The Commonwealth pays employees on a semi-monthly basis with a scheduled pay day on the 15th and 30th of each month. The two monthly pay periods are from the 1st to the 15th of the month and the 16th through the last day of the month. Pay check distribution is delayed by one pay period to allow for system processing. For example work performed during the 1st to the 15th day of the month is paid to the employee on the 30th of the month. Accordingly the cost accounting charges for labor costs posting in eMARS to operating accounts and highway projects are also delayed by approximately one pay period.
A good rule of measure is that the cost accounting charges for the pay period ending on the 15th of the month will post to eMARS by the 25th and those for the pay period ending on the last day of the month will post to eMARS by the 10th of the following month.

x close panel
Detailed Project Expenditure Report
Total E-MARS Expenditures for 1249801D = $764,191.18
Click here for Labor Costs Information
Year Month PBU Charge District Object Phase Program Code County Date ACT Activity Name Trans ID Reference # Vendor Name Expenditure Line Description
2024 10 FD52 07 E111 D 1249801D 011 4/26/2024 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042O1062411502727 $4,373.67 000001078602-3562507204
2024 10 FD52 07 E111 D 1249801D 011 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502727 $108.66 000001078602-3562507204
2024 10 FD52 07 E121 D 1249801D 011 4/26/2024 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042O1062411502727 $319.69 000001078602-3562507204
2024 10 FD52 07 E121 D 1249801D 011 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502727 $7.95 000001078602-3562507204
2024 10 FD52 07 E122 D 1249801D 011 4/26/2024 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042O1062411502727 $2,894.06 000001078602-3562507204
2024 10 FD52 07 E122 D 1249801D 011 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502727 $71.90 000001078602-3562507204
2024 10 FD52 07 E123 D 1249801D 011 4/26/2024 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042O1062411502727 $824.33 000001078602-3562507204
2024 10 FD52 07 E123 D 1249801D 011 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502727 $20.35 000001078602-3562507204
2024 10 FD52 07 E124 D 1249801D 011 4/26/2024 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042O1062411502727 $0.98 000001078602-3562507204
2024 10 FD52 07 E124 D 1249801D 011 4/26/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042O1062411502727 $0.02 000001078602-3562507204
2024 10 FD52 00 E111 D 1249801D 011 4/10/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041O1062410001613 $239.24 000001077076-3562500630
2024 10 FD52 00 E111 D 1249801D 011 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001613 $12.44 000001077076-3562500630
2024 10 FD52 00 E121 D 1249801D 011 4/10/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041O1062410001613 $16.84 000001077076-3562500630
2024 10 FD52 00 E121 D 1249801D 011 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001613 $0.88 000001077076-3562500630
2024 10 FD52 00 E122 D 1249801D 011 4/10/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041O1062410001613 $158.31 000001077076-3562500630
2024 10 FD52 00 E122 D 1249801D 011 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001613 $8.23 000001077076-3562500630
2024 10 FD52 00 E123 D 1249801D 011 4/10/2024 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041O1062410001613 $56.33 000001077076-3562500630
2024 10 FD52 00 E123 D 1249801D 011 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001613 $2.91 000001077076-3562500630
2024 10 FD52 07 E111 D 1249801D 011 4/10/2024 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041O1062410001615 $1,792.33 000001078602-3562507204
2024 10 FD52 07 E111 D 1249801D 011 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001615 $448.84 000001078602-3562507204
2024 10 FD52 07 E121 D 1249801D 011 4/10/2024 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041O1062410001615 $129.62 000001078602-3562507204
2024 10 FD52 07 E121 D 1249801D 011 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001615 $32.44 000001078602-3562507204
2024 10 FD52 07 E122 D 1249801D 011 4/10/2024 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041O1062410001615 $1,185.57 000001078602-3562507204
2024 10 FD52 07 E122 D 1249801D 011 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001615 $297.00 000001078602-3562507204
2024 10 FD52 07 E123 D 1249801D 011 4/10/2024 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041O1062410001615 $338.14 000001078602-3562507204
2024 10 FD52 07 E123 D 1249801D 011 4/10/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041O1062410001615 $84.08 000001078602-3562507204
2024 7 FD52 00 E111 D 1249801D 011 1/24/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR012O1062402306568 $568.58 000001076861-3562500061
2024 7 FD52 00 E111 D 1249801D 011 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306568 $126.21 000001076861-3562500061
2024 7 FD52 00 E121 D 1249801D 011 1/24/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR012O1062402306568 $40.72 000001076861-3562500061
2024 7 FD52 00 E121 D 1249801D 011 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306568 $9.04 000001076861-3562500061
2024 7 FD52 00 E122 D 1249801D 011 1/24/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR012O1062402306568 $376.17 000001076861-3562500061
2024 7 FD52 00 E122 D 1249801D 011 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306568 $83.51 000001076861-3562500061
2024 7 FD52 00 E123 D 1249801D 011 1/24/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR012O1062402306568 $153.78 000001076861-3562500061
2024 7 FD52 00 E123 D 1249801D 011 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306568 $33.89 000001076861-3562500061
2024 7 FD52 00 E124 D 1249801D 011 1/24/2024 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR012O1062402306568 $0.18 000001076861-3562500061
2024 7 FD52 00 E124 D 1249801D 011 1/24/2024 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012O1062402306568 $0.04 000001076861-3562500061
2023 11 FD52 07 E111 D 1249801D 011 5/15/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR051N1062312808056 $3,057.30 000001078602-3562507204
2023 11 FD52 07 E111 D 1249801D 011 5/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808056 $441.67 000001078602-3562507204
2023 11 FD52 07 E121 D 1249801D 011 5/15/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR051N1062312808056 $233.12 000001078602-3562507204
2023 11 FD52 07 E121 D 1249801D 011 5/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808056 $33.71 000001078602-3562507204
2023 11 FD52 07 E122 D 1249801D 011 5/15/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR051N1062312808056 $2,384.69 000001078602-3562507204
2023 11 FD52 07 E122 D 1249801D 011 5/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808056 $344.50 000001078602-3562507204
2023 11 FD52 07 E123 D 1249801D 011 5/15/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR051N1062312808056 $70.32 000001078602-3562507204
2023 11 FD52 07 E123 D 1249801D 011 5/15/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR051N1062312808056 $6.80 000001078602-3562507204
2023 10 FD52 07 E111 D 1249801D 011 4/28/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042N1062311106921 $2,673.74 000001078602-3562507204
2023 10 FD52 07 E111 D 1249801D 011 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106921 $278.84 000001078602-3562507204
2023 10 FD52 07 E121 D 1249801D 011 4/28/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042N1062311106921 $203.15 000001078602-3562507204
2023 10 FD52 07 E121 D 1249801D 011 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106921 $21.21 000001078602-3562507204
2023 10 FD52 07 E122 D 1249801D 011 4/28/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042N1062311106921 $2,085.22 000001078602-3562507204
2023 10 FD52 07 E122 D 1249801D 011 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106921 $217.50 000001078602-3562507204
2023 10 FD52 07 E123 D 1249801D 011 4/28/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042N1062311106921 $197.48 000001078602-3562507204
2023 10 FD52 07 E123 D 1249801D 011 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106921 $18.00 000001078602-3562507204
2023 10 FD52 07 E124 D 1249801D 011 4/28/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042N1062311106921 $1.32 000001078602-3562507204
2023 10 FD52 07 E124 D 1249801D 011 4/28/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042N1062311106921 $0.14 000001078602-3562507204
2023 10 FD52 07 E111 D 1249801D 011 4/14/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041N1062309605757 $902.53 000001078602-3562507204
2023 10 FD52 07 E111 D 1249801D 011 4/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605757 $1,263.54 000001078602-3562507204
2023 10 FD52 07 E121 D 1249801D 011 4/14/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041N1062309605757 $67.62 000001078602-3562507204
2023 10 FD52 07 E121 D 1249801D 011 4/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605757 $94.67 000001078602-3562507204
2023 10 FD52 07 E122 D 1249801D 011 4/14/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041N1062309605757 $703.97 000001078602-3562507204
2023 10 FD52 07 E122 D 1249801D 011 4/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605757 $985.56 000001078602-3562507204
2023 10 FD52 07 E123 D 1249801D 011 4/14/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041N1062309605757 $160.20 000001078602-3562507204
2023 10 FD52 07 E123 D 1249801D 011 4/14/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041N1062309605757 $217.15 000001078602-3562507204
2023 9 FD52 00 E111 D 1249801D 011 3/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR031N1062306703648 $478.62 000001076861-3562500061
2023 9 FD52 00 E111 D 1249801D 011 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703648 $34.13 000001076861-3562500061
2023 9 FD52 00 E121 D 1249801D 011 3/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR031N1062306703648 $33.41 000001076861-3562500061
2023 9 FD52 00 E121 D 1249801D 011 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703648 $2.38 000001076861-3562500061
2023 9 FD52 00 E122 D 1249801D 011 3/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR031N1062306703648 $373.32 000001076861-3562500061
2023 9 FD52 00 E122 D 1249801D 011 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703648 $26.62 000001076861-3562500061
2023 9 FD52 00 E123 D 1249801D 011 3/9/2023 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR031N1062306703648 $119.80 000001076861-3562500061
2023 9 FD52 00 E123 D 1249801D 011 3/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031N1062306703648 $8.48 000001076861-3562500061
