The Commonwealth pays employees on a semi-monthly basis with a scheduled pay day on the 15th and 30th of each month. The two monthly pay periods are from the 1st to the 15th of the month and the 16th through the last day of the month. Pay check distribution is delayed by one pay period to allow for system processing. For example work performed during the 1st to the 15th day of the month is paid to the employee on the 30th of the month. Accordingly the cost accounting charges for labor costs posting in eMARS to operating accounts and highway projects are also delayed by approximately one pay period.
A good rule of measure is that the cost accounting charges for the pay period ending on the 15th of the month will post to eMARS by the 25th and those for the pay period ending on the last day of the month will post to eMARS by the 10th of the following month.

x close panel
Detailed Project Expenditure Report
Total E-MARS Expenditures for 1354301D = $988,159.73
Click here for Labor Costs Information
Year Month PBU Charge District Object Phase Program Code County Date ACT Activity Name Trans ID Reference # Vendor Name Expenditure Line Description
2024 9 FD04 00 E111 D 1354301D 042 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810083 $118.44 000001086848-3562500610
2024 9 FD04 00 E121 D 1354301D 042 3/11/2024 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR031O1062406810083 $21.03 000001086848-3562500610
2024 9 FD04 00 E121 D 1354301D 042 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810083 $8.47 000001086848-3562500610
2024 9 FD04 00 E122 D 1354301D 042 3/11/2024 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR031O1062406810083 $201.29 000001086848-3562500610
2024 9 FD04 00 E122 D 1354301D 042 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810083 $78.37 000001086848-3562500610
2024 9 FD04 00 E123 D 1354301D 042 3/11/2024 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR031O1062406810083 $51.45 000001086848-3562500610
2024 9 FD04 00 E123 D 1354301D 042 3/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031O1062406810083 $19.06 000001086848-3562500610
2024 9 FD04 00 E111 D 1354301D 042 3/11/2024 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR031O1062406810083 $304.79 000001086848-3562500610
2024 8 FD04 00 E122 D 1354301D 042 2/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR022O1062405408924 $1,585.45 000001088999-3562500610
2024 8 FD04 00 E122 D 1354301D 042 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408924 $472.99 000001088999-3562500610
2024 8 FD04 00 E123 D 1354301D 042 2/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR022O1062405408924 $373.90 000001088999-3562500610
2024 8 FD04 00 E123 D 1354301D 042 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408924 $194.10 000001088999-3562500610
2024 8 FD04 00 E124 D 1354301D 042 2/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR022O1062405408924 $0.75 000001088999-3562500610
2024 8 FD04 00 E124 D 1354301D 042 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408924 $0.25 000001088999-3562500610
2024 8 FD04 00 E111 D 1354301D 042 2/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR022O1062405408924 $2,395.80 000001088999-3562500610
2024 8 FD04 00 E111 D 1354301D 042 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408924 $714.79 000001088999-3562500610
2024 8 FD04 00 E121 D 1354301D 042 2/26/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR022O1062405408924 $174.24 000001088999-3562500610
2024 8 FD04 00 E121 D 1354301D 042 2/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022O1062405408924 $46.22 000001088999-3562500610
2024 8 FD04 01 E143 D 1354301D 042 2/19/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400165460 PON22200001500 HDR ENGINEERING INC $19,220.00 Graves Co 1-80130
2024 8 FD04 01 E143 D 1354301D 042 2/19/2024 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400165476 PON22200001500 HDR ENGINEERING INC $13,950.00 Graves Co 1-80130
2024 8 FD04 00 E111 D 1354301D 042 2/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021O1062403907688 $1,665.22 000001088999-3562500610
2024 8 FD04 00 E111 D 1354301D 042 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907688 $92.80 000001088999-3562500610
2024 8 FD04 00 E121 D 1354301D 042 2/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021O1062403907688 $119.49 000001088999-3562500610
2024 8 FD04 00 E121 D 1354301D 042 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907688 $6.62 000001088999-3562500610
2024 8 FD04 00 E122 D 1354301D 042 2/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021O1062403907688 $1,101.68 000001088999-3562500610
2024 8 FD04 00 E122 D 1354301D 042 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907688 $61.41 000001088999-3562500610
2024 8 FD04 00 E123 D 1354301D 042 2/9/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR021O1062403907688 $293.47 000001088999-3562500610
2024 8 FD04 00 E123 D 1354301D 042 2/9/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021O1062403907688 $16.31 000001088999-3562500610
2024 7 FD04 00 E111 D 1354301D 042 1/31/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012O1062402306617 $188.05 000001088999-3562500610
2024 7 FD04 00 E111 D 1354301D 042 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306617 $44.05 000001088999-3562500610
2024 7 FD04 00 E121 D 1354301D 042 1/31/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012O1062402306617 $13.00 000001088999-3562500610
2024 7 FD04 00 E121 D 1354301D 042 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306617 $3.03 000001088999-3562500610
2024 7 FD04 00 E122 D 1354301D 042 1/31/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012O1062402306617 $124.57 000001088999-3562500610
2024 7 FD04 00 E122 D 1354301D 042 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306617 $29.15 000001088999-3562500610
2024 7 FD04 00 E123 D 1354301D 042 1/31/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012O1062402306617 $40.80 000001088999-3562500610
2024 7 FD04 00 E123 D 1354301D 042 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306617 $9.70 000001088999-3562500610
