 000001082265-3562507210
2023 3 FD52 07 E123 C 8768801C 009 9/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101627 $29.04 000001082265-3562507210
2023 3 FD52 00 E122 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101648 $41.57 000001084244-3562500610
2023 3 FD52 07 E123 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101668 $32.08 10776817-3562507380
2023 3 FD52 07 E111 C 8768801C 009 9/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR091M1062225101621 $116.10 000001081053-3562500680
2023 3 FD52 07 E111 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101621 $3.48 000001081053-3562500680
2023 3 FD52 07 E121 C 8768801C 009 9/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR091M1062225101621 $8.38 000001081053-3562500680
2023 3 FD52 07 E121 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101621 $0.25 000001081053-3562500680
2023 3 FD52 07 E122 C 8768801C 009 9/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR091M1062225101621 $90.54 000001081053-3562500680
2023 3 FD52 07 E122 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101621 $2.71 000001081053-3562500680
2023 3 FD52 07 E123 C 8768801C 009 9/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR091M1062225101621 $12.50 000001081053-3562500680
2023 3 FD52 07 E123 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101621 $0.37 000001081053-3562500680
2023 3 FD52 00 E123 C 8768801C 009 9/12/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR091M1062225101648 $157.59 000001084244-3562500610
2023 3 FD52 00 E123 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101648 $4.42 000001084244-3562500610
2023 3 FD52 07 E111 C 8768801C 009 9/12/2022 4580 CONSTRUCTION CONTRACTS CA-XR091M1062225101667 $3,780.62 10776817-3562507380
2023 3 FD52 07 E111 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101667 $277.33 10776817-3562507380
2023 3 FD52 07 E115 C 8768801C 009 9/12/2022 4580 CONSTRUCTION CONTRACTS CA-XR091M1062225101667 $777.69 10776817-3562507380
2023 3 FD52 00 E111 C 8768801C 009 9/12/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR091M1062225101647 $1,499.73 000001084244-3562500610
2023 3 FD52 07 E116 C 8768801C 009 9/12/2022 4580 CONSTRUCTION CONTRACTS CA-XR091M1062225101667 $65.25 10776817-3562507380
2023 3 FD52 00 E111 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101647 $53.30 000001084244-3562500610
2023 3 FD52 07 E121 C 8768801C 009 9/12/2022 4580 CONSTRUCTION CONTRACTS CA-XR091M1062225101667 $344.55 10776817-3562507380
2023 3 FD52 00 E115 C 8768801C 009 9/12/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR091M1062225101647 $32.02 000001084244-3562500610
2023 3 FD52 07 E121 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101667 $20.57 10776817-3562507380
2023 3 FD52 00 E121 C 8768801C 009 9/12/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR091M1062225101647 $114.54 000001084244-3562500610
2023 3 FD52 07 E122 C 8768801C 009 9/12/2022 4580 CONSTRUCTION CONTRACTS CA-XR091M1062225101667 $3,606.38 10776817-3562507380
2023 3 FD52 00 E121 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101647 $4.01 000001084244-3562500610
2023 3 FD52 07 E122 C 8768801C 009 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101667 $216.32 10776817-3562507380
2023 3 FD52 00 E122 C 8768801C 009 9/12/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR091M1062225101647 $1,194.70 000001084244-3562500610
2023 3 FD52 07 E123 C 8768801C 009 9/12/2022 4580 CONSTRUCTION CONTRACTS CA-XR091M1062225101667 $431.49 10776817-3562507380
2023 2 FD52 07 E797 C 8768801C 009 8/31/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P015K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $313,456.46
2023 2 FD52 00 E229 C 8768801C 009 8/29/2022 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162522237004260 $15.17
2023 2 FD52 00 E121 C 8768801C 009 8/24/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR082M1062223500435 $26.74 000001081807-3562500640
2023 2 FD52 00 E121 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500435 $3.19 000001081807-3562500640
2023 2 FD52 00 E122 C 8768801C 009 8/24/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR082M1062223500435 $171.74 000001081807-3562500640
2023 2 FD52 00 E122 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500435 $22.44 000001081807-3562500640
2023 2 FD52 00 E123 C 8768801C 009 8/24/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR082M1062223500435 $34.15 000001081807-3562500640
2023 2 FD52 00 E123 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500435 $4.39 000001081807-3562500640
2023 2 FD52 00 E124 C 8768801C 009 8/24/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR082M1062223500435 $0.09 000001081807-3562500640
2023 2 FD52 00 E124 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500435 $0.01 000001081807-3562500640
2023 2 FD52 00 E111 C 8768801C 009 8/24/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR082M1062223500468 $1,295.06 000001084244-3562500610
2023 2 FD52 00 E111 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500468 $29.31 000001084244-3562500610
2023 2 FD52 00 E121 C 8768801C 009 8/24/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR082M1062223500468 $95.85 000001084244-3562500610
2023 2 FD52 00 E121 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500468 $2.24 000001084244-3562500610
2023 2 FD52 00 E122 C 8768801C 009 8/24/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR082M1062223500468 $1,010.14 000001084244-3562500610
2023 2 FD52 00 E122 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500468 $22.86 000001084244-3562500610
2023 2 FD52 00 E123 C 8768801C 009 8/24/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR082M1062223500468 $167.05 000001084244-3562500610
2023 2 FD52 00 E123 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500468 $0.80 000001084244-3562500610
2023 2 FD52 00 E124 C 8768801C 009 8/24/2022 5341 GEOTECHNICAL INVEST (CONST) CA-XR082M1062223500468 $0.50 000001084244-3562500610
2023 2 FD52 00 E124 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500468 $0.01 000001084244-3562500610