2023 8 FD52 07 E111 D 1249801D 011 2/23/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR022N1062305302434 $1,465.50 000001078602-3562507204
2023 8 FD52 07 E111 D 1249801D 011 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302434 $109.50 000001078602-3562507204
2023 8 FD52 07 E121 D 1249801D 011 2/23/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR022N1062305302434 $112.12 000001078602-3562507204
2023 8 FD52 07 E121 D 1249801D 011 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302434 $8.38 000001078602-3562507204
2023 8 FD52 07 E122 D 1249801D 011 2/23/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR022N1062305302434 $1,143.09 000001078602-3562507204
2023 8 FD52 07 E122 D 1249801D 011 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302434 $85.41 000001078602-3562507204
2023 8 FD52 07 E123 D 1249801D 011 2/23/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR022N1062305302434 $46.57 000001078602-3562507204
2023 8 FD52 07 E123 D 1249801D 011 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302434 $4.87 000001078602-3562507204
2023 8 FD52 07 E124 D 1249801D 011 2/23/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR022N1062305302434 $0.75 000001078602-3562507204
2023 8 FD52 07 E124 D 1249801D 011 2/23/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022N1062305302434 $0.06 000001078602-3562507204
2023 8 FD52 07 E143 D 1249801D 011 2/20/2023 1550 DESIGN CONTRACTS-CONSULTANT PRC-2300153600 PON22200000620 GRW ENGINEERS INC $37,266.70 Preliminary Roadway Design
2023 8 FD52 07 E111 D 1249801D 011 2/9/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR021N1062303901406 $1,753.10 000001078602-3562507204
2023 8 FD52 07 E111 D 1249801D 011 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901406 $159.34 000001078602-3562507204
2023 8 FD52 07 E121 D 1249801D 011 2/9/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR021N1062303901406 $124.31 000001078602-3562507204
2023 8 FD52 07 E121 D 1249801D 011 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901406 $11.30 000001078602-3562507204
2023 8 FD52 07 E122 D 1249801D 011 2/9/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR021N1062303901406 $1,367.43 000001078602-3562507204
2023 8 FD52 07 E122 D 1249801D 011 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901406 $124.29 000001078602-3562507204
2023 8 FD52 07 E123 D 1249801D 011 2/9/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR021N1062303901406 $351.64 000001078602-3562507204
2023 8 FD52 07 E123 D 1249801D 011 2/9/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021N1062303901406 $31.71 000001078602-3562507204
2023 7 FD52 07 E124 D 1249801D 011 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300405 $0.15 000001078602-3562507204
2023 7 FD52 07 E111 D 1249801D 011 1/24/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR012N1062302300404 $2,325.66 000001078602-3562507204
2023 7 FD52 07 E111 D 1249801D 011 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300404 $378.36 000001078602-3562507204
2023 7 FD52 07 E121 D 1249801D 011 1/24/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR012N1062302300404 $164.33 000001078602-3562507204
2023 7 FD52 07 E121 D 1249801D 011 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300404 $26.73 000001078602-3562507204
2023 7 FD52 07 E122 D 1249801D 011 1/24/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR012N1062302300404 $1,814.02 000001078602-3562507204
2023 7 FD52 07 E122 D 1249801D 011 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300404 $295.12 000001078602-3562507204
2023 7 FD52 07 E123 D 1249801D 011 1/24/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR012N1062302300404 $565.34 000001078602-3562507204
2023 7 FD52 07 E123 D 1249801D 011 1/24/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012N1062302300404 $93.70 000001078602-3562507204
2023 7 FD52 07 E124 D 1249801D 011 1/24/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR012N1062302300404 $0.90 000001078602-3562507204
2023 7 FD52 07 E111 D 1249801D 011 1/12/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR011N1062300610243 $349.47 000001078602-3562507204
2023 7 FD52 07 E111 D 1249801D 011 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610243 $537.72 000001078602-3562507204
2023 7 FD52 07 E121 D 1249801D 011 1/12/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR011N1062300610243 $25.02 000001078602-3562507204
2023 7 FD52 07 E121 D 1249801D 011 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610243 $38.50 000001078602-3562507204
2023 7 FD52 07 E122 D 1249801D 011 1/12/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR011N1062300610243 $272.59 000001078602-3562507204
2023 7 FD52 07 E122 D 1249801D 011 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610243 $419.43 000001078602-3562507204
2023 7 FD52 07 E123 D 1249801D 011 1/12/2023 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR011N1062300610243 $64.61 000001078602-3562507204
2023 7 FD52 07 E123 D 1249801D 011 1/12/2023 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011N1062300610243 $97.59 000001078602-3562507204
2023 6 FD52 07 E111 D 1249801D 011 12/22/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR122M1062235509150 $1,805.31 000001078602-3562507204
2023 6 FD52 07 E111 D 1249801D 011 12/22/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509150 $79.98 000001078602-3562507204
2023 6 FD52 07 E121 D 1249801D 011 12/22/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR122M1062235509150 $123.49 000001078602-3562507204
2023 6 FD52 07 E121 D 1249801D 011 12/22/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509150 $5.47 000001078602-3562507204
2023 6 FD52 07 E122 D 1249801D 011 12/22/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR122M1062235509150 $1,408.15 000001078602-3562507204
2023 6 FD52 07 E122 D 1249801D 011 12/22/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509150 $62.38 000001078602-3562507204
2023 6 FD52 07 E123 D 1249801D 011 12/22/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR122M1062235509150 $591.63 000001078602-3562507204
2023 6 FD52 07 E123 D 1249801D 011 12/22/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509150 $25.98 000001078602-3562507204
2023 6 FD52 07 E124 D 1249801D 011 12/22/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR122M1062235509150 $0.96 000001078602-3562507204
2023 6 FD52 07 E124 D 1249801D 011 12/22/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122M1062235509150 $0.04 000001078602-3562507204
2023 6 FD52 07 E111 D 1249801D 011 12/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR121M1062234208200 $1,536.80 000001078602-3562507204
2023 6 FD52 07 E111 D 1249801D 011 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208200 $348.49 000001078602-3562507204
2023 6 FD52 07 E121 D 1249801D 011 12/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR121M1062234208200 $105.12 000001078602-3562507204
2023 6 FD52 07 E121 D 1249801D 011 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208200 $23.83 000001078602-3562507204
2023 6 FD52 07 E122 D 1249801D 011 12/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR121M1062234208200 $1,198.71 000001078602-3562507204
2023 6 FD52 07 E122 D 1249801D 011 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208200 $271.82 000001078602-3562507204
2023 6 FD52 07 E123 D 1249801D 011 12/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR121M1062234208200 $504.38 000001078602-3562507204
2023 6 FD52 07 E123 D 1249801D 011 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208200 $113.23 000001078602-3562507204
2023 6 FD52 00 E111 D 1249801D 011 12/12/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR121M1062234208196 $510.99 000001076861-3562500061
2023 6 FD52 00 E111 D 1249801D 011 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208196 $152.55 000001076861-3562500061
2023 6 FD52 00 E121 D 1249801D 011 12/12/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR121M1062234208196 $35.70 000001076861-3562500061
2023 6 FD52 00 E121 D 1249801D 011 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208196 $10.66 000001076861-3562500061
2023 6 FD52 00 E122 D 1249801D 011 12/12/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR121M1062234208196 $398.41 000001076861-3562500061
2023 6 FD52 00 E122 D 1249801D 011 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208196 $118.99 000001076861-3562500061
2023 6 FD52 00 E123 D 1249801D 011 12/12/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR121M1062234208196 $112.57 000001076861-3562500061
2023 6 FD52 00 E123 D 1249801D 011 12/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121M1062234208196 $33.26 000001076861-3562500061
2023 5 FD52 07 E111 D 1249801D 011 11/23/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR112M1062232607139 $1,508.23 000001078602-3562507204
2023 5 FD52 07 E124 D 1249801D 011 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607139 $0.20 000001078602-3562507204
2023 5 FD52 07 E111 D 1249801D 011 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607139 $377.06 000001078602-3562507204
2023 5 FD52 07 E121 D 1249801D 011 11/23/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR112M1062232607139 $103.17 000001078602-3562507204
2023 5 FD52 07 E121 D 1249801D 011 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607139 $25.79 000001078602-3562507204
2023 5 FD52 07 E122 D 1249801D 011 11/23/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR112M1062232607139 $1,176.43 000001078602-3562507204
2023 5 FD52 07 E122 D 1249801D 011 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607139 $294.10 000001078602-3562507204
2023 5 FD52 07 E123 D 1249801D 011 11/23/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR112M1062232607139 $495.11 000001078602-3562507204
2023 5 FD52 07 E123 D 1249801D 011 11/23/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112M1062232607139 $122.50 000001078602-3562507204
2023 5 FD52 07 E124 D 1249801D 011 11/23/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR112M1062232607139 $0.80 000001078602-3562507204
2023 5 FD52 07 E123 D 1249801D 011 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806147 $40.31 000001078602-3562507204
2023 5 FD52 07 E111 D 1249801D 011 11/7/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR111M1062230806146 $3,744.93 000001078602-3562507204
2023 5 FD52 07 E111 D 1249801D 011 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806146 $820.49 000001078602-3562507204
2023 5 FD52 07 E121 D 1249801D 011 11/7/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR111M1062230806146 $271.68 000001078602-3562507204
2023 5 FD52 07 E121 D 1249801D 011 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806146 $62.31 000001078602-3562507204
2023 5 FD52 07 E122 D 1249801D 011 11/7/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR111M1062230806146 $2,921.05 000001078602-3562507204