2024 7 FD04 00 E124 D 1354301D 042 1/31/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR012O1062402306617 $0.05 000001088999-3562500610
2024 7 FD04 00 E124 D 1354301D 042 1/31/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306617 $0.02 000001088999-3562500610
2024 7 FD04 00 E111 D 1354301D 042 1/11/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR122N1062335504644 $2,674.92 000001088999-3562500610
2024 7 FD04 00 E111 D 1354301D 042 1/11/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504644 $525.25 000001088999-3562500610
2024 7 FD04 00 E121 D 1354301D 042 1/11/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR122N1062335504644 $198.25 000001088999-3562500610
2024 7 FD04 00 E111 D 1354301D 042 1/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR011O1062400505739 $2,467.86 000001088999-3562500610
2024 7 FD04 00 E111 D 1354301D 042 1/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505739 $1,461.87 000001088999-3562500610
2024 7 FD04 00 E121 D 1354301D 042 1/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR011O1062400505739 $174.75 000001088999-3562500610
2024 7 FD04 00 E121 D 1354301D 042 1/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505739 $103.22 000001088999-3562500610
2024 7 FD04 00 E122 D 1354301D 042 1/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR011O1062400505739 $1,632.53 000001088999-3562500610
2024 7 FD04 00 E122 D 1354301D 042 1/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505739 $967.34 000001088999-3562500610
2024 7 FD04 00 E123 D 1354301D 042 1/10/2024 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR011O1062400505739 $490.01 000001088999-3562500610
2024 7 FD04 00 E123 D 1354301D 042 1/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011O1062400505739 $291.54 000001088999-3562500610
2024 6 FD04 00 E111 D 1354301D 042 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504601 $310.27 000001080408-3562500636
2024 6 FD04 00 E121 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504645 $38.85 000001088999-3562500610
2024 6 FD04 00 E124 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504601 $0.02 000001080408-3562500636
2024 6 FD04 00 E111 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504601 $83.53 000001080408-3562500636
2024 6 FD04 00 E122 D 1354301D 042 12/22/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR122N1062335504645 $1,770.35 000001088999-3562500610
2024 6 FD04 00 E121 D 1354301D 042 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504601 $23.58 000001080408-3562500636
2024 6 FD04 00 E122 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504645 $347.57 000001088999-3562500610
2024 6 FD04 00 E121 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504601 $6.35 000001080408-3562500636
2024 6 FD04 00 E123 D 1354301D 042 12/22/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR122N1062335504645 $414.98 000001088999-3562500610
2024 6 FD04 00 E111 D 1354301D 042 12/22/2023 1060 RDWAY PLANS-FINAL-DRAINAGE SEC CA-XR122N1062335504654 $1,193.26 000001090098-3562500630
2024 6 FD04 00 E111 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504654 $233.43 000001090098-3562500630
2024 6 FD04 00 E121 D 1354301D 042 12/22/2023 1060 RDWAY PLANS-FINAL-DRAINAGE SEC CA-XR122N1062335504654 $89.23 000001090098-3562500630
2024 6 FD04 00 E121 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504654 $17.45 000001090098-3562500630
2024 6 FD04 00 E122 D 1354301D 042 12/22/2023 1060 RDWAY PLANS-FINAL-DRAINAGE SEC CA-XR122N1062335504654 $789.63 000001090098-3562500630
2024 6 FD04 00 E122 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504654 $154.45 000001090098-3562500630
2024 6 FD04 00 E123 D 1354301D 042 12/22/2023 1060 RDWAY PLANS-FINAL-DRAINAGE SEC CA-XR122N1062335504654 $116.94 000001090098-3562500630
2024 6 FD04 00 E123 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504654 $22.51 000001090098-3562500630
2024 6 FD04 00 E124 D 1354301D 042 12/22/2023 1060 RDWAY PLANS-FINAL-DRAINAGE SEC CA-XR122N1062335504654 $0.30 000001090098-3562500630
2024 6 FD04 00 E122 D 1354301D 042 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504601 $205.31 000001080408-3562500636
2024 6 FD04 00 E123 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504645 $84.19 000001088999-3562500610
2024 6 FD04 00 E124 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504654 $0.05 000001090098-3562500630
2024 6 FD04 00 E122 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504601 $55.27 000001080408-3562500636
2024 6 FD04 00 E124 D 1354301D 042 12/22/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR122N1062335504645 $0.81 000001088999-3562500610
2024 6 FD04 00 E123 D 1354301D 042 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504601 $30.43 000001080408-3562500636
2024 6 FD04 00 E124 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504645 $0.18 000001088999-3562500610
2024 6 FD04 00 E123 D 1354301D 042 12/22/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122N1062335504601 $8.05 000001080408-3562500636
2024 6 FD04 00 E124 D 1354301D 042 12/22/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122N1062335504601 $0.08 000001080408-3562500636
2024 6 FD04 01 E143 D 1354301D 042 12/21/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400120978 PON22200001500 HDR ENGINEERING INC $49,500.00 Graves Co 1-80130
2024 6 FD04 01 E143 D 1354301D 042 12/21/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400126017 PON22200001500 HDR ENGINEERING INC $65,100.00 Graves Co 1-80130
2024 6 FD04 00 E111 D 1354301D 042 12/11/2023 1060 RDWAY PLANS-FINAL-DRAINAGE SEC CA-XR121N1062334203657 $477.37 000001090098-3562500630
2024 6 FD04 00 E111 D 1354301D 042 12/11/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR121N1062334203647 $908.73 000001088999-3562500610
2024 6 FD04 00 E111 D 1354301D 042 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203657 $184.25 000001090098-3562500630
2024 6 FD04 00 E111 D 1354301D 042 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203647 $334.40 000001088999-3562500610