2023 2 FD52 07 E111 C 8768801C 009 8/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR082M1062223500476 $1,189.13 10776817-3562507380
2023 2 FD52 07 E111 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500476 $232.76 10776817-3562507380
2023 2 FD52 07 E121 C 8768801C 009 8/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR082M1062223500476 $89.17 10776817-3562507380
2023 2 FD52 07 E121 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500476 $17.46 10776817-3562507380
2023 2 FD52 07 E122 C 8768801C 009 8/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR082M1062223500476 $927.52 10776817-3562507380
2023 2 FD52 07 E122 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500476 $181.55 10776817-3562507380
2023 2 FD52 07 E123 C 8768801C 009 8/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR082M1062223500476 $146.40 10776817-3562507380
2023 2 FD52 07 E123 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500476 $28.22 10776817-3562507380
2023 2 FD52 07 E124 C 8768801C 009 8/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR082M1062223500476 $0.37 10776817-3562507380
2023 2 FD52 07 E124 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500476 $0.07 10776817-3562507380
2023 2 FD52 00 E111 C 8768801C 009 8/24/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR082M1062223500435 $220.11 000001081807-3562500640
2023 2 FD52 00 E111 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500435 $28.77 000001081807-3562500640
2023 2 FD52 00 E112 C 8768801C 009 8/24/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR082M1062223500435 $135.00 000001081807-3562500640
2023 2 FD52 00 E112 C 8768801C 009 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500435 $13.50 000001081807-3562500640
2023 2 FD52 07 E797 C 8768801C 009 8/17/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P014K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $57,629.99
2023 2 FD52 07 E111 C 8768801C 009 8/16/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR081M1062222110124 $693.69 000001082265-3562507210
2023 2 FD52 07 E111 C 8768801C 009 8/16/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110124 $77.23 000001082265-3562507210
2023 2 FD52 07 E121 C 8768801C 009 8/16/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR081M1062222110124 $52.77 000001082265-3562507210
2023 2 FD52 07 E121 C 8768801C 009 8/16/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110124 $5.87 000001082265-3562507210
2023 2 FD52 07 E122 C 8768801C 009 8/16/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR081M1062222110124 $541.08 000001082265-3562507210
2023 2 FD52 07 E122 C 8768801C 009 8/16/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110124 $60.24 000001082265-3562507210
2023 2 FD52 07 E123 C 8768801C 009 8/16/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR081M1062222110124 $70.81 000001082265-3562507210
2023 2 FD52 07 E123 C 8768801C 009 8/16/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110124 $7.76 000001082265-3562507210
2023 2 FD52 07 E229 C 8768801C 009 8/12/2022 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162522222017240 $196.54
2023 2 FD52 07 E111 C 8768801C 009 8/10/2022 4010 CONSTRUCTION ENGINEERING CA-XR081M1062222110118 $292.57 000001081053-3562500680
2023 2 FD52 07 E111 C 8768801C 009 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110118 $32.36 000001081053-3562500680
2023 2 FD52 07 E121 C 8768801C 009 8/10/2022 4010 CONSTRUCTION ENGINEERING CA-XR081M1062222110118 $21.98 000001081053-3562500680
2023 2 FD52 07 E121 C 8768801C 009 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110118 $2.43 000001081053-3562500680
2023 2 FD52 07 E122 C 8768801C 009 8/10/2022 4010 CONSTRUCTION ENGINEERING CA-XR081M1062222110118 $228.73 000001081053-3562500680
2023 2 FD52 07 E122 C 8768801C 009 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110118 $25.24 000001081053-3562500680
2023 2 FD52 07 E123 C 8768801C 009 8/10/2022 4010 CONSTRUCTION ENGINEERING CA-XR081M1062222110118 $35.47 000001081053-3562500680
2023 2 FD52 07 E123 C 8768801C 009 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110118 $3.86 000001081053-3562500680
2023 2 FD52 07 E111 C 8768801C 009 8/10/2022 4580 CONSTRUCTION CONTRACTS CA-XR081M1062222110155 $4,453.33 10776817-3562507380
2023 2 FD52 07 E115 C 8768801C 009 8/10/2022 4580 CONSTRUCTION CONTRACTS CA-XR081M1062222110155 $3,394.20 10776817-3562507380
2023 2 FD52 07 E121 C 8768801C 009 8/10/2022 4580 CONSTRUCTION CONTRACTS CA-XR081M1062222110155 $594.79 10776817-3562507380
2023 2 FD52 07 E121 C 8768801C 009 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110155 $0.03 10776817-3562507380
2023 2 FD52 07 E122 C 8768801C 009 8/10/2022 4580 CONSTRUCTION CONTRACTS CA-XR081M1062222110155 $6,121.07 10776817-3562507380
2023 2 FD52 07 E123 C 8768801C 009 8/10/2022 4580 CONSTRUCTION CONTRACTS CA-XR081M1062222110155 $276.51 10776817-3562507380
2023 2 FD52 00 E111 C 8768801C 009 8/10/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR081M1062222110121 $242.20 000001081807-3562500640
2023 2 FD52 00 E112 C 8768801C 009 8/10/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR081M1062222110121 $135.00 000001081807-3562500640
2023 2 FD52 00 E112 C 8768801C 009 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110121 $41.40 000001081807-3562500640
2023 2 FD52 00 E121 C 8768801C 009 8/10/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR081M1062222110121 $28.07 000001081807-3562500640
2023 2 FD52 00 E121 C 8768801C 009 8/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081M1062222110121 $3.16 000001081807-3562500640
2023 2 FD52 00 E122 C 8768801C 009 8/10/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR081M1062222110121 $188.91 000001081807-3562500640
2023 2 FD52 00 E123 C 8768801C 009 8/10/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR081M1062222110121 $37.50 000001081807-3562500640
2023 2 FD52 07 E797 C 8768801C 009 8/3/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P013K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $81,726.27