2023 5 FD52 07 E122 D 1249801D 011 11/7/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111M1062230806146 $639.98 000001078602-3562507204
2023 5 FD52 07 E123 D 1249801D 011 11/7/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR111M1062230806146 $658.13 000001078602-3562507204
2023 4 FD52 07 E111 D 1249801D 011 10/31/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR102M1062229405037 $1,904.54 000001078602-3562507204
2023 4 FD52 07 E111 D 1249801D 011 10/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405038 $182.13 000001078602-3562507204
2023 4 FD52 07 E121 D 1249801D 011 10/24/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR102M1062229405038 $129.41 000001078602-3562507204
2023 4 FD52 07 E121 D 1249801D 011 10/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405038 $11.69 000001078602-3562507204
2023 4 FD52 07 E122 D 1249801D 011 10/24/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR102M1062229405038 $1,485.66 000001078602-3562507204
2023 4 FD52 07 E122 D 1249801D 011 10/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405038 $142.06 000001078602-3562507204
2023 4 FD52 07 E123 D 1249801D 011 10/24/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR102M1062229405038 $599.16 000001078602-3562507204
2023 4 FD52 07 E123 D 1249801D 011 10/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405038 $37.10 000001078602-3562507204
2023 4 FD52 07 E124 D 1249801D 011 10/24/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR102M1062229405038 $1.00 000001078602-3562507204
2023 4 FD52 07 E124 D 1249801D 011 10/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102M1062229405038 $0.09 000001078602-3562507204
2023 4 FD52 07 E111 D 1249801D 011 10/10/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR101M1062228003928 $1,656.77 000001078602-3562507204
2023 4 FD52 07 E111 D 1249801D 011 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003928 $228.52 000001078602-3562507204
2023 4 FD52 07 E121 D 1249801D 011 10/10/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR101M1062228003928 $113.33 000001078602-3562507204
2023 4 FD52 07 E121 D 1249801D 011 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003928 $15.63 000001078602-3562507204
2023 4 FD52 07 E122 D 1249801D 011 10/10/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR101M1062228003928 $1,292.28 000001078602-3562507204
2023 4 FD52 07 E122 D 1249801D 011 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003928 $178.25 000001078602-3562507204
2023 4 FD52 07 E123 D 1249801D 011 10/10/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR101M1062228003928 $543.36 000001078602-3562507204
2023 4 FD52 07 E123 D 1249801D 011 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003928 $74.25 000001078602-3562507204
2023 4 FD52 00 E111 D 1249801D 011 10/10/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR101M1062228003923 $510.78 000001076861-3562500061
2023 4 FD52 00 E111 D 1249801D 011 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003923 $51.08 000001076861-3562500061
2023 4 FD52 00 E121 D 1249801D 011 10/10/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR101M1062228003923 $35.69 000001076861-3562500061
2023 4 FD52 00 E121 D 1249801D 011 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003923 $3.57 000001076861-3562500061
2023 4 FD52 00 E122 D 1249801D 011 10/10/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR101M1062228003923 $398.41 000001076861-3562500061
2023 4 FD52 00 E122 D 1249801D 011 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003923 $39.84 000001076861-3562500061
2023 4 FD52 00 E123 D 1249801D 011 10/10/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR101M1062228003923 $112.39 000001076861-3562500061
2023 4 FD52 00 E123 D 1249801D 011 10/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101M1062228003923 $11.14 000001076861-3562500061
2023 3 FD52 00 E111 D 1249801D 011 9/28/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR092M1062226602751 $255.39 000001076861-3562500061
2023 3 FD52 00 E111 D 1249801D 011 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602751 $212.84 000001076861-3562500061
2023 3 FD52 00 E121 D 1249801D 011 9/28/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR092M1062226602751 $18.15 000001076861-3562500061
2023 3 FD52 00 E121 D 1249801D 011 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602751 $15.12 000001076861-3562500061
2023 3 FD52 00 E122 D 1249801D 011 9/28/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR092M1062226602751 $199.21 000001076861-3562500061
2023 3 FD52 00 E122 D 1249801D 011 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602751 $166.01 000001076861-3562500061
2023 3 FD52 07 E111 D 1249801D 011 9/28/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR092M1062226602757 $685.56 000001078602-3562507204
2023 3 FD52 00 E123 D 1249801D 011 9/28/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR092M1062226602751 $56.54 000001076861-3562500061
2023 3 FD52 07 E111 D 1249801D 011 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602757 $257.09 000001078602-3562507204
2023 3 FD52 00 E123 D 1249801D 011 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602751 $46.40 000001076861-3562500061
2023 3 FD52 07 E121 D 1249801D 011 9/28/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR092M1062226602757 $46.90 000001078602-3562507204
2023 3 FD52 00 E124 D 1249801D 011 9/28/2022 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR092M1062226602751 $0.07 000001076861-3562500061
2023 3 FD52 07 E121 D 1249801D 011 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602757 $17.58 000001078602-3562507204
2023 3 FD52 00 E124 D 1249801D 011 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602751 $0.09 000001076861-3562500061
2023 3 FD52 07 E122 D 1249801D 011 9/28/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR092M1062226602757 $534.74 000001078602-3562507204
2023 3 FD52 07 E122 D 1249801D 011 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602757 $200.53 000001078602-3562507204
2023 3 FD52 07 E123 D 1249801D 011 9/28/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR092M1062226602757 $225.29 000001078602-3562507204
2023 3 FD52 07 E123 D 1249801D 011 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602757 $83.52 000001078602-3562507204
2023 3 FD52 07 E124 D 1249801D 011 9/28/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR092M1062226602757 $0.36 000001078602-3562507204
2023 3 FD52 07 E124 D 1249801D 011 9/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092M1062226602757 $0.14 000001078602-3562507204
2023 3 FD52 07 E111 D 1249801D 011 9/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR091M1062225101611 $473.54 000001078602-3562507204
2023 3 FD52 07 E111 D 1249801D 011 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101611 $261.28 000001078602-3562507204
2023 3 FD52 07 E121 D 1249801D 011 9/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR091M1062225101611 $30.38 000001078602-3562507204
2023 3 FD52 07 E121 D 1249801D 011 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101611 $16.75 000001078602-3562507204
2023 3 FD52 07 E122 D 1249801D 011 9/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR091M1062225101611 $369.41 000001078602-3562507204
2023 3 FD52 07 E122 D 1249801D 011 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101611 $203.80 000001078602-3562507204
2023 3 FD52 07 E123 D 1249801D 011 9/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR091M1062225101611 $98.26 000001078602-3562507204
2023 3 FD52 07 E123 D 1249801D 011 9/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091M1062225101611 $53.22 000001078602-3562507204
2023 2 FD52 00 E111 D 1249801D 011 8/24/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR082M1062223500465 $327.52 000001084211-3562500061
2023 2 FD52 00 E111 D 1249801D 011 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500465 $67.08 000001084211-3562500061
2023 2 FD52 00 E121 D 1249801D 011 8/24/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR082M1062223500465 $22.60 000001084211-3562500061
2023 2 FD52 00 E121 D 1249801D 011 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500465 $4.63 000001084211-3562500061
2023 2 FD52 00 E122 D 1249801D 011 8/24/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR082M1062223500465 $255.53 000001084211-3562500061
2023 2 FD52 00 E122 D 1249801D 011 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500465 $52.33 000001084211-3562500061
2023 2 FD52 00 E123 D 1249801D 011 8/24/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR082M1062223500465 $71.67 000001084211-3562500061
2023 2 FD52 00 E123 D 1249801D 011 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500465 $14.51 000001084211-3562500061
2023 2 FD52 00 E124 D 1249801D 011 8/24/2022 0070 ENV STUDIES-HIST/CULTURAL CA-XR082M1062223500465 $0.13 000001084211-3562500061
2023 2 FD52 00 E124 D 1249801D 011 8/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082M1062223500465 $0.02 000001084211-3562500061
2023 1 FD52 07 E111 D 1249801D 011 7/25/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR072M1062220308979 $279.14 000001078602-3562507204
2023 1 FD52 07 E111 D 1249801D 011 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308979 $27.91 000001078602-3562507204
2023 1 FD52 07 E121 D 1249801D 011 7/25/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR072M1062220308979 $21.36 000001078602-3562507204
2023 1 FD52 07 E121 D 1249801D 011 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308979 $2.13 000001078602-3562507204
2023 1 FD52 07 E122 D 1249801D 011 7/25/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR072M1062220308979 $217.73 000001078602-3562507204
2023 1 FD52 07 E122 D 1249801D 011 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308979 $21.77 000001078602-3562507204
2023 1 FD52 07 E123 D 1249801D 011 7/25/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR072M1062220308979 $8.46 000001078602-3562507204
2023 1 FD52 07 E123 D 1249801D 011 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308979 $0.80 000001078602-3562507204
2023 1 FD52 07 E124 D 1249801D 011 7/25/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR072M1062220308979 $0.09 000001078602-3562507204
2023 1 FD52 07 E124 D 1249801D 011 7/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072M1062220308979 $0.01 000001078602-3562507204
2023 1 FD52 07 E111 D 1249801D 011 7/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR071M1062219207865 $2,806.00 000001078602-3562507204
2023 1 FD52 07 E111 D 1249801D 011 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207865 $220.55 000001078602-3562507204
2023 1 FD52 07 E121 D 1249801D 011 7/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR071M1062219207865 $207.99 000001078602-3562507204
2023 1 FD52 07 E121 D 1249801D 011 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207865 $16.75 000001078602-3562507204