2024 6 FD04 00 E121 D 1354301D 042 12/11/2023 1060 RDWAY PLANS-FINAL-DRAINAGE SEC CA-XR121N1062334203657 $35.25 000001090098-3562500630
2024 6 FD04 00 E121 D 1354301D 042 12/11/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR121N1062334203647 $66.50 000001088999-3562500610
2024 6 FD04 00 E121 D 1354301D 042 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203657 $13.60 000001090098-3562500630
2024 6 FD04 00 E121 D 1354301D 042 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203647 $24.68 000001088999-3562500610
2024 6 FD04 00 E122 D 1354301D 042 12/11/2023 1060 RDWAY PLANS-FINAL-DRAINAGE SEC CA-XR121N1062334203657 $315.85 000001090098-3562500630
2024 6 FD04 00 E122 D 1354301D 042 12/11/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR121N1062334203647 $601.31 000001088999-3562500610
2024 6 FD04 00 E122 D 1354301D 042 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203657 $121.92 000001090098-3562500630
2024 6 FD04 00 E122 D 1354301D 042 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203647 $221.26 000001088999-3562500610
2024 6 FD04 00 E123 D 1354301D 042 12/11/2023 1060 RDWAY PLANS-FINAL-DRAINAGE SEC CA-XR121N1062334203657 $46.89 000001090098-3562500630
2024 6 FD04 00 E123 D 1354301D 042 12/11/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR121N1062334203647 $149.76 000001088999-3562500610
2024 6 FD04 00 E123 D 1354301D 042 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203657 $17.77 000001090098-3562500630
2024 6 FD04 00 E123 D 1354301D 042 12/11/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121N1062334203647 $55.39 000001088999-3562500610
2024 5 FD04 00 E111 D 1354301D 042 11/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111N1062331201509 $875.18 000001088999-3562500610
2024 5 FD04 00 E111 D 1354301D 042 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201509 $45.69 000001088999-3562500610
2024 5 FD04 00 E121 D 1354301D 042 11/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111N1062331201509 $65.21 000001088999-3562500610
2024 5 FD04 00 E121 D 1354301D 042 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201509 $3.42 000001088999-3562500610
2024 5 FD04 00 E122 D 1354301D 042 11/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111N1062331201509 $579.13 000001088999-3562500610
2024 5 FD04 00 E122 D 1354301D 042 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201509 $30.24 000001088999-3562500610
2024 5 FD04 00 E123 D 1354301D 042 11/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR111N1062331201509 $147.55 000001088999-3562500610
2024 5 FD04 00 E123 D 1354301D 042 11/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111N1062331201509 $7.68 000001088999-3562500610
2024 4 FD04 00 E111 D 1354301D 042 10/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101N1062328009722 $2,454.63 000001088999-3562500610
2024 4 FD04 00 E111 D 1354301D 042 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009722 $217.05 000001088999-3562500610
2024 4 FD04 00 E121 D 1354301D 042 10/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101N1062328009722 $178.59 000001088999-3562500610
2024 4 FD04 00 E121 D 1354301D 042 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009722 $16.03 000001088999-3562500610
2024 4 FD04 00 E122 D 1354301D 042 10/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101N1062328009722 $1,624.23 000001088999-3562500610
2024 4 FD04 00 E122 D 1354301D 042 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009722 $143.63 000001088999-3562500610
2024 4 FD04 00 E123 D 1354301D 042 10/9/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR101N1062328009722 $364.45 000001088999-3562500610
2024 4 FD04 00 E123 D 1354301D 042 10/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101N1062328009722 $36.80 000001088999-3562500610
2024 3 FD04 00 E123 D 1354301D 042 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208452 $37.52 000001088999-3562500610
2024 3 FD04 00 E124 D 1354301D 042 9/29/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062327208452 $0.47 000001088999-3562500610
2024 3 FD04 00 E124 D 1354301D 042 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208452 $0.07 000001088999-3562500610
2024 3 FD04 00 E111 D 1354301D 042 9/29/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062327208452 $1,415.06 000001088999-3562500610
2024 3 FD04 00 E111 D 1354301D 042 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208452 $234.67 000001088999-3562500610
2024 3 FD04 00 E121 D 1354301D 042 9/29/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062327208452 $103.55 000001088999-3562500610
2024 3 FD04 00 E121 D 1354301D 042 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208452 $17.23 000001088999-3562500610
2024 3 FD04 00 E122 D 1354301D 042 9/29/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062327208452 $936.24 000001088999-3562500610
2024 3 FD04 00 E122 D 1354301D 042 9/29/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062327208452 $155.28 000001088999-3562500610
2024 3 FD04 00 E123 D 1354301D 042 9/29/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062327208452 $227.30 000001088999-3562500610
2024 3 FD04 00 E123 D 1354301D 042 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507101 ($37.52) 000001088999-3562500610
2024 3 FD04 00 E124 D 1354301D 042 9/28/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062326507101 ($0.47) 000001088999-3562500610
2024 3 FD04 00 E124 D 1354301D 042 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507101 ($0.07) 000001088999-3562500610
2024 3 FD04 00 E111 D 1354301D 042 9/28/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062326507101 ($1,415.06) 000001088999-3562500610
2024 3 FD04 00 E111 D 1354301D 042 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507101 ($234.67) 000001088999-3562500610
2024 3 FD04 00 E121 D 1354301D 042 9/28/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062326507101 ($103.55) 000001088999-3562500610
2024 3 FD04 00 E121 D 1354301D 042 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507101 ($17.23) 000001088999-3562500610