2023 1 FD52 07 E229 C 8768801C 009 7/28/2022 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162522206013570 $196.54
2023 1 FD52 07 E111 C 8768801C 009 7/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR072M1062220308999 $432.99 000001082265-3562507210
2023 1 FD52 07 E111 C 8768801C 009 7/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308999 $43.30 000001082265-3562507210
2023 1 FD52 07 E121 C 8768801C 009 7/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR072M1062220308999 $31.78 000001082265-3562507210
2023 1 FD52 07 E121 C 8768801C 009 7/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308999 $3.18 000001082265-3562507210
2023 1 FD52 07 E122 C 8768801C 009 7/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR072M1062220308999 $337.73 000001082265-3562507210
2023 1 FD52 07 E122 C 8768801C 009 7/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308999 $33.77 000001082265-3562507210
2023 1 FD52 07 E123 C 8768801C 009 7/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR072M1062220308999 $63.11 000001082265-3562507210
2023 1 FD52 07 E123 C 8768801C 009 7/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308999 $6.21 000001082265-3562507210
2023 1 FD52 07 E124 C 8768801C 009 7/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR072M1062220308999 $0.18 000001082265-3562507210
2023 1 FD52 07 E124 C 8768801C 009 7/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308999 $0.02 000001082265-3562507210
2023 1 FD52 07 E122 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308990 $255.41 000001081053-3562500680
2023 1 FD52 07 E123 C 8768801C 009 7/25/2022 4010 CONSTRUCTION ENGINEERING CA-XR072M1062220308990 $41.84 000001081053-3562500680
2023 1 FD52 07 E123 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308990 $38.90 000001081053-3562500680
2023 1 FD52 07 E124 C 8768801C 009 7/25/2022 4010 CONSTRUCTION ENGINEERING CA-XR072M1062220308990 $0.11 000001081053-3562500680
2023 1 FD52 07 E124 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308990 $0.11 000001081053-3562500680
2023 1 FD52 00 E111 C 8768801C 009 7/25/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR072M1062220308995 $219.99 000001081807-3562500640
2023 1 FD52 00 E111 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308995 $82.79 000001081807-3562500640
2023 1 FD52 00 E112 C 8768801C 009 7/25/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR072M1062220308995 $135.00 000001081807-3562500640
2023 1 FD52 00 E112 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308995 $13.50 000001081807-3562500640
2023 1 FD52 00 E121 C 8768801C 009 7/25/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR072M1062220308995 $26.73 000001081807-3562500640
2023 1 FD52 00 E121 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308995 $7.21 000001081807-3562500640
2023 1 FD52 00 E122 C 8768801C 009 7/25/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR072M1062220308995 $171.74 000001081807-3562500640
2023 1 FD52 00 E122 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308995 $64.58 000001081807-3562500640
2023 1 FD52 00 E123 C 8768801C 009 7/25/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR072M1062220308995 $34.27 000001081807-3562500640
2023 1 FD52 00 E123 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308995 $12.65 000001081807-3562500640
2023 1 FD52 00 E124 C 8768801C 009 7/25/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR072M1062220308995 $0.09 000001081807-3562500640
2023 1 FD52 00 E124 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308995 $0.03 000001081807-3562500640
2023 1 FD52 07 E111 C 8768801C 009 7/25/2022 4580 CONSTRUCTION CONTRACTS CA-XR072M1062220309052 $2,001.62 10776817-3562507380
2023 1 FD52 07 E111 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220309052 $200.16 10776817-3562507380
2023 1 FD52 07 E115 C 8768801C 009 7/25/2022 4580 CONSTRUCTION CONTRACTS CA-XR072M1062220309052 $1,955.65 10776817-3562507380
2023 1 FD52 07 E121 C 8768801C 009 7/25/2022 4580 CONSTRUCTION CONTRACTS CA-XR072M1062220309052 $299.60 10776817-3562507380
2023 1 FD52 07 E121 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220309052 $15.13 10776817-3562507380
2023 1 FD52 07 E122 C 8768801C 009 7/25/2022 4580 CONSTRUCTION CONTRACTS CA-XR072M1062220309052 $3,113.63 10776817-3562507380
2023 1 FD52 07 E122 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220309052 $156.13 10776817-3562507380
2023 1 FD52 07 E123 C 8768801C 009 7/25/2022 4580 CONSTRUCTION CONTRACTS CA-XR072M1062220309052 $359.56 10776817-3562507380
2023 1 FD52 07 E123 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220309052 $35.45 10776817-3562507380
2023 1 FD52 07 E124 C 8768801C 009 7/25/2022 4580 CONSTRUCTION CONTRACTS CA-XR072M1062220309052 $0.91 10776817-3562507380
2023 1 FD52 07 E124 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220309052 $0.09 10776817-3562507380
2023 1 FD52 07 E111 C 8768801C 009 7/25/2022 4010 CONSTRUCTION ENGINEERING CA-XR072M1062220308989 $350.26 000001081053-3562500680
2023 1 FD52 07 E111 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308989 $327.46 000001081053-3562500680
2023 1 FD52 07 E121 C 8768801C 009 7/25/2022 4010 CONSTRUCTION ENGINEERING CA-XR072M1062220308989 $26.34 000001081053-3562500680
2023 1 FD52 07 E121 C 8768801C 009 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308989 $24.80 000001081053-3562500680
2023 1 FD52 07 E122 C 8768801C 009 7/25/2022 4010 CONSTRUCTION ENGINEERING CA-XR072M1062220308989 $273.21 000001081053-3562500680
2023 1 FD52 07 E797 C 8768801C 009 7/22/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P012K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $98,272.96
2023 1 FD52 07 E797 C 8768801C 009 7/15/2022 4580 CONSTRUCTION CONTRACTS PRC-2300008668 PON22200004165 VAUGHN AND MELTON $1,001.25 SW HWY & Bridge Construction Inspection Region 1
2023 1 FD52 07 E229 C 8768801C 009 7/13/2022 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162522191009910 $196.54