2023 1 FD52 07 E122 D 1249801D 011 7/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR071M1062219207865 $2,356.20 000001078602-3562507204
2023 1 FD52 07 E122 D 1249801D 011 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207865 $185.19 000001078602-3562507204
2023 1 FD52 07 E123 D 1249801D 011 7/12/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR071M1062219207865 $191.78 000001078602-3562507204
2023 1 FD52 07 E123 D 1249801D 011 7/12/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071M1062219207865 $8.65 000001078602-3562507204
2022 12 FD52 07 E111 D 1249801D 011 6/27/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR062M1062217506754 $1,164.97 000001078602-3562507204
2022 12 FD52 07 E111 D 1249801D 011 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506754 $302.21 000001078602-3562507204
2022 12 FD52 07 E121 D 1249801D 011 6/27/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR062M1062217506754 $80.00 000001078602-3562507204
2022 12 FD52 07 E121 D 1249801D 011 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506754 $20.75 000001078602-3562507204
2022 12 FD52 07 E122 D 1249801D 011 6/27/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR062M1062217506754 $978.42 000001078602-3562507204
2022 12 FD52 07 E122 D 1249801D 011 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506754 $253.76 000001078602-3562507204
2022 12 FD52 07 E123 D 1249801D 011 6/27/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR062M1062217506754 $196.31 000001078602-3562507204
2022 12 FD52 07 E123 D 1249801D 011 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506754 $50.20 000001078602-3562507204
2022 12 FD52 07 E124 D 1249801D 011 6/27/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR062M1062217506754 $0.43 000001078602-3562507204
2022 12 FD52 07 E124 D 1249801D 011 6/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062M1062217506754 $0.11 000001078602-3562507204
2022 12 FD52 07 E143 D 1249801D 011 6/16/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200230640 PON22200000620 GRW ENGINEERS INC $110,862.98 Preliminary Engineering and Engineering Services
2022 12 FD52 07 E123 D 1249801D 011 6/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905711 $16.62 000001078602-3562507204
2022 12 FD52 07 E111 D 1249801D 011 6/13/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR061M1062215905711 $441.37 000001078602-3562507204
2022 12 FD52 07 E111 D 1249801D 011 6/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905711 $100.05 000001078602-3562507204
2022 12 FD52 07 E121 D 1249801D 011 6/13/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR061M1062215905711 $29.78 000001078602-3562507204
2022 12 FD52 07 E121 D 1249801D 011 6/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905711 $6.73 000001078602-3562507204
2022 12 FD52 07 E122 D 1249801D 011 6/13/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR061M1062215905711 $370.62 000001078602-3562507204
2022 12 FD52 07 E122 D 1249801D 011 6/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR061M1062215905711 $84.02 000001078602-3562507204
2022 12 FD52 07 E123 D 1249801D 011 6/13/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR061M1062215905711 $74.34 000001078602-3562507204
2022 11 FD52 07 E111 D 1249801D 011 5/23/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR052M1062214004661 $1,353.53 000001078602-3562507204
2022 11 FD52 07 E121 D 1249801D 011 5/23/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR052M1062214004661 $92.96 000001078602-3562507204
2022 11 FD52 07 E122 D 1249801D 011 5/23/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR052M1062214004661 $1,136.56 000001078602-3562507204
2022 11 FD52 07 E123 D 1249801D 011 5/23/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR052M1062214004661 $227.38 000001078602-3562507204
2022 11 FD52 07 E124 D 1249801D 011 5/23/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR052M1062214004661 $0.50 000001078602-3562507204
2022 11 FD52 00 E111 D 1249801D 011 5/23/2022 0092 ENV STUDIES-PERMITTING CA-XR052M1062214004674 $520.24 000001080828-3562500061
2022 11 FD52 00 E121 D 1249801D 011 5/23/2022 0092 ENV STUDIES-PERMITTING CA-XR052M1062214004674 $36.75 000001080828-3562500061
2022 11 FD52 00 E122 D 1249801D 011 5/23/2022 0092 ENV STUDIES-PERMITTING CA-XR052M1062214004674 $436.85 000001080828-3562500061
2022 11 FD52 00 E123 D 1249801D 011 5/23/2022 0092 ENV STUDIES-PERMITTING CA-XR052M1062214004674 $123.52 000001080828-3562500061
2022 11 FD52 00 E124 D 1249801D 011 5/23/2022 0092 ENV STUDIES-PERMITTING CA-XR052M1062214004674 $0.20 000001080828-3562500061
2022 10 FD52 07 E111 D 1249801D 011 4/28/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042M1062211202525 $490.59 000001078602-3562507204
2022 10 FD52 07 E111 D 1249801D 011 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202525 $83.31 000001078602-3562507204
2022 10 FD52 07 E121 D 1249801D 011 4/28/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042M1062211202525 $35.19 000001078602-3562507204
2022 10 FD52 07 E121 D 1249801D 011 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202525 $5.46 000001078602-3562507204
2022 10 FD52 07 E122 D 1249801D 011 4/28/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042M1062211202525 $411.94 000001078602-3562507204
2022 10 FD52 07 E122 D 1249801D 011 4/28/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202525 $69.96 000001078602-3562507204
2022 10 FD52 07 E123 D 1249801D 011 4/28/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042M1062211202525 $56.04 000001078602-3562507204
2022 10 FD52 07 E123 D 1249801D 011 4/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202526 $15.79 000001078602-3562507204
2022 10 FD52 07 E124 D 1249801D 011 4/25/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR042M1062211202526 $0.27 000001078602-3562507204
2022 10 FD52 07 E124 D 1249801D 011 4/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042M1062211202526 $0.05 000001078602-3562507204
2022 10 FD52 00 E111 D 1249801D 011 4/13/2022 0010 ENV STUDIES-UST/HZM CA-XR041M1062209801495 $477.92 000001082111-3562500061
2022 10 FD52 00 E111 D 1249801D 011 4/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801495 $5.42 000001082111-3562500061
2022 10 FD52 00 E121 D 1249801D 011 4/13/2022 0010 ENV STUDIES-UST/HZM CA-XR041M1062209801495 $33.62 000001082111-3562500061
2022 10 FD52 00 E121 D 1249801D 011 4/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801495 $0.38 000001082111-3562500061
2022 10 FD52 00 E122 D 1249801D 011 4/13/2022 0010 ENV STUDIES-UST/HZM CA-XR041M1062209801495 $401.54 000001082111-3562500061
2022 10 FD52 00 E122 D 1249801D 011 4/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801495 $4.55 000001082111-3562500061
2022 10 FD52 00 E123 D 1249801D 011 4/13/2022 0010 ENV STUDIES-UST/HZM CA-XR041M1062209801495 $93.73 000001082111-3562500061
2022 10 FD52 00 E123 D 1249801D 011 4/13/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801495 $1.05 000001082111-3562500061
2022 10 FD52 00 E111 D 1249801D 011 4/13/2022 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041M1062209801501 $146.99 000001082283-3562500610
2022 10 FD52 00 E121 D 1249801D 011 4/13/2022 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041M1062209801501 $10.08 000001082283-3562500610
2022 10 FD52 00 E122 D 1249801D 011 4/13/2022 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041M1062209801501 $123.43 000001082283-3562500610
2022 10 FD52 00 E123 D 1249801D 011 4/13/2022 5011 GEOTECH INVEST ROADWAY (DESIGN CA-XR041M1062209801501 $25.73 000001082283-3562500610
2022 10 FD52 07 E143 D 1249801D 011 4/11/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200180640 PON22200000620 GRW ENGINEERS INC $110,369.55 Boyle/Co-0/000-003
2022 10 FD52 07 E111 D 1249801D 011 4/11/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041M1062209801466 $764.72 000001078602-3562507204
2022 10 FD52 07 E111 D 1249801D 011 4/11/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801466 $883.66 000001078602-3562507204
2022 10 FD52 07 E121 D 1249801D 011 4/11/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041M1062209801466 $48.29 000001078602-3562507204
2022 10 FD52 07 E121 D 1249801D 011 4/11/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801466 $55.81 000001078602-3562507204
2022 10 FD52 07 E122 D 1249801D 011 4/11/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041M1062209801466 $642.11 000001078602-3562507204
2022 10 FD52 07 E122 D 1249801D 011 4/11/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801466 $742.01 000001078602-3562507204
2022 10 FD52 07 E123 D 1249801D 011 4/11/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR041M1062209801466 $172.59 000001078602-3562507204
2022 10 FD52 07 E123 D 1249801D 011 4/11/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041M1062209801466 $194.38 000001078602-3562507204
2022 9 FD52 07 E111 D 1249801D 011 3/24/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR032M1062208200384 $1,454.55 000001078602-3562507204
2022 9 FD52 07 E111 D 1249801D 011 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200384 $2,065.12 000001078602-3562507204
2022 9 FD52 07 E121 D 1249801D 011 3/24/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR032M1062208200384 $105.62 000001078602-3562507204
2022 9 FD52 07 E121 D 1249801D 011 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200384 $157.02 000001078602-3562507204
2022 9 FD52 07 E122 D 1249801D 011 3/24/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR032M1062208200384 $1,221.38 000001078602-3562507204
2022 9 FD52 07 E122 D 1249801D 011 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200384 $1,734.08 000001078602-3562507204
2022 9 FD52 07 E123 D 1249801D 011 3/24/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR032M1062208200384 $165.62 000001078602-3562507204
2022 9 FD52 07 E123 D 1249801D 011 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200384 $83.33 000001078602-3562507204
2022 9 FD52 07 E124 D 1249801D 011 3/24/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR032M1062208200384 $0.54 000001078602-3562507204
2022 9 FD52 07 E124 D 1249801D 011 3/24/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR032M1062208200384 $0.77 000001078602-3562507204
2022 9 FD52 07 E111 D 1249801D 011 3/9/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR031M1062206709452 $2,771.58 000001078602-3562507204
2022 9 FD52 07 E111 D 1249801D 011 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709452 $86.99 000001078602-3562507204
2022 9 FD52 07 E121 D 1249801D 011 3/9/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR031M1062206709452 $197.31 000001078602-3562507204
2022 9 FD52 07 E121 D 1249801D 011 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709452 $5.49 000001078602-3562507204
2022 9 FD52 07 E122 D 1249801D 011 3/9/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR031M1062206709452 $2,327.30 000001078602-3562507204