2024 3 FD04 00 E122 D 1354301D 042 9/28/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062326507101 ($936.24) 000001088999-3562500610
2024 3 FD04 00 E122 D 1354301D 042 9/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507101 ($155.28) 000001088999-3562500610
2024 3 FD04 00 E123 D 1354301D 042 9/28/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062326507101 ($227.30) 000001088999-3562500610
2024 3 FD04 01 E143 D 1354301D 042 9/25/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400055806 PON22200001500 HDR ENGINEERING INC $51,000.00 Graves Co 1-80130
2024 3 FD04 00 E123 D 1354301D 042 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507101 $37.52 000001088999-3562500610
2024 3 FD04 00 E124 D 1354301D 042 9/25/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062326507101 $0.47 000001088999-3562500610
2024 3 FD04 00 E124 D 1354301D 042 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507101 $0.07 000001088999-3562500610
2024 3 FD04 00 E111 D 1354301D 042 9/25/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062326507101 $1,415.06 000001088999-3562500610
2024 3 FD04 00 E111 D 1354301D 042 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507101 $234.67 000001088999-3562500610
2024 3 FD04 00 E121 D 1354301D 042 9/25/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062326507101 $103.55 000001088999-3562500610
2024 3 FD04 00 E121 D 1354301D 042 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507101 $17.23 000001088999-3562500610
2024 3 FD04 00 E122 D 1354301D 042 9/25/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062326507101 $936.24 000001088999-3562500610
2024 3 FD04 00 E122 D 1354301D 042 9/25/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092N1062326507101 $155.28 000001088999-3562500610
2024 3 FD04 00 E123 D 1354301D 042 9/25/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR092N1062326507101 $227.30 000001088999-3562500610
2024 3 FD04 00 E121 D 1354301D 042 9/19/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091N1062325106131 $83.54 000001088999-3562500610
2024 3 FD04 00 E121 D 1354301D 042 9/19/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106131 $7.97 000001088999-3562500610
2024 3 FD04 00 E122 D 1354301D 042 9/19/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091N1062325106131 $744.85 000001088999-3562500610
2024 3 FD04 00 E122 D 1354301D 042 9/19/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106131 $70.66 000001088999-3562500610
2024 3 FD04 00 E123 D 1354301D 042 9/19/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091N1062325106131 $191.02 000001088999-3562500610
2024 3 FD04 00 E123 D 1354301D 042 9/19/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106131 $18.16 000001088999-3562500610
2024 3 FD04 00 E111 D 1354301D 042 9/19/2023 5021 GEOTECH INVEST STRUCTURE (DESI CA-XR091N1062325106130 $1,125.67 000001088999-3562500610
2024 3 FD04 00 E111 D 1354301D 042 9/19/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091N1062325106130 $106.78 000001088999-3562500610
2024 2 FD04 00 E111 D 1354301D 042 8/24/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR082N1062323504932 $34.80 000001080575-3562500061
2024 2 FD04 00 E111 D 1354301D 042 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504932 $10.42 000001080575-3562500061
2024 2 FD04 00 E121 D 1354301D 042 8/24/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR082N1062323504932 $2.59 000001080575-3562500061
2024 2 FD04 00 E121 D 1354301D 042 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504932 $0.78 000001080575-3562500061
2024 2 FD04 00 E122 D 1354301D 042 8/24/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR082N1062323504932 $22.98 000001080575-3562500061
2024 2 FD04 00 E122 D 1354301D 042 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504932 $6.90 000001080575-3562500061
2024 2 FD04 00 E123 D 1354301D 042 8/24/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR082N1062323504932 $4.68 000001080575-3562500061
2024 2 FD04 00 E123 D 1354301D 042 8/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082N1062323504932 $1.38 000001080575-3562500061
2024 2 FD04 00 E124 D 1354301D 042 8/24/2023 0070 ENV STUDIES-HIST/CULTURAL CA-XR082N1062323504932 $0.01 000001080575-3562500061
2024 2 FD04 01 E143 D 1354301D 042 8/14/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400024049 PON22200001500 HDR ENGINEERING INC $56,000.00 Graves Co 1-80130
2024 1 FD04 01 E143 D 1354301D 042 7/14/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2400010143 PON22200001500 HDR ENGINEERING INC $55,000.00 Graves Co 1-80130
2024 1 FD04 01 E147 D 1354301D 042 7/7/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF PRC-2400003864 PAXTON MEDIA GROUP LLC $622.50 ad for meeting about KY303 Corridor & KY121(042)
2024 1 FD04 01 E147 D 1354301D 042 7/7/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF PRC-2400003833 Kentucky Pubishing Inc. $361.00 ad for meeting about KY303 Corridor & KY121(042) 04-21-23
2024 1 FD04 01 E147 D 1354301D 042 7/7/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF PRC-2400003833 Kentucky Pubishing Inc. $361.00 ad for meeting about KY303 Corridor & KY121(042) 05-05-23
2024 1 FD04 01 E147 D 1354301D 042 7/7/2023 1050 RDWAY PLANS-FINAL-PLANS & PROF PRC-2400003833 Kentucky Pubishing Inc. $181.00 ad for meeting about KY303 Corridor & KY121(042) 05-12-23
2023 12 FD04 01 E143 D 1354301D 042 6/19/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300248231 PON22200001500 HDR ENGINEERING INC $59,900.00 Graves Co 1-80130
2023 12 FD04 00 E111 D 1354301D 042 6/15/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR061N1062315810131 $262.71 000001080408-3562500636
2023 12 FD04 00 E111 D 1354301D 042 6/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810131 $38.65 000001080408-3562500636
2023 12 FD04 00 E121 D 1354301D 042 6/15/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR061N1062315810131 $19.62 000001080408-3562500636
2023 12 FD04 00 E121 D 1354301D 042 6/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810131 $2.89 000001080408-3562500636