2023 1 FD52 07 E121 C 8768801C 009 7/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR071M1062219207876 $33.91 000001081053-3562500680
2023 1 FD52 07 E121 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207876 $2.75 000001081053-3562500680
2023 1 FD52 07 E122 C 8768801C 009 7/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR071M1062219207876 $387.18 000001081053-3562500680
2023 1 FD52 07 E122 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207876 $31.17 000001081053-3562500680
2023 1 FD52 07 E123 C 8768801C 009 7/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR071M1062219207876 $57.20 000001081053-3562500680
2023 1 FD52 07 E123 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207876 $4.61 000001081053-3562500680
2023 1 FD52 07 E111 C 8768801C 009 7/12/2022 4580 CONSTRUCTION CONTRACTS CA-XR071M1062219208097 $5,813.81 10776817-3562507380
2023 1 FD52 07 E111 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219208097 $166.31 10776817-3562507380
2023 1 FD52 07 E115 C 8768801C 009 7/12/2022 4580 CONSTRUCTION CONTRACTS CA-XR071M1062219208097 $545.74 10776817-3562507380
2023 1 FD52 07 E121 C 8768801C 009 7/12/2022 4580 CONSTRUCTION CONTRACTS CA-XR071M1062219208097 $475.80 10776817-3562507380
2023 1 FD52 07 E121 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219208097 $12.38 10776817-3562507380
2023 1 FD52 07 E122 C 8768801C 009 7/12/2022 4580 CONSTRUCTION CONTRACTS CA-XR071M1062219208097 $5,340.13 10776817-3562507380
2023 1 FD52 07 E122 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219208097 $139.65 10776817-3562507380
2023 1 FD52 07 E123 C 8768801C 009 7/12/2022 4580 CONSTRUCTION CONTRACTS CA-XR071M1062219208097 $857.76 10776817-3562507380
2023 1 FD52 07 E123 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219208097 $20.34 10776817-3562507380
2023 1 FD52 07 E111 C 8768801C 009 7/12/2022 4010 CONSTRUCTION ENGINEERING CA-XR071M1062219207876 $461.10 000001081053-3562500680
2023 1 FD52 07 E111 C 8768801C 009 7/12/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR071M1062219207883 $3,000.92 000001082265-3562507210
2023 1 FD52 07 E111 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207883 $291.44 000001082265-3562507210
2023 1 FD52 07 E111 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207876 $37.13 000001081053-3562500680
2023 1 FD52 07 E121 C 8768801C 009 7/12/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR071M1062219207883 $219.31 000001082265-3562507210
2023 1 FD52 07 E121 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207883 $20.04 000001082265-3562507210
2023 1 FD52 07 E122 C 8768801C 009 7/12/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR071M1062219207883 $2,519.87 000001082265-3562507210
2023 1 FD52 07 E122 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207883 $244.72 000001082265-3562507210
2023 1 FD52 07 E123 C 8768801C 009 7/12/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR071M1062219207883 $467.72 000001082265-3562507210
2023 1 FD52 07 E123 C 8768801C 009 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207883 $65.09 000001082265-3562507210
2023 1 FD52 07 E797 C 8768801C 009 7/7/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P011K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $499,745.09
2022 12 FD52 07 E124 C 8768801C 009 6/28/2022 4010 CONSTRUCTION ENGINEERING CA-XR062M1062217506768 $0.09 000001081053-3562500680
2022 12 FD52 07 E111 C 8768801C 009 6/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR062M1062217506776 $3,432.21 000001082265-3562507210
2022 12 FD52 07 E111 C 8768801C 009 6/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506776 $539.73 000001082265-3562507210
2022 12 FD52 07 E121 C 8768801C 009 6/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR062M1062217506776 $250.87 000001082265-3562507210
2022 12 FD52 07 E121 C 8768801C 009 6/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506776 $38.83 000001082265-3562507210
2022 12 FD52 07 E122 C 8768801C 009 6/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR062M1062217506776 $2,882.02 000001082265-3562507210
2022 12 FD52 07 E122 C 8768801C 009 6/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506776 $453.21 000001082265-3562507210
2022 12 FD52 07 E123 C 8768801C 009 6/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR062M1062217506776 $576.21 000001082265-3562507210
2022 12 FD52 07 E123 C 8768801C 009 6/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506776 $101.67 000001082265-3562507210
2022 12 FD52 07 E124 C 8768801C 009 6/28/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR062M1062217506776 $1.66 000001082265-3562507210
2022 12 FD52 07 E124 C 8768801C 009 6/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506776 $0.29 000001082265-3562507210
2022 12 FD52 07 E229 C 8768801C 009 6/27/2022 4010 CONSTRUCTION ENGINEERING IET-XE13A162522176012840 $132.00
2022 12 FD52 07 E229 C 8768801C 009 6/27/2022 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162522176043550 $176.25
2022 12 FD52 07 E229 C 8768801C 009 6/27/2022 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162522176043920 $91.00
2022 12 FD52 07 E111 C 8768801C 009 6/27/2022 4580 CONSTRUCTION CONTRACTS CA-XR062M1062217506805 $4,251.98 10675981-3562507380
2022 12 FD52 07 E111 C 8768801C 009 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506805 $135.91 10675981-3562507380
2022 12 FD52 07 E115 C 8768801C 009 6/27/2022 4580 CONSTRUCTION CONTRACTS CA-XR062M1062217506805 $526.92 10675981-3562507380
2022 12 FD52 07 E121 C 8768801C 009 6/27/2022 4580 CONSTRUCTION CONTRACTS CA-XR062M1062217506805 $360.01 10675981-3562507380
2022 12 FD52 07 E121 C 8768801C 009 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506805 $10.22 10675981-3562507380
2022 12 FD52 07 E122 C 8768801C 009 6/27/2022 4580 CONSTRUCTION CONTRACTS CA-XR062M1062217506805 $4,012.84 10675981-3562507380
2022 12 FD52 07 E122 C 8768801C 009 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506805 $114.12 10675981-3562507380
