WATSON LN,WATSON LN,WATSON LN |
HENDERSON |
$330,000.00 |
94402 - 3 |
11/30/2023 |
THIS AUTHORIZATION DEOBLIGATES $1,300,000 FEDERAL STP FROM (2-383.00 ROW) AND OBLIGATES $1,000,000 (2-383.10) AND $630,000 (2-383.20) OF FEDERAL STP FUNDS FOR THE ROW PHASES. (STATE FUND MATCH) |
CS 1372 |
WATSON LN,WATSON LN,WATSON LN |
HENDERSON |
$3,210,000.00 |
94402 - 2 |
8/12/2021 |
THIS AUTHORIZATION PROVIDES FEDERAL STP FUNDS FOR THE R/W AND UTILITY PHASES OF THE PROJECT WITH STATE FUND MATCH. *C-PHASE UNDER BREAKOUTS 2-383.10/.20* |
CS 1372 |
WATSON LN,WATSON LN,WATSON LN |
HENDERSON |
$500,000.00 |
94402 - 1 |
9/3/2020 |
THIS MODIFICATION PROVIDES ADDITIONAL FEDERAL STP DESIGN FUNDS TO FINALIZE PHASE II ACTIVITIES AND TO FEDERALIZE THE PROJECT. |
CS 1372 |
WATSON LN,WATSON LN,WATSON LN |
HENDERSON |
$400,000.00 |
94402 - 0 |
6/20/2018 |
THIS AUTHORIZATION PROVIDES INITIAL DESIGN FUNDS FOR THE PROJECT. TJ |
CS 1372 |