2023 12 FD04 00 E122 D 1354301D 042 6/15/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR061N1062315810131 $204.89 000001080408-3562500636
2023 12 FD04 00 E122 D 1354301D 042 6/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810131 $30.15 000001080408-3562500636
2023 12 FD04 00 E123 D 1354301D 042 6/15/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR061N1062315810131 $29.99 000001080408-3562500636
2023 12 FD04 00 E123 D 1354301D 042 6/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061N1062315810131 $4.35 000001080408-3562500636
2023 11 FD04 01 E143 D 1354301D 042 5/18/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300222829 PON22200001500 HDR ENGINEERING INC $22,600.00 Graves Co 1-80130
2023 10 FD04 00 E111 D 1354301D 042 4/14/2023 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041N1062309605795 $867.68 000001086848-3562500610
2023 10 FD04 00 E111 D 1354301D 042 4/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605795 $1.40 000001086848-3562500610
2023 10 FD04 00 E112 D 1354301D 042 4/14/2023 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041N1062309605795 $90.20 000001086848-3562500610
2023 10 FD04 00 E121 D 1354301D 042 4/14/2023 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041N1062309605795 $70.89 000001086848-3562500610
2023 10 FD04 00 E121 D 1354301D 042 4/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605795 $0.10 000001086848-3562500610
2023 10 FD04 00 E122 D 1354301D 042 4/14/2023 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041N1062309605795 $676.79 000001086848-3562500610
2023 10 FD04 00 E122 D 1354301D 042 4/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605795 $1.09 000001086848-3562500610
2023 10 FD04 00 E123 D 1354301D 042 4/14/2023 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041N1062309605795 $102.06 000001086848-3562500610
2023 10 FD04 00 E123 D 1354301D 042 4/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605795 $0.23 000001086848-3562500610
2023 9 FD04 00 E123 D 1354301D 042 3/31/2023 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR032N1062308304678 $174.79 000001086848-3562500610
2023 9 FD04 00 E123 D 1354301D 042 3/31/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304678 $6.51 000001086848-3562500610
2023 9 FD04 00 E124 D 1354301D 042 3/31/2023 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR032N1062308304678 $0.26 000001086848-3562500610
2023 9 FD04 00 E124 D 1354301D 042 3/31/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304678 $0.01 000001086848-3562500610
2023 9 FD04 00 E111 D 1354301D 042 3/31/2023 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR032N1062308304678 $1,043.84 000001086848-3562500610
2023 9 FD04 00 E111 D 1354301D 042 3/31/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304678 $39.20 000001086848-3562500610
2023 9 FD04 00 E112 D 1354301D 042 3/31/2023 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR032N1062308304678 $721.56 000001086848-3562500610
2023 9 FD04 00 E112 D 1354301D 042 3/31/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304678 $80.17 000001086848-3562500610
2023 9 FD04 00 E121 D 1354301D 042 3/31/2023 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR032N1062308304678 $127.30 000001086848-3562500610
2023 9 FD04 00 E121 D 1354301D 042 3/31/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304678 $8.84 000001086848-3562500610
2023 9 FD04 00 E122 D 1354301D 042 3/31/2023 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR032N1062308304678 $814.52 000001086848-3562500610
2023 9 FD04 00 E122 D 1354301D 042 3/31/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032N1062308304678 $30.58 000001086848-3562500610
2023 9 FD04 01 E143 D 1354301D 042 3/20/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300172524 PON22200001500 HDR ENGINEERING INC $1,422.30 Graves Co 1-80130
2023 9 FD04 00 E111 D 1354301D 042 3/1/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR022N1062305302452 $343.64 000001083236-3562500061
2023 9 FD04 00 E121 D 1354301D 042 3/1/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR022N1062305302452 $25.92 000001083236-3562500061
2023 9 FD04 00 E122 D 1354301D 042 3/1/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR022N1062305302452 $268.04 000001083236-3562500061
2023 9 FD04 00 E123 D 1354301D 042 3/1/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR022N1062305302452 $69.98 000001083236-3562500061
2023 9 FD04 00 E124 D 1354301D 042 3/1/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR022N1062305302452 $0.18 000001083236-3562500061
2023 8 FD04 00 E111 D 1354301D 042 2/23/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR022N1062305302440 $61.44 000001080408-3562500636
2023 8 FD04 00 E111 D 1354301D 042 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302440 $20.88 000001080408-3562500636
2023 8 FD04 00 E121 D 1354301D 042 2/23/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR022N1062305302440 $4.66 000001080408-3562500636
2023 8 FD04 00 E121 D 1354301D 042 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302440 $1.58 000001080408-3562500636
2023 8 FD04 00 E122 D 1354301D 042 2/23/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR022N1062305302440 $47.90 000001080408-3562500636
2023 8 FD04 00 E122 D 1354301D 042 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302440 $16.29 000001080408-3562500636
2023 8 FD04 00 E123 D 1354301D 042 2/23/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR022N1062305302440 $7.03 000001080408-3562500636
2023 8 FD04 00 E123 D 1354301D 042 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302440 $2.35 000001080408-3562500636
2023 8 FD04 00 E124 D 1354301D 042 2/23/2023 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR022N1062305302440 $0.02 000001080408-3562500636
2023 8 FD04 00 E124 D 1354301D 042 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302440 $0.01 000001080408-3562500636
2023 8 FD04 01 E143 D 1354301D 042 2/10/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300149483 PON22200001500 HDR ENGINEERING INC $39,827.70 Graves Co 1-80130