2022 12 FD52 07 E123 C 8768801C 009 6/27/2022 4580 CONSTRUCTION CONTRACTS CA-XR062M1062217506805 $669.58 10675981-3562507380
2022 12 FD52 07 E123 C 8768801C 009 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506805 $25.99 10675981-3562507380
2022 12 FD52 07 E124 C 8768801C 009 6/27/2022 4580 CONSTRUCTION CONTRACTS CA-XR062M1062217506805 $1.75 10675981-3562507380
2022 12 FD52 07 E124 C 8768801C 009 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506805 $0.07 10675981-3562507380
2022 12 FD52 07 E111 C 8768801C 009 6/27/2022 4010 CONSTRUCTION ENGINEERING CA-XR062M1062217506767 $246.16 000001081053-3562500680
2022 12 FD52 07 E121 C 8768801C 009 6/27/2022 4010 CONSTRUCTION ENGINEERING CA-XR062M1062217506767 $18.64 000001081053-3562500680
2022 12 FD52 07 E122 C 8768801C 009 6/27/2022 4010 CONSTRUCTION ENGINEERING CA-XR062M1062217506767 $206.70 000001081053-3562500680
2022 12 FD52 07 E123 C 8768801C 009 6/27/2022 4010 CONSTRUCTION ENGINEERING CA-XR062M1062217506767 $32.13 000001081053-3562500680
2022 12 FD52 07 E797 C 8768801C 009 6/24/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P010K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $205,114.21
2022 12 FD52 07 E229 C 8768801C 009 6/13/2022 4010 CONSTRUCTION ENGINEERING IET-XE13A162522161004850 $66.00
2022 12 FD52 07 E229 C 8768801C 009 6/13/2022 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162522161022490 $20.68
2022 12 FD52 07 E111 C 8768801C 009 6/13/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR061M1062215905731 $1,209.79 000001082265-3562507210
2022 12 FD52 07 E111 C 8768801C 009 6/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905731 $502.18 000001082265-3562507210
2022 12 FD52 07 E121 C 8768801C 009 6/13/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR061M1062215905731 $83.41 000001082265-3562507210
2022 12 FD52 07 E121 C 8768801C 009 6/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905731 $34.57 000001082265-3562507210
2022 12 FD52 07 E122 C 8768801C 009 6/13/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR061M1062215905731 $1,015.86 000001082265-3562507210
2022 12 FD52 07 E122 C 8768801C 009 6/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905731 $421.68 000001082265-3562507210
2022 12 FD52 07 E123 C 8768801C 009 6/13/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR061M1062215905731 $270.80 000001082265-3562507210
2022 12 FD52 07 E123 C 8768801C 009 6/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905731 $111.08 000001082265-3562507210
2022 12 FD52 07 E111 C 8768801C 009 6/9/2022 4010 CONSTRUCTION ENGINEERING CA-XR061M1062215905723 $276.40 000001081053-3562500680
2022 12 FD52 07 E111 C 8768801C 009 6/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905723 $39.51 000001081053-3562500680
2022 12 FD52 07 E121 C 8768801C 009 6/9/2022 4010 CONSTRUCTION ENGINEERING CA-XR061M1062215905723 $20.50 000001081053-3562500680
2022 12 FD52 07 E121 C 8768801C 009 6/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905723 $2.89 000001081053-3562500680
2022 12 FD52 07 E122 C 8768801C 009 6/9/2022 4010 CONSTRUCTION ENGINEERING CA-XR061M1062215905723 $232.12 000001081053-3562500680
2022 12 FD52 07 E122 C 8768801C 009 6/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905723 $33.18 000001081053-3562500680
2022 12 FD52 07 E123 C 8768801C 009 6/9/2022 4010 CONSTRUCTION ENGINEERING CA-XR061M1062215905723 $39.94 000001081053-3562500680
2022 12 FD52 07 E123 C 8768801C 009 6/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905723 $5.23 000001081053-3562500680
2022 12 FD52 07 E111 C 8768801C 009 6/9/2022 4580 CONSTRUCTION CONTRACTS CA-XR061M1062215905753 $2,247.96 10675981-3562507380
2022 12 FD52 07 E111 C 8768801C 009 6/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905753 $495.82 10675981-3562507380
2022 12 FD52 07 E115 C 8768801C 009 6/9/2022 4580 CONSTRUCTION CONTRACTS CA-XR061M1062215905753 $1,185.57 10675981-3562507380
2022 12 FD52 07 E121 C 8768801C 009 6/9/2022 4580 CONSTRUCTION CONTRACTS CA-XR061M1062215905753 $258.37 10675981-3562507380
2022 12 FD52 07 E121 C 8768801C 009 6/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905753 $37.14 10675981-3562507380
2022 12 FD52 07 E122 C 8768801C 009 6/9/2022 4580 CONSTRUCTION CONTRACTS CA-XR061M1062215905753 $2,883.35 10675981-3562507380
2022 12 FD52 07 E122 C 8768801C 009 6/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905753 $416.34 10675981-3562507380
2022 12 FD52 07 E123 C 8768801C 009 6/9/2022 4580 CONSTRUCTION CONTRACTS CA-XR061M1062215905753 $408.12 10675981-3562507380
2022 12 FD52 07 E123 C 8768801C 009 6/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905753 $89.02 10675981-3562507380
2022 12 FD52 07 E797 C 8768801C 009 6/8/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P009K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $171,473.15
2022 11 FD52 07 E229 C 8768801C 009 5/26/2022 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162522145014470 $168.73
2022 11 FD52 07 E797 C 8768801C 009 5/25/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P008K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $145,736.58
2022 11 FD52 07 E111 C 8768801C 009 5/25/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR052M1062214004684 $2,425.57 000001082265-3562507210
2022 11 FD52 07 E111 C 8768801C 009 5/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004684 $269.31 000001082265-3562507210
2022 11 FD52 07 E121 C 8768801C 009 5/25/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR052M1062214004684 $173.57 000001082265-3562507210
2022 11 FD52 07 E121 C 8768801C 009 5/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004684 $19.27 000001082265-3562507210
2022 11 FD52 07 E122 C 8768801C 009 5/25/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR052M1062214004684 $2,036.74 000001082265-3562507210
2022 11 FD52 07 E122 C 8768801C 009 5/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004684 $226.14 000001082265-3562507210
2022 11 FD52 07 E123 C 8768801C 009 5/25/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR052M1062214004684 $439.28 000001082265-3562507210