2022 9 FD52 07 E122 D 1249801D 011 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709452 $73.04 000001078602-3562507204
2022 9 FD52 07 E123 D 1249801D 011 3/9/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR031M1062206709452 $528.22 000001078602-3562507204
2022 9 FD52 07 E123 D 1249801D 011 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709452 $19.14 000001078602-3562507204
2022 9 FD52 00 E111 D 1249801D 011 3/9/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031M1062206709445 $202.32 000001077076-3562500636
2022 9 FD52 00 E111 D 1249801D 011 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709445 $9.31 000001077076-3562500636
2022 9 FD52 00 E121 D 1249801D 011 3/9/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031M1062206709445 $14.35 000001077076-3562500636
2022 9 FD52 00 E121 D 1249801D 011 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709445 $0.67 000001077076-3562500636
2022 9 FD52 00 E122 D 1249801D 011 3/9/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031M1062206709445 $169.89 000001077076-3562500636
2022 9 FD52 00 E122 D 1249801D 011 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709445 $7.82 000001077076-3562500636
2022 9 FD52 00 E123 D 1249801D 011 3/9/2022 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031M1062206709445 $45.77 000001077076-3562500636
2022 9 FD52 00 E123 D 1249801D 011 3/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031M1062206709445 $2.09 000001077076-3562500636
2022 8 FD52 07 E111 D 1249801D 011 2/25/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR022M1062205308410 $1,798.97 000001078602-3562507204
2022 8 FD52 07 E111 D 1249801D 011 2/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022M1062205308410 $520.68 000001078602-3562507204
2022 8 FD52 07 E121 D 1249801D 011 2/25/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR022M1062205308410 $120.20 000001078602-3562507204
2022 8 FD52 07 E121 D 1249801D 011 2/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022M1062205308410 $34.34 000001078602-3562507204
2022 8 FD52 07 E122 D 1249801D 011 2/25/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR022M1062205308410 $1,510.60 000001078602-3562507204
2022 8 FD52 07 E122 D 1249801D 011 2/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022M1062205308410 $437.21 000001078602-3562507204
2022 8 FD52 07 E123 D 1249801D 011 2/25/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR022M1062205308410 $292.01 000001078602-3562507204
2022 8 FD52 07 E123 D 1249801D 011 2/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022M1062205308410 $90.50 000001078602-3562507204
2022 8 FD52 07 E124 D 1249801D 011 2/25/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR022M1062205308410 $0.68 000001078602-3562507204
2022 8 FD52 07 E124 D 1249801D 011 2/25/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022M1062205308410 $0.21 000001078602-3562507204
2022 8 FD52 07 E143 D 1249801D 011 2/24/2022 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200144654 PON22200000620 GRW ENGINEERS INC $120,337.82 Preliminary Engineering and Engineering Services
2022 8 FD52 07 E111 D 1249801D 011 2/9/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR021M1062203907431 $3,629.97 000001078602-3562507204
2022 8 FD52 07 E111 D 1249801D 011 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907431 $446.09 000001078602-3562507204
2022 8 FD52 07 E121 D 1249801D 011 2/9/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR021M1062203907431 $254.67 000001078602-3562507204
2022 8 FD52 07 E121 D 1249801D 011 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907431 $31.48 000001078602-3562507204
2022 8 FD52 07 E122 D 1249801D 011 2/9/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR021M1062203907431 $3,048.08 000001078602-3562507204
2022 8 FD52 07 E122 D 1249801D 011 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907431 $374.58 000001078602-3562507204
2022 8 FD52 07 E123 D 1249801D 011 2/9/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR021M1062203907431 $384.96 000001078602-3562507204
2022 8 FD52 07 E123 D 1249801D 011 2/9/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR021M1062203907431 $43.63 000001078602-3562507204
2022 7 FD52 07 E111 D 1249801D 011 1/27/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR012M1062202106442 $2,229.66 000001078602-3562507204
2022 7 FD52 07 E111 D 1249801D 011 1/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012M1062202106442 $247.74 000001078602-3562507204
2022 7 FD52 07 E121 D 1249801D 011 1/27/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR012M1062202106442 $151.51 000001078602-3562507204
2022 7 FD52 07 E121 D 1249801D 011 1/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012M1062202106442 $16.83 000001078602-3562507204
2022 7 FD52 07 E122 D 1249801D 011 1/27/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR012M1062202106442 $1,872.24 000001078602-3562507204
2022 7 FD52 07 E122 D 1249801D 011 1/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012M1062202106442 $208.03 000001078602-3562507204
2022 7 FD52 07 E123 D 1249801D 011 1/27/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR012M1062202106442 $409.80 000001078602-3562507204
2022 7 FD52 07 E123 D 1249801D 011 1/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012M1062202106442 $44.97 000001078602-3562507204
2022 7 FD52 07 E124 D 1249801D 011 1/27/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR012M1062202106442 $0.90 000001078602-3562507204
2022 7 FD52 07 E124 D 1249801D 011 1/27/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR012M1062202106442 $0.10 000001078602-3562507204
2022 7 FD52 07 E111 D 1249801D 011 1/10/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR011M1062200705542 $1,266.23 000001078602-3562507204
2022 7 FD52 07 E111 D 1249801D 011 1/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705542 $1,211.17 000001078602-3562507204
2022 7 FD52 07 E121 D 1249801D 011 1/10/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR011M1062200705542 $86.04 000001078602-3562507204
2022 7 FD52 07 E121 D 1249801D 011 1/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705542 $82.30 000001078602-3562507204
2022 7 FD52 07 E122 D 1249801D 011 1/10/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR011M1062200705542 $1,063.26 000001078602-3562507204
2022 7 FD52 07 E122 D 1249801D 011 1/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705542 $1,017.01 000001078602-3562507204
2022 7 FD52 07 E123 D 1249801D 011 1/10/2022 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR011M1062200705542 $234.93 000001078602-3562507204
2022 7 FD52 07 E123 D 1249801D 011 1/10/2022 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR011M1062200705542 $219.84 000001078602-3562507204
2022 6 FD52 07 E124 D 1249801D 011 12/22/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR122L1062135504485 $0.71 000001078602-3562507204
2022 6 FD52 00 E121 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504513 $3.36 000001080828-3562500061
2022 6 FD52 00 E122 D 1249801D 011 12/22/2021 0092 ENV STUDIES-PERMITTING CA-XR122L1062135504513 $397.13 000001080828-3562500061
2022 6 FD52 00 E122 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504513 $39.72 000001080828-3562500061
2022 6 FD52 00 E123 D 1249801D 011 12/22/2021 0092 ENV STUDIES-PERMITTING CA-XR122L1062135504513 $106.98 000001080828-3562500061
2022 6 FD52 00 E123 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504513 $10.60 000001080828-3562500061
2022 6 FD52 00 E124 D 1249801D 011 12/22/2021 0092 ENV STUDIES-PERMITTING CA-XR122L1062135504513 $0.18 000001080828-3562500061
2022 6 FD52 00 E124 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504513 $0.02 000001080828-3562500061
2022 6 FD52 07 E124 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504485 $0.29 000001078602-3562507204
2022 6 FD52 00 E111 D 1249801D 011 12/22/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122L1062135504473 $66.25 000001077076-3562500636
2022 6 FD52 00 E111 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504473 $0.66 000001077076-3562500636
2022 6 FD52 00 E121 D 1249801D 011 12/22/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122L1062135504473 $4.71 000001077076-3562500636
2022 6 FD52 00 E121 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504473 $0.05 000001077076-3562500636
2022 6 FD52 00 E122 D 1249801D 011 12/22/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122L1062135504473 $55.60 000001077076-3562500636
2022 6 FD52 00 E122 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504473 $0.56 000001077076-3562500636
2022 6 FD52 00 E123 D 1249801D 011 12/22/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122L1062135504473 $14.26 000001077076-3562500636
2022 6 FD52 00 E123 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504473 $0.14 000001077076-3562500636
2022 6 FD52 00 E124 D 1249801D 011 12/22/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR122L1062135504473 $0.02 000001077076-3562500636
2022 6 FD52 00 E111 D 1249801D 011 12/22/2021 0092 ENV STUDIES-PERMITTING CA-XR122L1062135504513 $472.94 000001080828-3562500061
2022 6 FD52 00 E111 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504513 $47.30 000001080828-3562500061
2022 6 FD52 00 E121 D 1249801D 011 12/22/2021 0092 ENV STUDIES-PERMITTING CA-XR122L1062135504513 $33.54 000001080828-3562500061
2022 6 FD52 07 E111 D 1249801D 011 12/22/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR122L1062135504484 $1,749.19 000001078602-3562507204
2022 6 FD52 07 E111 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504484 $728.21 000001078602-3562507204
2022 6 FD52 07 E121 D 1249801D 011 12/22/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR122L1062135504484 $130.19 000001078602-3562507204
2022 6 FD52 07 E121 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504484 $54.20 000001078602-3562507204
2022 6 FD52 07 E122 D 1249801D 011 12/22/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR122L1062135504484 $1,468.79 000001078602-3562507204
2022 6 FD52 07 E122 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504484 $611.48 000001078602-3562507204
2022 6 FD52 07 E123 D 1249801D 011 12/22/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR122L1062135504484 $314.85 000001078602-3562507204
2022 6 FD52 07 E123 D 1249801D 011 12/22/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR122L1062135504484 $128.95 000001078602-3562507204
2022 6 FD52 07 E111 D 1249801D 011 12/8/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR121L1062134103553 $1,611.39 000001078602-3562507204
2022 6 FD52 07 E111 D 1249801D 011 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103553 $453.30 000001078602-3562507204
2022 6 FD52 07 E121 D 1249801D 011 12/8/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR121L1062134103553 $110.37 000001078602-3562507204