2023 8 FD04 00 E111 D 1354301D 042 2/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR021N1062303901423 $315.04 000001083236-3562500061
2023 8 FD04 00 E111 D 1354301D 042 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901423 $28.56 000001083236-3562500061
2023 8 FD04 00 E121 D 1354301D 042 2/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR021N1062303901423 $23.32 000001083236-3562500061
2023 8 FD04 00 E121 D 1354301D 042 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901423 $2.11 000001083236-3562500061
2023 8 FD04 00 E122 D 1354301D 042 2/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR021N1062303901423 $245.70 000001083236-3562500061
2023 8 FD04 00 E122 D 1354301D 042 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901423 $22.28 000001083236-3562500061
2023 8 FD04 00 E123 D 1354301D 042 2/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR021N1062303901423 $64.23 000001083236-3562500061
2023 8 FD04 00 E123 D 1354301D 042 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901423 $5.74 000001083236-3562500061
2023 7 FD04 01 E143 D 1354301D 042 1/26/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300129596 PON22200001500 HDR ENGINEERING INC $27,000.00 Graves Co 1-80130
2023 7 FD04 00 E111 D 1354301D 042 1/12/2023 0010 ENV STUDIES-UST/HZM CA-XR011N1062300610248 $131.42 000001080694-3562500061
2023 7 FD04 00 E111 D 1354301D 042 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610248 $49.17 000001080694-3562500061
2023 7 FD04 00 E121 D 1354301D 042 1/12/2023 0010 ENV STUDIES-UST/HZM CA-XR011N1062300610248 $9.30 000001080694-3562500061
2023 7 FD04 00 E121 D 1354301D 042 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610248 $3.48 000001080694-3562500061
2023 7 FD04 00 E122 D 1354301D 042 1/12/2023 0010 ENV STUDIES-UST/HZM CA-XR011N1062300610248 $102.47 000001080694-3562500061
2023 7 FD04 00 E122 D 1354301D 042 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610248 $38.35 000001080694-3562500061
2023 7 FD04 00 E123 D 1354301D 042 1/12/2023 0010 ENV STUDIES-UST/HZM CA-XR011N1062300610248 $27.22 000001080694-3562500061
2023 7 FD04 00 E123 D 1354301D 042 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610248 $10.07 000001080694-3562500061
2023 6 FD04 01 E143 D 1354301D 042 12/13/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300108417 PON22200001500 HDR ENGINEERING INC $34,702.00 Graves Co 1-80130
2023 5 FD04 00 E111 D 1354301D 042 11/29/2022 0060 ENV STUDIES-ARCHAEOLOGY CA-XR112M1062232607147 $399.26 000001080637-3562500061
2023 5 FD04 00 E111 D 1354301D 042 11/29/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607147 $64.59 000001080637-3562500061
2023 5 FD04 00 E121 D 1354301D 042 11/29/2022 0060 ENV STUDIES-ARCHAEOLOGY CA-XR112M1062232607147 $30.10 000001080637-3562500061
2023 5 FD04 00 E121 D 1354301D 042 11/29/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607147 $4.86 000001080637-3562500061
2023 5 FD04 00 E122 D 1354301D 042 11/29/2022 0060 ENV STUDIES-ARCHAEOLOGY CA-XR112M1062232607147 $311.34 000001080637-3562500061
2023 5 FD04 00 E122 D 1354301D 042 11/29/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607147 $50.38 000001080637-3562500061
2023 5 FD04 00 E123 D 1354301D 042 11/29/2022 0060 ENV STUDIES-ARCHAEOLOGY CA-XR112M1062232607147 $52.78 000001080637-3562500061
2023 5 FD04 00 E123 D 1354301D 042 11/29/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607147 $8.41 000001080637-3562500061
2023 5 FD04 00 E124 D 1354301D 042 11/29/2022 0060 ENV STUDIES-ARCHAEOLOGY CA-XR112M1062232607147 $0.13 000001080637-3562500061
2023 5 FD04 00 E124 D 1354301D 042 11/29/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607147 $0.02 000001080637-3562500061
2023 5 FD04 00 E111 D 1354301D 042 11/23/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112M1062232607146 $320.75 000001080408-3562500630
2023 5 FD04 00 E111 D 1354301D 042 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607146 $152.77 000001080408-3562500630
2023 5 FD04 00 E121 D 1354301D 042 11/23/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112M1062232607146 $24.27 000001080408-3562500630
2023 5 FD04 00 E121 D 1354301D 042 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607146 $11.53 000001080408-3562500636
2023 5 FD04 00 E122 D 1354301D 042 11/23/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112M1062232607146 $250.13 000001080408-3562500630
2023 5 FD04 00 E122 D 1354301D 042 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607146 $119.16 000001080408-3562500636
2023 5 FD04 00 E123 D 1354301D 042 11/23/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112M1062232607146 $34.23 000001080408-3562500630
2023 5 FD04 00 E123 D 1354301D 042 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607146 $16.09 000001080408-3562500630
2023 5 FD04 00 E124 D 1354301D 042 11/23/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112M1062232607146 $0.09 000001080408-3562500630
2023 5 FD04 00 E124 D 1354301D 042 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607146 $0.04 000001080408-3562500630
2023 5 FD04 01 E143 D 1354301D 042 11/9/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300085404 PON22200001500 HDR ENGINEERING INC $32,800.00 Graves Co 1-80130
2023 4 FD04 00 E111 D 1354301D 042 10/24/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR102M1062229405058 $189.00 000001083236-3562500061
2023 4 FD04 00 E121 D 1354301D 042 10/24/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR102M1062229405058 $14.25 000001083236-3562500061
2023 4 FD04 00 E122 D 1354301D 042 10/24/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR102M1062229405058 $147.42 000001083236-3562500061
2023 4 FD04 00 E123 D 1354301D 042 10/24/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR102M1062229405058 $35.35 000001083236-3562500061
2023 4 FD04 00 E124 D 1354301D 042 10/24/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR102M1062229405058 $0.10 000001083236-3562500061
2023 4 FD04 01 E143 D 1354301D 042 10/11/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300063676 PON22200001500 HDR ENGINEERING INC $46,795.00 Graves Co 1-80130