2022 11 FD52 07 E123 C 8768801C 009 5/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004684 $48.08 000001082265-3562507210
2022 11 FD52 07 E124 C 8768801C 009 5/25/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR052M1062214004684 $1.10 000001082265-3562507210
2022 11 FD52 07 E124 C 8768801C 009 5/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004684 $0.12 000001082265-3562507210
2022 11 FD52 07 E124 C 8768801C 009 5/23/2022 4010 CONSTRUCTION ENGINEERING CA-XR052M1062214004676 $0.10 000001081053-3562500620
2022 11 FD52 07 E124 C 8768801C 009 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004676 $0.01 000001081053-3562500620
2022 11 FD52 07 E111 C 8768801C 009 5/23/2022 4010 CONSTRUCTION ENGINEERING CA-XR052M1062214004676 $161.59 000001081053-3562500620
2022 11 FD52 07 E111 C 8768801C 009 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004676 $17.88 000001081053-3562500620
2022 11 FD52 07 E111 C 8768801C 009 5/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR052M1062214004708 $5,699.51 10675981-3562507380
2022 11 FD52 07 E121 C 8768801C 009 5/23/2022 4010 CONSTRUCTION ENGINEERING CA-XR052M1062214004676 $11.88 000001081053-3562500620
2022 11 FD52 07 E111 C 8768801C 009 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004708 $18.90 10675981-3562507380
2022 11 FD52 07 E115 C 8768801C 009 5/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR052M1062214004708 $621.01 10675981-3562507380
2022 11 FD52 07 E121 C 8768801C 009 5/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR052M1062214004708 $475.55 10675981-3562507380
2022 11 FD52 07 E121 C 8768801C 009 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004708 $1.44 10675981-3562507380
2022 11 FD52 07 E122 C 8768801C 009 5/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR052M1062214004708 $5,307.25 10675981-3562507380
2022 11 FD52 07 E122 C 8768801C 009 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004708 $15.87 10675981-3562507380
2022 11 FD52 07 E123 C 8768801C 009 5/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR052M1062214004708 $884.39 10675981-3562507380
2022 11 FD52 07 E124 C 8768801C 009 5/23/2022 4580 CONSTRUCTION CONTRACTS CA-XR052M1062214004708 $2.44 10675981-3562507380
2022 11 FD52 07 E124 C 8768801C 009 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004708 $0.01 10675981-3562507380
2022 11 FD52 07 E121 C 8768801C 009 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004676 $1.32 000001081053-3562500620
2022 11 FD52 07 E122 C 8768801C 009 5/23/2022 4010 CONSTRUCTION ENGINEERING CA-XR052M1062214004676 $135.82 000001081053-3562500620
2022 11 FD52 07 E122 C 8768801C 009 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004676 $15.01 000001081053-3562500620
2022 11 FD52 07 E123 C 8768801C 009 5/23/2022 4010 CONSTRUCTION ENGINEERING CA-XR052M1062214004676 $34.75 000001081053-3562500620
2022 11 FD52 07 E123 C 8768801C 009 5/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR052M1062214004676 $3.78 000001081053-3562500620
2022 11 FD52 07 E123 C 8768801C 009 5/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212603685 $7.17 10675981-3562507380
2022 11 FD52 07 E111 C 8768801C 009 5/13/2022 4580 CONSTRUCTION CONTRACTS CA-XR051M1062212603685 $7,180.91 10675981-3562507380
2022 11 FD52 07 E111 C 8768801C 009 5/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212603685 $587.70 10675981-3562507380
2022 11 FD52 07 E115 C 8768801C 009 5/13/2022 4580 CONSTRUCTION CONTRACTS CA-XR051M1062212603685 $959.74 10675981-3562507380
2022 11 FD52 07 E121 C 8768801C 009 5/13/2022 4580 CONSTRUCTION CONTRACTS CA-XR051M1062212603685 $614.47 10675981-3562507380
2022 11 FD52 07 E121 C 8768801C 009 5/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212603685 $44.87 10675981-3562507380
2022 11 FD52 07 E122 C 8768801C 009 5/13/2022 4580 CONSTRUCTION CONTRACTS CA-XR051M1062212603685 $6,835.71 10675981-3562507380
2022 11 FD52 07 E122 C 8768801C 009 5/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212603685 $493.48 10675981-3562507380
2022 11 FD52 07 E123 C 8768801C 009 5/13/2022 4580 CONSTRUCTION CONTRACTS CA-XR051M1062212603685 $948.27 10675981-3562507380
2022 11 FD52 07 E229 C 8768801C 009 5/12/2022 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162522130016690 $175.60
2022 11 FD52 07 E229 C 8768801C 009 5/12/2022 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162522130016980 $154.00
2022 11 FD52 07 E797 C 8768801C 009 5/11/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P007K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $27,988.75
2022 11 FD52 07 E111 C 8768801C 009 5/9/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR051M1062212603666 $4,847.80 000001082265-3562507210
2022 11 FD52 07 E111 C 8768801C 009 5/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212603666 $265.78 000001082265-3562507210
2022 11 FD52 07 E121 C 8768801C 009 5/9/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR051M1062212603666 $357.23 000001082265-3562507210
2022 11 FD52 07 E121 C 8768801C 009 5/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212603666 $18.85 000001082265-3562507210
2022 11 FD52 07 E122 C 8768801C 009 5/9/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR051M1062212603666 $4,070.69 000001082265-3562507210
2022 11 FD52 07 E122 C 8768801C 009 5/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212603666 $223.18 000001082265-3562507210
2022 11 FD52 07 E123 C 8768801C 009 5/9/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR051M1062212603666 $732.25 000001082265-3562507210
2022 11 FD52 07 E123 C 8768801C 009 5/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051M1062212603666 $53.90 000001082265-3562507210
2022 10 FD52 07 E111 C 8768801C 009 4/28/2022 4580 CONSTRUCTION CONTRACTS CA-XR042M1062211202570 $5,426.70 10675981-3562507380
2022 10 FD52 07 E111 C 8768801C 009 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202570 $560.70 10675981-3562507380
2022 10 FD52 07 E115 C 8768801C 009 4/28/2022 4580 CONSTRUCTION CONTRACTS CA-XR042M1062211202570 $583.38 10675981-3562507380