2022 6 FD52 07 E121 D 1249801D 011 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103553 $30.84 000001078602-3562507204
2022 6 FD52 07 E122 D 1249801D 011 12/8/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR121L1062134103553 $1,353.07 000001078602-3562507204
2022 6 FD52 07 E122 D 1249801D 011 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103553 $380.64 000001078602-3562507204
2022 6 FD52 07 E123 D 1249801D 011 12/8/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR121L1062134103553 $334.05 000001078602-3562507204
2022 6 FD52 07 E123 D 1249801D 011 12/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR121L1062134103553 $93.53 000001078602-3562507204
2022 5 FD52 07 E143 D 1249801D 011 11/30/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200089874 PON22200000620 GRW ENGINEERS INC $84,107.55 Preliminary Engineering and Engineering Services
2022 5 FD52 07 E111 D 1249801D 011 11/23/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR112L1062132602517 $1,365.12 000001078602-3562507204
2022 5 FD52 07 E111 D 1249801D 011 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602517 $560.06 000001078602-3562507204
2022 5 FD52 07 E121 D 1249801D 011 11/23/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR112L1062132602517 $92.02 000001078602-3562507204
2022 5 FD52 07 E121 D 1249801D 011 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602517 $37.76 000001078602-3562507204
2022 5 FD52 07 E122 D 1249801D 011 11/23/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR112L1062132602517 $1,146.29 000001078602-3562507204
2022 5 FD52 07 E122 D 1249801D 011 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602517 $470.28 000001078602-3562507204
2022 5 FD52 07 E123 D 1249801D 011 11/23/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR112L1062132602517 $298.06 000001078602-3562507204
2022 5 FD52 07 E123 D 1249801D 011 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602517 $120.20 000001078602-3562507204
2022 5 FD52 07 E124 D 1249801D 011 11/23/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR112L1062132602517 $0.71 000001078602-3562507204
2022 5 FD52 07 E124 D 1249801D 011 11/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR112L1062132602517 $0.29 000001078602-3562507204
2022 5 FD52 07 E111 D 1249801D 011 11/8/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR111L1062130901513 $1,822.50 000001078602-3562507204
2022 5 FD52 07 E111 D 1249801D 011 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901513 $102.68 000001078602-3562507204
2022 5 FD52 07 E121 D 1249801D 011 11/8/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR111L1062130901513 $120.92 000001078602-3562507204
2022 5 FD52 07 E121 D 1249801D 011 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901513 $6.81 000001078602-3562507204
2022 5 FD52 07 E122 D 1249801D 011 11/8/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR111L1062130901513 $1,530.35 000001078602-3562507204
2022 5 FD52 07 E122 D 1249801D 011 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901513 $86.22 000001078602-3562507204
2022 5 FD52 07 E123 D 1249801D 011 11/8/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR111L1062130901513 $396.22 000001078602-3562507204
2022 5 FD52 07 E111 D 1249801D 011 11/8/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR111L1062130901516 $398.91 000001078915-3562507200
2022 5 FD52 07 E123 D 1249801D 011 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901513 $22.04 000001078602-3562507204
2022 5 FD52 07 E111 D 1249801D 011 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901516 $19.42 000001078915-3562507200
2022 5 FD52 07 E121 D 1249801D 011 11/8/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR111L1062130901516 $27.77 000001078915-3562507200
2022 5 FD52 07 E121 D 1249801D 011 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901516 $1.36 000001078915-3562507200
2022 5 FD52 07 E122 D 1249801D 011 11/8/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR111L1062130901516 $334.91 000001078915-3562507200
2022 5 FD52 07 E122 D 1249801D 011 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901516 $16.31 000001078915-3562507200
2022 5 FD52 07 E123 D 1249801D 011 11/8/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR111L1062130901516 $90.18 000001078915-3562507200
2022 5 FD52 07 E123 D 1249801D 011 11/8/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR111L1062130901516 $4.35 000001078915-3562507200
2022 5 FD52 07 E143 D 1249801D 011 11/4/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200077398 PON22200000620 GRW ENGINEERS INC $34,547.44 Preliminary Engineering and Engineering Services
2022 4 FD52 07 E111 D 1249801D 011 10/25/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR102L1062129500414 $709.42 000001078915-3562507200
2022 4 FD52 07 E121 D 1249801D 011 10/25/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR102L1062129500414 $50.31 000001078915-3562507200
2022 4 FD52 07 E122 D 1249801D 011 10/25/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR102L1062129500414 $595.70 000001078915-3562507200
2022 4 FD52 07 E111 D 1249801D 011 10/25/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR102L1062129500410 $1,003.43 000001078602-3562507204
2022 4 FD52 07 E123 D 1249801D 011 10/25/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR102L1062129500414 $160.33 000001078915-3562507200
2022 4 FD52 07 E111 D 1249801D 011 10/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102L1062129500410 $130.68 000001078602-3562507204
2022 4 FD52 07 E124 D 1249801D 011 10/25/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR102L1062129500414 $0.27 000001078915-3562507200
2022 4 FD52 07 E121 D 1249801D 011 10/25/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR102L1062129500410 $67.65 000001078602-3562507204
2022 4 FD52 07 E121 D 1249801D 011 10/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102L1062129500410 $8.81 000001078602-3562507204
2022 4 FD52 07 E122 D 1249801D 011 10/25/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR102L1062129500410 $842.58 000001078602-3562507204
2022 4 FD52 07 E122 D 1249801D 011 10/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102L1062129500410 $109.73 000001078602-3562507204
2022 4 FD52 07 E123 D 1249801D 011 10/25/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR102L1062129500410 $218.34 000001078602-3562507204
2022 4 FD52 07 E123 D 1249801D 011 10/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102L1062129500410 $28.04 000001078602-3562507204
2022 4 FD52 07 E124 D 1249801D 011 10/25/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR102L1062129500410 $0.52 000001078602-3562507204
2022 4 FD52 07 E124 D 1249801D 011 10/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR102L1062129500410 $0.07 000001078602-3562507204
2022 4 FD52 07 E111 D 1249801D 011 10/11/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR101L1062128110131 $236.47 000001078915-3562507200
2022 4 FD52 07 E121 D 1249801D 011 10/11/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR101L1062128110131 $16.47 000001078915-3562507200
2022 4 FD52 07 E122 D 1249801D 011 10/11/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR101L1062128110131 $198.56 000001078915-3562507200
2022 4 FD52 07 E123 D 1249801D 011 10/11/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR101L1062128110131 $53.44 000001078915-3562507200
2022 4 FD52 07 E111 D 1249801D 011 10/11/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR101L1062128110127 $3,302.99 000001078602-3562507204
2022 4 FD52 07 E111 D 1249801D 011 10/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101L1062128110127 $208.59 000001078602-3562507204
2022 4 FD52 07 E121 D 1249801D 011 10/11/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR101L1062128110127 $238.14 000001078602-3562507204
2022 4 FD52 07 E121 D 1249801D 011 10/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101L1062128110127 $14.95 000001078602-3562507204
2022 4 FD52 07 E122 D 1249801D 011 10/11/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR101L1062128110127 $2,773.52 000001078602-3562507204
2022 4 FD52 07 E122 D 1249801D 011 10/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101L1062128110127 $175.15 000001078602-3562507204
2022 4 FD52 07 E123 D 1249801D 011 10/11/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR101L1062128110127 $554.99 000001078602-3562507204
2022 4 FD52 07 E123 D 1249801D 011 10/11/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR101L1062128110127 $35.59 000001078602-3562507204
2022 3 FD52 07 E111 D 1249801D 011 9/30/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR092L1062126709045 $1,800.25 000001078602-3562507204
2022 3 FD52 07 E111 D 1249801D 011 9/30/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709045 $248.20 000001078602-3562507204
2022 3 FD52 07 E121 D 1249801D 011 9/30/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR092L1062126709045 $126.87 000001078602-3562507204
2022 3 FD52 07 E121 D 1249801D 011 9/30/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709045 $17.61 000001078602-3562507204
2022 3 FD52 07 E122 D 1249801D 011 9/30/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR092L1062126709045 $1,511.67 000001078602-3562507204
2022 3 FD52 07 E122 D 1249801D 011 9/30/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709045 $208.41 000001078602-3562507204
2022 3 FD52 07 E123 D 1249801D 011 9/30/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR092L1062126709045 $334.25 000001078602-3562507204
2022 3 FD52 07 E123 D 1249801D 011 9/30/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709045 $44.19 000001078602-3562507204
2022 3 FD52 07 E124 D 1249801D 011 9/30/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR092L1062126709045 $0.67 000001078602-3562507204
2022 3 FD52 07 E124 D 1249801D 011 9/30/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709045 $0.09 000001078602-3562507204
2022 3 FD52 07 E124 D 1249801D 011 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709051 $0.01 000001078915-3562507200
2022 3 FD52 07 E111 D 1249801D 011 9/27/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR092L1062126709050 $110.41 000001078915-3562507200
2022 3 FD52 07 E111 D 1249801D 011 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709050 $30.90 000001078915-3562507200
2022 3 FD52 07 E121 D 1249801D 011 9/27/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR092L1062126709050 $7.82 000001078915-3562507200
2022 3 FD52 07 E121 D 1249801D 011 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709050 $2.18 000001078915-3562507200
2022 3 FD52 07 E122 D 1249801D 011 9/27/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR092L1062126709050 $92.66 000001078915-3562507200
2022 3 FD52 07 E122 D 1249801D 011 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709050 $25.95 000001078915-3562507200
2022 3 FD52 07 E123 D 1249801D 011 9/27/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR092L1062126709050 $25.00 000001078915-3562507200