2023 3 FD04 01 E143 D 1354301D 042 9/19/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300049184 PON22200001500 HDR ENGINEERING INC $22,700.00 Graves Co 1-80130
2023 3 FD04 00 E111 D 1354301D 042 9/14/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091M1062225101618 $1,282.94 000001080408-3562500636
2023 3 FD04 00 E111 D 1354301D 042 9/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101618 $109.95 000001080408-3562500636
2023 3 FD04 00 E121 D 1354301D 042 9/14/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091M1062225101618 $96.94 000001080408-3562500636
2023 3 FD04 00 E121 D 1354301D 042 9/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101618 $8.31 000001080408-3562500636
2023 3 FD04 00 E122 D 1354301D 042 9/14/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091M1062225101618 $1,000.67 000001080408-3562500636
2023 3 FD04 00 E122 D 1354301D 042 9/14/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101618 $85.75 000001080408-3562500636
2023 3 FD04 00 E123 D 1354301D 042 9/14/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR091M1062225101618 $130.43 000001080408-3562500636
2023 3 FD04 00 E123 D 1354301D 042 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101619 $11.01 000001080408-3562500636
2023 2 FD04 01 E143 D 1354301D 042 8/12/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300025816 PON22200001500 HDR ENGINEERING INC $54,500.00 Graves Co 1-80130
2023 2 FD04 01 E143 D 1354301D 042 8/12/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300025816 PON22200001500 HDR ENGINEERING INC $20,205.00 Graves Co 1-80130
2023 2 FD04 00 E111 D 1354301D 042 8/10/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR081M1062222110131 $540.00 000001083236-3562500061
2023 2 FD04 00 E121 D 1354301D 042 8/10/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR081M1062222110131 $39.93 000001083236-3562500061
2023 2 FD04 00 E122 D 1354301D 042 8/10/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR081M1062222110131 $421.20 000001083236-3562500061
2023 2 FD04 00 E123 D 1354301D 042 8/10/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR081M1062222110131 $106.06 000001083236-3562500061
2023 1 FD04 01 E143 D 1354301D 042 7/13/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300006927 PON22200001500 HDR ENGINEERING INC $55,300.00 Graves Co 1-80130
2023 1 FD04 00 E111 D 1354301D 042 7/12/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR071M1062219207874 $227.50 000001080575-3562500061
2023 1 FD04 00 E111 D 1354301D 042 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207874 $22.75 000001080575-3562500061
2023 1 FD04 00 E121 D 1354301D 042 7/12/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR071M1062219207874 $16.71 000001080575-3562500061
2023 1 FD04 00 E121 D 1354301D 042 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207874 $1.67 000001080575-3562500061
2023 1 FD04 00 E122 D 1354301D 042 7/12/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR071M1062219207874 $191.04 000001080575-3562500061
2023 1 FD04 00 E122 D 1354301D 042 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207874 $19.10 000001080575-3562500061
2023 1 FD04 00 E123 D 1354301D 042 7/12/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR071M1062219207874 $32.19 000001080575-3562500061
2023 1 FD04 00 E123 D 1354301D 042 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207874 $3.17 000001080575-3562500061
2022 12 FD04 00 E111 D 1354301D 042 6/27/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR062M1062217506766 $227.50 000001080575-3562500061
2022 12 FD04 00 E111 D 1354301D 042 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506766 $22.75 000001080575-3562500061
2022 12 FD04 00 E121 D 1354301D 042 6/27/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR062M1062217506766 $16.94 000001080575-3562500061
2022 12 FD04 00 E121 D 1354301D 042 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506766 $1.69 000001080575-3562500061
2022 12 FD04 00 E122 D 1354301D 042 6/27/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR062M1062217506766 $191.03 000001080575-3562500061
2022 12 FD04 00 E122 D 1354301D 042 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506766 $19.10 000001080575-3562500061
2022 12 FD04 00 E123 D 1354301D 042 6/27/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR062M1062217506766 $32.18 000001080575-3562500061
2022 12 FD04 00 E123 D 1354301D 042 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506766 $3.17 000001080575-3562500061
2022 12 FD04 00 E111 D 1354301D 042 6/27/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR062M1062217506795 $454.55 000001083236-3562500061
2022 12 FD04 00 E124 D 1354301D 042 6/27/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR062M1062217506766 $0.09 000001080575-3562500061
2022 12 FD04 00 E124 D 1354301D 042 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506766 $0.01 000001080575-3562500061
2022 12 FD04 00 E121 D 1354301D 042 6/27/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR062M1062217506795 $34.22 000001083236-3562500061
2022 12 FD04 00 E122 D 1354301D 042 6/27/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR062M1062217506795 $381.69 000001083236-3562500061
2022 12 FD04 00 E123 D 1354301D 042 6/27/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR062M1062217506795 $96.42 000001083236-3562500061
2022 12 FD04 00 E124 D 1354301D 042 6/27/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR062M1062217506795 $0.28 000001083236-3562500061
2022 12 FD04 01 E143 D 1354301D 042 6/8/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200223715 PON22200001500 HDR ENGINEERING INC $48,320.00 Graves Co 1-80130
2022 11 FD04 01 E143 D 1354301D 042 5/11/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200204454 PON22200001500 HDR ENGINEERING INC $36,470.00 Graves Co 1-80130
2022 10 FD04 01 E143 D 1354301D 042 4/19/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200186035 PON22200001500 HDR ENGINEERING INC $21,660.00 Graves Co 1-80130
2022 9 FD04 01 E143 D 1354301D 042 3/21/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200168366 PON22200001500 HDR ENGINEERING INC $22,350.00 Graves Co 1-80130
