HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$3,000,000.00 |
92242 - 14 |
3/9/2023 |
THIS AUTHORIZATION PROVIDES FD52 NHPP FUNDS WITH STATE MATCHING FUNDS FOR PE AND ENVIRONMENTAL. (INDOT WILL WILL REIMBURSE 50% OF THE DESIGN COSTS - $1.5M). |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$8,300,000.00 |
92242 - 13 |
6/9/2022 |
THIS MODIFICATION PROVIDES $1,500,000 FEDERAL NH FUNDS FOR DESIGN PHASE TO COVER BI-STATE EXPENSES WITH INDOT AND $6,800,000 FEDERAL NH FUNDS FOR CONSTRUCTION PHASE TO COVER IN-LIEU FEES ON THE PROJECT. (STATE FUND MATCH) |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$3,000,000.00 |
92242 - 12 |
5/5/2022 |
THIS MODIFICATION PROVIDES $3,000,000 FEDERAL NH FUNDS TO COVER R/W ACQUISTIONS WITH STATE FUND MATCH. (PREVIOUS AUTHORIZATION WAS UNDERESTIMATED) |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$3,250,000.00 |
92242 - 11 |
4/18/2022 |
THIS AUTHORIZATION TRANSFERS $2,750,000 FEDERAL NH FUNDS FROM PROGRAM (92242-01) INTO PROGRAM (92242-02R) AND AUTHORIZES AN ADDITIONAL $3,250,000 FEDERAL NH FUNDS (92242-02) TO COVER COMMISSIONERS AWARDS. STATE FUND MATCH |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
($35,000,000.00) |
92242 - 10 |
1/10/2022 |
THIS MODIFICATION RELEASES $28,000,000 FEDERAL NHPP AND $7,000,000 STATE MATCHING FUNDS BASED ON AWARD AMOUNT FOR THE DESIGN-BUILD CONTRACT. (TOTAL AUTH $186,000,000 INCL. 20% STATE MATCH) |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$232,000,000.00 |
92242 - 9 |
9/9/2021 |
THIS AUTHORIZATION PROVIDES ADDITIONAL FD52 NHPP FUNDS FOR THE R/W PHASE, INITIAL UTILITY FUNDS, AND INITIAL CONSTRUCTION FUNDS FOR ITEM NO. 2-1088.20, THE I-69 ORX SECTION 1 DESIGN-BUILD PROJECT. |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$4,000,000.00 |
92242 - 8 |
4/12/2021 |
THIS AUTHORIZATION PROVIDES $3,200,000 OF FEDERAL NH FUNDS WITH $800,000 OF 20% STATE MATCHING FUNDS TOTAL OF $4,000,000 FOR CONTINUATION OF PE AND DESIGN-BUILD PROCUREMENT ACTIVITIES. |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$7,825,000.00 |
92242 - 7 |
3/24/2021 |
THIS AUTHORIZATION PROVIDES FEDERAL NHPP FUNDS FOR ADVANCED ACQUISTION OF R/W FUNDS FOR THE PROJECT. (STATE FUND MATCH) (APPROVED BY FHWA TO ADVANCE FUNDING) |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$1,975,000.00 |
92242 - 6 |
2/22/2021 |
THIS AUTHORIZATION PROVIDES FEDERAL NHPP FUNDS FOR ADVANCED ACQUISTION OF R/W FUNDS FOR THE PROJECT. (STATE FUND MATCH) (APPROVED BY FHWA TO ADVANCE FUNDING) |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$500,000.00 |
92242 - 5 |
11/30/2020 |
THIS AUTHORIZATION PROVIDES FEDERAL NHPP FUNDS FOR ADVANCED ACQUISTION OF R/W FUNDS FOR PARCEL #632. (STATE FUND MATCH) (APPROVED BY FHWA TO ADVANCE FUNDING) |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$9,000,000.00 |
92242 - 4 |
10/13/2020 |
THIS AUTHORIZATION PROVIDES $7,200,000 OF FEDERAL NH FUNDS WITH $1,800,000 OF 20% STATE MATCHING FUNDS TOTAL OF $9,000,000 FOR CONTINUATION OF PE AND ENVIRONMENTAL ACTIVITIES. |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$65,000.00 |
92242 - 3 |
7/6/2020 |
FUNDING FOR THE R/W PHASE OF THIS PROJECT IS PART OF THE “ADVANCE ACQUISITION OF R/W” PROGRAM TEMPORARILY USING STATE FUNDS, AND THE R/W PHASE WILL BE PROGRAMMED FOR REIMBURSEMENT OF FEDERAL FUNDING UPON COMPLETION OF THE PROJECT ENVIRONMENTAL DOCUMENT. |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$200,000.00 |
92242 - 2 |
3/4/2019 |
THIS MODIFICATION PROVIDES $200,000 (FD52) TO COVER KYTC STATE FORCE CHARGES UNDER EMARS#92242-02P. TJ |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$200,000.00 |
92242 - 1 |
3/8/2018 |
THIS MODIFICATION PROVIDES ADDITIONAL FUNDS TO COVER KYTC STATE FORCE CHARGES UNDER EMARS#92242-02P. TJ |
|
HENDERSON, KY- EVANSVILLE, IN |
HENDERSON |
$8,820,000.00 |
92242 - 0 |
9/22/2016 |
THIS AUTHORIZATION PROVIDES INITIAL PLANNING/DESIGN FUNDING FOR THE PROJECT. TJ |
|