2022 10 FD52 07 E121 C 8768801C 009 4/28/2022 4580 CONSTRUCTION CONTRACTS CA-XR042M1062211202570 $456.03 10675981-3562507380
2022 10 FD52 07 E121 C 8768801C 009 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202570 $42.73 10675981-3562507380
2022 10 FD52 07 E122 C 8768801C 009 4/28/2022 4580 CONSTRUCTION CONTRACTS CA-XR042M1062211202570 $5,046.58 10675981-3562507380
2022 10 FD52 07 E122 C 8768801C 009 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202570 $470.82 10675981-3562507380
2022 10 FD52 07 E123 C 8768801C 009 4/28/2022 4580 CONSTRUCTION CONTRACTS CA-XR042M1062211202570 $613.17 10675981-3562507380
2022 10 FD52 07 E123 C 8768801C 009 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202570 $28.55 10675981-3562507380
2022 10 FD52 07 E124 C 8768801C 009 4/28/2022 4580 CONSTRUCTION CONTRACTS CA-XR042M1062211202570 $2.39 10675981-3562507380
2022 10 FD52 07 E124 C 8768801C 009 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202570 $0.27 10675981-3562507380
2022 10 FD52 07 E797 C 8768801C 009 4/27/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P006K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $118,072.93
2022 10 FD52 07 E229 C 8768801C 009 4/26/2022 5182 INSP-MISCELLANEOUS MATERIALS IET-XE13A162522115012800 $195.99
2022 10 FD52 07 E111 C 8768801C 009 4/25/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR042M1062211202556 $2,004.60 000001082265-3562507210
2022 10 FD52 07 E111 C 8768801C 009 4/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202556 $200.46 000001082265-3562507210
2022 10 FD52 07 E121 C 8768801C 009 4/25/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR042M1062211202556 $146.63 000001082265-3562507210
2022 10 FD52 07 E121 C 8768801C 009 4/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202556 $14.66 000001082265-3562507210
2022 10 FD52 07 E122 C 8768801C 009 4/25/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR042M1062211202556 $1,683.27 000001082265-3562507210
2022 10 FD52 07 E122 C 8768801C 009 4/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202556 $168.32 000001082265-3562507210
2022 10 FD52 07 E123 C 8768801C 009 4/25/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR042M1062211202556 $315.57 000001082265-3562507210
2022 10 FD52 07 E123 C 8768801C 009 4/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202556 $31.04 000001082265-3562507210
2022 10 FD52 07 E124 C 8768801C 009 4/25/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR042M1062211202556 $0.90 000001082265-3562507210
2022 10 FD52 07 E124 C 8768801C 009 4/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202556 $0.10 000001082265-3562507210
2022 10 FD52 07 E115 C 8768801C 009 4/25/2022 4010 CONSTRUCTION ENGINEERING CA-XR042M1062211202543 $82.80 000001081053-3562500680
2022 10 FD52 07 E121 C 8768801C 009 4/25/2022 4010 CONSTRUCTION ENGINEERING CA-XR042M1062211202543 $6.30 000001081053-3562500680
2022 10 FD52 07 E122 C 8768801C 009 4/25/2022 4010 CONSTRUCTION ENGINEERING CA-XR042M1062211202543 $69.53 000001081053-3562500680
2022 10 FD52 07 E122 C 8768801C 009 4/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202543 ($0.01) 000001081053-3562500680
2022 10 FD52 07 E797 C 8768801C 009 4/13/2022 4580 CONSTRUCTION CONTRACTS PRC-XCONST092211330P005K CTXCONST0922113300001K FREDERICK & MAY CONSTRUCTION CO INC $183,044.75
2022 10 FD52 07 E111 C 8768801C 009 4/13/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR041M1062209801501 $183.76 000001082265-3562507210
2022 10 FD52 07 E121 C 8768801C 009 4/13/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR041M1062209801501 $13.44 000001082265-3562507210
2022 10 FD52 07 E122 C 8768801C 009 4/13/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR041M1062209801501 $154.29 000001082265-3562507210
2022 10 FD52 07 E123 C 8768801C 009 4/13/2022 5182 INSP-MISCELLANEOUS MATERIALS CA-XR041M1062209801501 $28.88 000001082265-3562507210
2022 10 FD52 00 E121 C 8768801C 009 4/11/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR041M1062209801488 $0.02 000001081807-3562500640
2022 10 FD52 07 E111 C 8768801C 009 4/11/2022 4580 CONSTRUCTION CONTRACTS CA-XR041M1062209801506 $4,470.18 10675981-3562507380
2022 10 FD52 07 E111 C 8768801C 009 4/11/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801506 $88.17 10675981-3562507380
2022 10 FD52 07 E115 C 8768801C 009 4/11/2022 4580 CONSTRUCTION CONTRACTS CA-XR041M1062209801506 $376.37 10675981-3562507380
2022 10 FD52 07 E121 C 8768801C 009 4/11/2022 4580 CONSTRUCTION CONTRACTS CA-XR041M1062209801506 $365.03 10675981-3562507380
2022 10 FD52 07 E121 C 8768801C 009 4/11/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801506 $6.75 10675981-3562507380
2022 10 FD52 07 E122 C 8768801C 009 4/11/2022 4580 CONSTRUCTION CONTRACTS CA-XR041M1062209801506 $4,069.65 10675981-3562507380
2022 10 FD52 07 E122 C 8768801C 009 4/11/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801506 $74.04 10675981-3562507380
2022 10 FD52 07 E123 C 8768801C 009 4/11/2022 4580 CONSTRUCTION CONTRACTS CA-XR041M1062209801506 $700.62 10675981-3562507380
2022 10 FD52 07 E111 C 8768801C 009 4/11/2022 4010 CONSTRUCTION ENGINEERING CA-XR041M1062209801481 $186.93 000001081053-3562500680
2022 10 FD52 07 E111 C 8768801C 009 4/11/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801481 $16.94 000001081053-3562500680
2022 10 FD52 07 E121 C 8768801C 009 4/11/2022 4010 CONSTRUCTION ENGINEERING CA-XR041M1062209801481 $14.15 000001081053-3562500680
2022 10 FD52 07 E121 C 8768801C 009 4/11/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801481 $1.28 000001081053-3562500680
2022 10 FD52 07 E122 C 8768801C 009 4/11/2022 4010 CONSTRUCTION ENGINEERING CA-XR041M1062209801481 $156.92 000001081053-3562500680
2022 10 FD52 07 E122 C 8768801C 009 4/11/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801481 $14.23 000001081053-3562500680
2022 10 FD52 07 E123 C 8768801C 009 4/11/2022 4010 CONSTRUCTION ENGINEERING CA-XR041M1062209801481 $29.49 000001081053-3562500680