2022 3 FD52 07 E123 D 1249801D 011 9/27/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR092L1062126709050 $6.93 000001078915-3562507200
2022 3 FD52 07 E124 D 1249801D 011 9/27/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR092L1062126709050 $0.04 000001078915-3562507200
2022 3 FD52 07 E111 D 1249801D 011 9/13/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR091L1062125207988 $1,561.53 000001078602-3562507204
2022 3 FD52 07 E111 D 1249801D 011 9/13/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091L1062125207988 $35.51 000001078602-3562507204
2022 3 FD52 07 E121 D 1249801D 011 9/13/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR091L1062125207988 $103.61 000001078602-3562507204
2022 3 FD52 07 E121 D 1249801D 011 9/13/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091L1062125207988 $2.36 000001078602-3562507204
2022 3 FD52 07 E122 D 1249801D 011 9/13/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR091L1062125207988 $1,311.22 000001078602-3562507204
2022 3 FD52 07 E122 D 1249801D 011 9/13/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091L1062125207988 $29.82 000001078602-3562507204
2022 3 FD52 07 E123 D 1249801D 011 9/13/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR091L1062125207988 $339.35 000001078602-3562507204
2022 3 FD52 07 E123 D 1249801D 011 9/13/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR091L1062125207988 $7.62 000001078602-3562507204
2022 2 FD52 07 E111 D 1249801D 011 8/25/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR082L1062123606980 $1,828.92 000001078602-3562507204
2022 2 FD52 07 E111 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606980 $96.26 000001078602-3562507204
2022 2 FD52 07 E121 D 1249801D 011 8/25/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR082L1062123606980 $123.29 000001078602-3562507204
2022 2 FD52 07 E121 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606980 $6.49 000001078602-3562507204
2022 2 FD52 07 E122 D 1249801D 011 8/25/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR082L1062123606980 $1,535.74 000001078602-3562507204
2022 2 FD52 07 E122 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606980 $80.83 000001078602-3562507204
2022 2 FD52 07 E123 D 1249801D 011 8/25/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR082L1062123606980 $397.60 000001078602-3562507204
2022 2 FD52 07 E123 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606980 $20.66 000001078602-3562507204
2022 2 FD52 07 E124 D 1249801D 011 8/25/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR082L1062123606980 $0.95 000001078602-3562507204
2022 2 FD52 07 E124 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606980 $0.05 000001078602-3562507204
2022 2 FD52 00 E111 D 1249801D 011 8/25/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR082L1062123606966 $200.30 000001077076-3562500636
2022 2 FD52 00 E111 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606966 $12.75 000001077076-3562500636
2022 2 FD52 00 E121 D 1249801D 011 8/25/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR082L1062123606966 $14.26 000001077076-3562500636
2022 2 FD52 00 E121 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606966 $0.91 000001077076-3562500636
2022 2 FD52 00 E122 D 1249801D 011 8/25/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR082L1062123606966 $168.19 000001077076-3562500636
2022 2 FD52 00 E122 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606966 $10.71 000001077076-3562500636
2022 2 FD52 00 E123 D 1249801D 011 8/25/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR082L1062123606966 $43.14 000001077076-3562500636
2022 2 FD52 00 E123 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606966 $2.72 000001077076-3562500636
2022 2 FD52 00 E124 D 1249801D 011 8/25/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR082L1062123606966 $0.07 000001077076-3562500636
2022 2 FD52 07 E111 D 1249801D 011 8/25/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR082L1062123606984 $260.12 000001078915-3562507200
2022 2 FD52 07 E111 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606984 $1.74 000001078915-3562507200
2022 2 FD52 07 E121 D 1249801D 011 8/25/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR082L1062123606984 $18.45 000001078915-3562507200
2022 2 FD52 07 E121 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606984 $0.12 000001078915-3562507200
2022 2 FD52 07 E122 D 1249801D 011 8/25/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR082L1062123606984 $218.42 000001078915-3562507200
2022 2 FD52 07 E122 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606984 $1.46 000001078915-3562507200
2022 2 FD52 07 E123 D 1249801D 011 8/25/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR082L1062123606984 $58.79 000001078915-3562507200
2022 2 FD52 07 E123 D 1249801D 011 8/25/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR082L1062123606984 $0.39 000001078915-3562507200
2022 2 FD52 07 E124 D 1249801D 011 8/25/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR082L1062123606984 $0.10 000001078915-3562507200
2022 2 FD52 07 E111 D 1249801D 011 8/9/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR081L1062121805836 $350.03 000001078602-3562507204
2022 2 FD52 07 E111 D 1249801D 011 8/9/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121805836 $205.35 000001078602-3562507204
2022 2 FD52 07 E121 D 1249801D 011 8/9/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR081L1062121805836 $23.22 000001078602-3562507204
2022 2 FD52 07 E121 D 1249801D 011 8/9/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121805836 $13.62 000001078602-3562507204
2022 2 FD52 07 E122 D 1249801D 011 8/9/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR081L1062121805836 $293.92 000001078602-3562507204
2022 2 FD52 07 E122 D 1249801D 011 8/9/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121805836 $172.43 000001078602-3562507204
2022 2 FD52 07 E123 D 1249801D 011 8/9/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR081L1062121805836 $76.58 000001078602-3562507204
2022 2 FD52 07 E123 D 1249801D 011 8/9/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121805836 $44.07 000001078602-3562507204
2022 2 FD52 07 E111 D 1249801D 011 8/9/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR081L1062121805841 $236.47 000001078915-3562507200
2022 2 FD52 07 E121 D 1249801D 011 8/9/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR081L1062121805841 $16.47 000001078915-3562507200
2022 2 FD52 07 E122 D 1249801D 011 8/9/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR081L1062121805841 $198.56 000001078915-3562507200
2022 2 FD52 07 E123 D 1249801D 011 8/9/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR081L1062121805841 $53.44 000001078915-3562507200
2022 2 FD52 07 E111 D 1249801D 011 8/9/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081L1062121805823 $400.24 000001077342-3562507204
2022 2 FD52 07 E111 D 1249801D 011 8/9/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121805823 $152.83 000001077342-3562507204
2022 2 FD52 07 E121 D 1249801D 011 8/9/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081L1062121805823 $28.28 000001077342-3562507204
2022 2 FD52 07 E121 D 1249801D 011 8/9/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121805823 $10.52 000001077342-3562507204
2022 2 FD52 07 E122 D 1249801D 011 8/9/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081L1062121805823 $336.07 000001077342-3562507204
2022 2 FD52 07 E122 D 1249801D 011 8/9/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121805823 $128.33 000001077342-3562507204
2022 2 FD52 07 E123 D 1249801D 011 8/9/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR081L1062121805823 $78.75 000001077342-3562507204
2022 2 FD52 07 E123 D 1249801D 011 8/9/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR081L1062121805823 $30.92 000001077342-3562507204
2022 1 FD52 00 E111 D 1249801D 011 7/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR072L1062120404692 $165.58 000001077076-3562500636
2022 1 FD52 00 E111 D 1249801D 011 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404692 $17.54 000001077076-3562500636
2022 1 FD52 00 E121 D 1249801D 011 7/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR072L1062120404692 $11.78 000001077076-3562500636
2022 1 FD52 07 E111 D 1249801D 011 7/26/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR072L1062120404725 $236.47 000001078915-3562507200
2022 1 FD52 00 E121 D 1249801D 011 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404692 $1.24 000001077076-3562500636
2022 1 FD52 07 E111 D 1249801D 011 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404725 $23.65 000001078915-3562507200
2022 1 FD52 00 E122 D 1249801D 011 7/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR072L1062120404692 $139.01 000001077076-3562500636
2022 1 FD52 07 E121 D 1249801D 011 7/26/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR072L1062120404725 $16.77 000001078915-3562507200
2022 1 FD52 00 E122 D 1249801D 011 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404692 $14.73 000001077076-3562500636
2022 1 FD52 07 E121 D 1249801D 011 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404725 $1.68 000001078915-3562507200
2022 1 FD52 00 E123 D 1249801D 011 7/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR072L1062120404692 $35.66 000001077076-3562500636
2022 1 FD52 07 E122 D 1249801D 011 7/26/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR072L1062120404725 $198.56 000001078915-3562507200
2022 1 FD52 00 E123 D 1249801D 011 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404692 $3.74 000001077076-3562500636
2022 1 FD52 07 E122 D 1249801D 011 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404725 $19.86 000001078915-3562507200
2022 1 FD52 00 E124 D 1249801D 011 7/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR072L1062120404692 $0.06 000001077076-3562500636
2022 1 FD52 07 E123 D 1249801D 011 7/26/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR072L1062120404725 $53.49 000001078915-3562507200
2022 1 FD52 00 E124 D 1249801D 011 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404692 $0.01 000001077076-3562500636
2022 1 FD52 07 E123 D 1249801D 011 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404725 $5.30 000001078915-3562507200
2022 1 FD52 07 E124 D 1249801D 011 7/26/2021 0640 ENV STUDIES-GEN-CONSULT CA-XR072L1062120404725 $0.09 000001078915-3562507200
2022 1 FD52 07 E124 D 1249801D 011 7/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR072L1062120404725 $0.01 000001078915-3562507200
2022 1 FD52 07 E143 D 1249801D 011 7/14/2021 1550 DESIGN CONTRACTS-CONSULTANT PRC-2200008669 PON22000003790 GRW AERIAL SURVEYS INC $57,347.68 Simpson Co. 3-8856.00
2022 1 FD52 07 E229 D 1249801D 011 7/12/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL IET-XE13A162521192001690 $8.74