2022 6 FD04 00 E111 D 1354301D 042 12/8/2021 0010 ENV STUDIES-UST/HZM CA-XR121L1062134103574 $260.66 000001080694-3562500061
2022 6 FD04 00 E111 D 1354301D 042 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103574 $312.79 000001080694-3562500061
2022 6 FD04 00 E121 D 1354301D 042 12/8/2021 0010 ENV STUDIES-UST/HZM CA-XR121L1062134103574 $18.40 000001080694-3562500061
2022 6 FD04 00 E121 D 1354301D 042 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103574 $22.07 000001080694-3562500061
2022 6 FD04 00 E122 D 1354301D 042 12/8/2021 0010 ENV STUDIES-UST/HZM CA-XR121L1062134103574 $218.88 000001080694-3562500061
2022 6 FD04 00 E122 D 1354301D 042 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103574 $262.65 000001080694-3562500061
2022 6 FD04 00 E123 D 1354301D 042 12/8/2021 0010 ENV STUDIES-UST/HZM CA-XR121L1062134103574 $49.20 000001080694-3562500061
2022 6 FD04 00 E123 D 1354301D 042 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103574 $57.81 000001080694-3562500061
2022 6 FD04 00 E111 D 1354301D 042 12/8/2021 0060 ENV STUDIES-ARCHAEOLOGY CA-XR121L1062134103571 $503.98 000001080637-3562500061
2022 6 FD04 00 E111 D 1354301D 042 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103571 $323.57 000001080637-3562500061
2022 6 FD04 00 E121 D 1354301D 042 12/8/2021 0060 ENV STUDIES-ARCHAEOLOGY CA-XR121L1062134103571 $37.60 000001080637-3562500061
2022 6 FD04 00 E121 D 1354301D 042 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103571 $24.14 000001080637-3562500061
2022 6 FD04 00 E122 D 1354301D 042 12/8/2021 0060 ENV STUDIES-ARCHAEOLOGY CA-XR121L1062134103571 $423.20 000001080637-3562500061
2022 6 FD04 00 E122 D 1354301D 042 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103571 $271.70 000001080637-3562500061
2022 6 FD04 00 E123 D 1354301D 042 12/8/2021 0060 ENV STUDIES-ARCHAEOLOGY CA-XR121L1062134103571 $70.68 000001080637-3562500061
2022 6 FD04 00 E123 D 1354301D 042 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103571 $44.41 000001080637-3562500061
2022 5 FD04 00 E122 D 1354301D 042 11/29/2021 0060 ENV STUDIES-ARCHAEOLOGY CA-XR112L1062132602555 $211.89 000001080637-3562500061
2022 5 FD04 00 E122 D 1354301D 042 11/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602555 $36.67 000001080637-3562500061
2022 5 FD04 00 E123 D 1354301D 042 11/29/2021 0060 ENV STUDIES-ARCHAEOLOGY CA-XR112L1062132602555 $35.18 000001080637-3562500061
2022 5 FD04 00 E123 D 1354301D 042 11/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602555 $6.00 000001080637-3562500061
2022 5 FD04 00 E124 D 1354301D 042 11/29/2021 0060 ENV STUDIES-ARCHAEOLOGY CA-XR112L1062132602555 $0.10 000001080637-3562500061
2022 5 FD04 00 E124 D 1354301D 042 11/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602555 $0.01 000001080637-3562500061
2022 5 FD04 00 E111 D 1354301D 042 11/29/2021 0060 ENV STUDIES-ARCHAEOLOGY CA-XR112L1062132602555 $252.05 000001080637-3562500061
2022 5 FD04 00 E111 D 1354301D 042 11/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602555 $43.67 000001080637-3562500061
2022 5 FD04 00 E121 D 1354301D 042 11/29/2021 0060 ENV STUDIES-ARCHAEOLOGY CA-XR112L1062132602555 $18.98 000001080637-3562500061
2022 5 FD04 00 E121 D 1354301D 042 11/29/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602555 $3.28 000001080637-3562500061
2022 5 FD04 00 E123 D 1354301D 042 11/23/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112L1062132602543 $18.73 000001080408-3562500636
2022 5 FD04 00 E123 D 1354301D 042 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602543 $2.86 000001080408-3562500636
2022 5 FD04 00 E124 D 1354301D 042 11/23/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112L1062132602543 $0.05 000001080408-3562500636
2022 5 FD04 00 E124 D 1354301D 042 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602543 $0.01 000001080408-3562500636
2022 5 FD04 00 E111 D 1354301D 042 11/23/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112L1062132602543 $175.14 000001080408-3562500636
2022 5 FD04 00 E111 D 1354301D 042 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602543 $27.15 000001080408-3562500636
2022 5 FD04 00 E121 D 1354301D 042 11/23/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112L1062132602543 $13.24 000001080408-3562500636
2022 5 FD04 00 E121 D 1354301D 042 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602543 $2.06 000001080408-3562500636
2022 5 FD04 00 E122 D 1354301D 042 11/23/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR112L1062132602543 $147.06 000001080408-3562500636
2022 5 FD04 00 E111 D 1354301D 042 11/23/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR112L1062132602549 $227.50 000001080575-3562500061
2022 5 FD04 00 E111 D 1354301D 042 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602549 $22.75 000001080575-3562500061
2022 5 FD04 00 E121 D 1354301D 042 11/23/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR112L1062132602549 $16.93 000001080575-3562500061
2022 5 FD04 00 E121 D 1354301D 042 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602549 $1.69 000001080575-3562500061
2022 5 FD04 00 E122 D 1354301D 042 11/23/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR112L1062132602549 $191.03 000001080575-3562500061
2022 5 FD04 00 E122 D 1354301D 042 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602549 $19.10 000001080575-3562500061
2022 5 FD04 00 E123 D 1354301D 042 11/23/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR112L1062132602549 $31.41 000001080575-3562500061
2022 5 FD04 00 E123 D 1354301D 042 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602549 $3.09 000001080575-3562500061
2022 5 FD04 00 E124 D 1354301D 042 11/23/2021 0070 ENV STUDIES-HIST/CULTURAL CA-XR112L1062132602549 $0.09 000001080575-3562500061
2022 5 FD04 00 E124 D 1354301D 042 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602549 $0.01 000001080575-3562500061
2022 5 FD04 00 E122 D 1354301D 042 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602543 $22.80 000001080408-3562500636