2022 10 FD52 07 E123 C 8768801C 009 4/11/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801481 $2.63 000001081053-3562500680
2022 9 FD52 00 E229 C 8768801C 009 3/28/2022 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162522084002640 $81.74
2022 9 FD52 07 E111 C 8768801C 009 3/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR032M1062208200429 $5,266.75 10675981-3562507380
2022 9 FD52 07 E111 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200429 $193.04 10675981-3562507380
2022 9 FD52 07 E115 C 8768801C 009 3/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR032M1062208200429 $621.01 10675981-3562507380
2022 9 FD52 07 E121 C 8768801C 009 3/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR032M1062208200429 $442.78 10675981-3562507380
2022 9 FD52 07 E121 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200429 $14.37 10675981-3562507380
2022 9 FD52 07 E122 C 8768801C 009 3/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR032M1062208200429 $4,943.94 10675981-3562507380
2022 9 FD52 07 E122 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200429 $162.10 10675981-3562507380
2022 9 FD52 07 E123 C 8768801C 009 3/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR032M1062208200429 $879.31 10675981-3562507380
2022 9 FD52 07 E123 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200429 $31.90 10675981-3562507380
2022 9 FD52 07 E124 C 8768801C 009 3/24/2022 4580 CONSTRUCTION CONTRACTS CA-XR032M1062208200429 $2.27 10675981-3562507380
2022 9 FD52 07 E124 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200429 $0.08 10675981-3562507380
2022 9 FD52 00 E111 C 8768801C 009 3/24/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR032M1062208200414 $203.83 000001081807-3562500640
2022 9 FD52 00 E111 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200414 $7.07 000001081807-3562500640
2022 9 FD52 00 E121 C 8768801C 009 3/24/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR032M1062208200414 $15.16 000001081807-3562500640
2022 9 FD52 00 E121 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200414 $0.53 000001081807-3562500640
2022 9 FD52 00 E122 C 8768801C 009 3/24/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR032M1062208200414 $171.19 000001081807-3562500640
2022 9 FD52 00 E122 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200414 $5.94 000001081807-3562500640
2022 9 FD52 00 E123 C 8768801C 009 3/24/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR032M1062208200414 $34.11 000001081807-3562500640
2022 9 FD52 00 E123 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200414 $1.17 000001081807-3562500640
2022 9 FD52 00 E124 C 8768801C 009 3/24/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR032M1062208200414 $0.09 000001081807-3562500640
2022 9 FD52 00 E111 C 8768801C 009 3/24/2022 5213 ASPHALT MIX DESIGN CA-XR032M1062208200426 $638.21 000001082058-3562500640
2022 9 FD52 00 E111 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200426 $186.33 000001082058-3562500640
2022 9 FD52 00 E121 C 8768801C 009 3/24/2022 5213 ASPHALT MIX DESIGN CA-XR032M1062208200426 $47.58 000001082058-3562500640
2022 9 FD52 00 E121 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200426 $14.04 000001082058-3562500640
2022 9 FD52 00 E122 C 8768801C 009 3/24/2022 5213 ASPHALT MIX DESIGN CA-XR032M1062208200426 $536.00 000001082058-3562500640
2022 9 FD52 00 E122 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200426 $156.46 000001082058-3562500640
2022 9 FD52 00 E123 C 8768801C 009 3/24/2022 5213 ASPHALT MIX DESIGN CA-XR032M1062208200426 $102.44 000001082058-3562500640
2022 9 FD52 00 E123 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200426 $25.02 000001082058-3562500640
2022 9 FD52 00 E124 C 8768801C 009 3/24/2022 5213 ASPHALT MIX DESIGN CA-XR032M1062208200426 $0.27 000001082058-3562500640
2022 9 FD52 00 E124 C 8768801C 009 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200426 $0.07 000001082058-3562500640
2022 9 FD52 00 E229 C 8768801C 009 3/11/2022 5062 SAMPLINGS & TESTING-AGGREGATE IET-XE13A162522069004120 $50.02
2022 9 FD52 07 E229 C 8768801C 009 3/11/2022 4010 CONSTRUCTION ENGINEERING IET-XE13A162522069004230 $138.90
2022 9 FD52 07 E111 C 8768801C 009 3/9/2022 4580 CONSTRUCTION CONTRACTS CA-XR031M1062206709482 $6,369.07 10675981-3562507380
2022 9 FD52 07 E111 C 8768801C 009 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709482 $37.64 10675981-3562507380
2022 9 FD52 07 E115 C 8768801C 009 3/9/2022 4580 CONSTRUCTION CONTRACTS CA-XR031M1062206709482 $225.82 10675981-3562507380
2022 9 FD52 07 E121 C 8768801C 009 3/9/2022 4580 CONSTRUCTION CONTRACTS CA-XR031M1062206709482 $495.55 10675981-3562507380
2022 9 FD52 07 E121 C 8768801C 009 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709482 $2.85 10675981-3562507380
2022 9 FD52 07 E122 C 8768801C 009 3/9/2022 4580 CONSTRUCTION CONTRACTS CA-XR031M1062206709482 $5,537.73 10675981-3562507380
2022 9 FD52 07 E122 C 8768801C 009 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709482 $31.61 10675981-3562507380
2022 9 FD52 07 E123 C 8768801C 009 3/9/2022 4580 CONSTRUCTION CONTRACTS CA-XR031M1062206709482 $1,011.30 10675981-3562507380
2022 9 FD52 07 E123 C 8768801C 009 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709482 $4.59 10675981-3562507380
2022 9 FD52 07 E111 C 8768801C 009 3/9/2022 4010 CONSTRUCTION ENGINEERING CA-XR031M1062206709468 $607.42 000001081053-3562500680
2022 9 FD52 07 E115 C 8768801C 009 3/9/2022 4010 CONSTRUCTION ENGINEERING CA-XR031M1062206709468 $82.80 000001081053-3562500680
2022 9 FD52 07 E121 C 8768801C 009 3/9/2022 4010 CONSTRUCTION ENGINEERING CA-XR031M1062206709468 $51.35 000001081053-3562500680
2022 9 FD52 00 E111 C 8768801C 009 3/9/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR031M1062206709481 $249.18 000001081807-3562500640
2022 9 FD52 07 E122 C 8768801C 009 3/9/2022 4010 CONSTRUCTION ENGINEERING CA-XR031M1062206709468 $579.58 000001081053-3562500680
2022 9 FD52 00 E115 C 8768801C 009 3/9/2022 5062 SAMPLINGS & TESTING-AGGREGATE CA-XR031M1062206709481 $41.40 000001081807-3562500640