2022 1 FD52 00 E122 D 1249801D 011 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003557 $62.62 000001077076-3562500636
2022 1 FD52 00 E123 D 1249801D 011 7/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071L1062119003557 $35.77 000001077076-3562500636
2022 1 FD52 00 E123 D 1249801D 011 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003557 $15.83 000001077076-3562500636
2022 1 FD52 07 E111 D 1249801D 011 7/12/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR071L1062119003576 $2,859.01 000001078602-3562507204
2022 1 FD52 07 E111 D 1249801D 011 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003576 $100.28 000001078602-3562507204
2022 1 FD52 07 E121 D 1249801D 011 7/12/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR071L1062119003576 $206.16 000001078602-3562507204
2022 1 FD52 07 E121 D 1249801D 011 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003576 $7.29 000001078602-3562507204
2022 1 FD52 07 E122 D 1249801D 011 7/12/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR071L1062119003576 $2,413.85 000001078602-3562507204
2022 1 FD52 07 E122 D 1249801D 011 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003576 $84.67 000001078602-3562507204
2022 1 FD52 07 E123 D 1249801D 011 7/12/2021 1330 CONSULT SPV-RDWAY PLANS-FINAL CA-XR071L1062119003576 $488.81 000001078602-3562507204
2022 1 FD52 07 E123 D 1249801D 011 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003576 $15.14 000001078602-3562507204
2022 1 FD52 00 E111 D 1249801D 011 7/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071L1062119003557 $165.58 000001077076-3562500636
2022 1 FD52 00 E111 D 1249801D 011 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003557 $74.17 000001077076-3562500636
2022 1 FD52 00 E121 D 1249801D 011 7/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071L1062119003557 $11.56 000001077076-3562500636
2022 1 FD52 00 E121 D 1249801D 011 7/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR071L1062119003557 $5.19 000001077076-3562500636
2022 1 FD52 00 E122 D 1249801D 011 7/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR071L1062119003557 $139.76 000001077076-3562500636
2022 1 FD52 00 E111 D 1249801D 011 7/1/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR062L1062117302480 $132.38 000001077076-3562500636
2022 1 FD52 00 E111 D 1249801D 011 7/1/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062L1062117302480 $4.30 000001077076-3562500636
2022 1 FD52 00 E121 D 1249801D 011 7/1/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR062L1062117302480 $9.43 000001077076-3562500636
2022 1 FD52 00 E121 D 1249801D 011 7/1/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062L1062117302480 $0.31 000001077076-3562500636
2022 1 FD52 00 E122 D 1249801D 011 7/1/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR062L1062117302480 $111.30 000001077076-3562500636
2022 1 FD52 00 E122 D 1249801D 011 7/1/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062L1062117302480 $3.63 000001077076-3562500636
2022 1 FD52 00 E123 D 1249801D 011 7/1/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR062L1062117302480 $28.39 000001077076-3562500636
2022 1 FD52 00 E123 D 1249801D 011 7/1/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR062L1062117302480 $0.92 000001077076-3562500636
2022 1 FD52 00 E124 D 1249801D 011 7/1/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR062L1062117302480 $0.07 000001077076-3562500636
2021 10 FD52 00 E123 D 1249801D 011 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308673 $4.03 000001077076-3562500636
2021 10 FD52 00 E124 D 1249801D 011 4/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042L1062111308673 $0.06 000001077076-3562500636
2021 10 FD52 00 E111 D 1249801D 011 4/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042L1062111308673 $165.49 000001077076-3562500636
2021 10 FD52 07 E111 D 1249801D 011 4/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042L1062111308677 $442.71 000001077342-3562507204
2021 10 FD52 00 E111 D 1249801D 011 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308673 $18.87 000001077076-3562500636
2021 10 FD52 07 E111 D 1249801D 011 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308677 $106.24 000001077342-3562507204
2021 10 FD52 07 E121 D 1249801D 011 4/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042L1062111308677 $31.88 000001077342-3562507204
2021 10 FD52 07 E121 D 1249801D 011 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308677 $7.65 000001077342-3562507204
2021 10 FD52 07 E122 D 1249801D 011 4/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042L1062111308677 $373.78 000001077342-3562507204
2021 10 FD52 07 E122 D 1249801D 011 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308677 $89.69 000001077342-3562507204
2021 10 FD52 07 E123 D 1249801D 011 4/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042L1062111308677 $80.33 000001077342-3562507204
2021 10 FD52 07 E123 D 1249801D 011 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308677 $19.07 000001077342-3562507204
2021 10 FD52 07 E124 D 1249801D 011 4/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042L1062111308677 $0.14 000001077342-3562507204
2021 10 FD52 07 E124 D 1249801D 011 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308677 $0.03 000001077342-3562507204
2021 10 FD52 00 E121 D 1249801D 011 4/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042L1062111308673 $11.78 000001077076-3562500636
2021 10 FD52 00 E121 D 1249801D 011 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308673 $1.34 000001077076-3562500636
2021 10 FD52 00 E122 D 1249801D 011 4/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042L1062111308673 $139.76 000001077076-3562500636
2021 10 FD52 00 E122 D 1249801D 011 4/26/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR042L1062111308673 $15.93 000001077076-3562500636
2021 10 FD52 00 E123 D 1249801D 011 4/26/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR042L1062111308673 $35.66 000001077076-3562500636
2021 10 FD52 00 E111 D 1249801D 011 4/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041L1062109907648 $455.20 000001077076-3562500636
2021 10 FD52 00 E111 D 1249801D 011 4/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041L1062109907648 $47.34 000001077076-3562500636
2021 10 FD52 00 E121 D 1249801D 011 4/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041L1062109907648 $31.81 000001077076-3562500636
2021 10 FD52 00 E121 D 1249801D 011 4/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041L1062109907648 $3.31 000001077076-3562500636
2021 10 FD52 00 E122 D 1249801D 011 4/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041L1062109907648 $384.35 000001077076-3562500636
2021 10 FD52 00 E122 D 1249801D 011 4/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041L1062109907648 $39.97 000001077076-3562500636
2021 10 FD52 00 E123 D 1249801D 011 4/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041L1062109907648 $98.07 000001077076-3562500636
2021 10 FD52 00 E123 D 1249801D 011 4/12/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR041L1062109907648 $10.10 000001077076-3562500636
2021 10 FD52 07 E111 D 1249801D 011 4/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041L1062109907652 $2,705.42 000001077342-3562507204
2021 10 FD52 07 E121 D 1249801D 011 4/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041L1062109907652 $190.65 000001077342-3562507204
2021 10 FD52 07 E122 D 1249801D 011 4/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041L1062109907652 $2,284.19 000001077342-3562507204
2021 10 FD52 07 E123 D 1249801D 011 4/12/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR041L1062109907652 $489.91 000001077342-3562507204
2021 9 FD52 00 E111 D 1249801D 011 3/24/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032L1062108206577 $314.52 000001077076-3562500636
2021 9 FD52 00 E121 D 1249801D 011 3/24/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032L1062108206577 $22.38 000001077076-3562500636
2021 9 FD52 00 E122 D 1249801D 011 3/24/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032L1062108206577 $265.55 000001077076-3562500636
2021 9 FD52 00 E123 D 1249801D 011 3/24/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032L1062108206577 $67.70 000001077076-3562500636
2021 9 FD52 00 E124 D 1249801D 011 3/24/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR032L1062108206577 $0.12 000001077076-3562500636
2021 9 FD52 00 E111 D 1249801D 011 3/10/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031L1062106805544 $202.32 000001077076-3562500636
2021 9 FD52 00 E111 D 1249801D 011 3/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031L1062106805544 $8.10 000001077076-3562500636
2021 9 FD52 00 E121 D 1249801D 011 3/10/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031L1062106805544 $14.14 000001077076-3562500636
2021 9 FD52 00 E121 D 1249801D 011 3/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031L1062106805544 $0.56 000001077076-3562500636
2021 9 FD52 00 E122 D 1249801D 011 3/10/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031L1062106805544 $170.83 000001077076-3562500636
2021 9 FD52 00 E122 D 1249801D 011 3/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031L1062106805544 $6.83 000001077076-3562500636
2021 9 FD52 00 E123 D 1249801D 011 3/10/2021 1040 ROADWAY PLANS-PRELIMINARY-OFF CA-XR031L1062106805544 $43.55 000001077076-3562500636
2021 9 FD52 00 E123 D 1249801D 011 3/10/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR031L1062106805544 $1.73 000001077076-3562500636
2021 8 FD52 00 E111 D 1249801D 011 2/23/2021 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR022L1062105304434 $885.06 000001076861-3562500061
2021 8 FD52 00 E111 D 1249801D 011 2/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022L1062105304434 $108.42 000001076861-3562500061
2021 8 FD52 00 E121 D 1249801D 011 2/23/2021 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR022L1062105304434 $66.28 000001076861-3562500061
2021 8 FD52 00 E121 D 1249801D 011 2/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022L1062105304434 $8.12 000001076861-3562500061
2021 8 FD52 00 E122 D 1249801D 011 2/23/2021 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR022L1062105304434 $747.25 000001076861-3562500061
2021 8 FD52 00 E122 D 1249801D 011 2/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022L1062105304434 $91.54 000001076861-3562500061
2021 8 FD52 00 E123 D 1249801D 011 2/23/2021 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR022L1062105304434 $168.50 000001076861-3562500061
2021 8 FD52 00 E123 D 1249801D 011 2/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022L1062105304434 $20.33 000001076861-3562500061
2021 8 FD52 00 E124 D 1249801D 011 2/23/2021 0091 ENV STUDIES-ENV PROJ MGR (EPM) CA-XR022L1062105304434 $0.44 000001076861-3562500061
2021 8 FD52 00 E124 D 1249801D 011 2/23/2021 7777 FEDERAL NON-PARTICIPATING LEAVE COSTS CA-XR022L1062105304434 $0.05 000001076861-3562500061