Highway Plan Phase Info
Phase Funding FY Amount
Right of way NH 2026 $2,500,000.00
Utility Relocation NH 2027 $2,500,000.00
Construction NH 2028 $10,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D $0.00 AUTHORIZED 6/20/2018 $2,000,000.00
R NH $2,500,000.00 2026 ESTIMATED $0.00
U NH $2,500,000.00 2027 ESTIMATED $0.00
C NH $10,000,000.00 2028 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 94405 9440501D $2,000,000.00 $0.00 $1,505,668.28 $390,487.19 $132,778.71
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: SAFETY, SPOT IMPROVEMENTS AND CONGESTION MITIGATION FOR INDUSTRIAL PARKWAY (KY 67) IN CARTER, BOYD, AND GREENUP COUNTIES FOR BRAIDY INDUSTRIES ALUMINUM PLANT DEVELOPMENT.
Location:
Route 1 Boyd County KY-67 from MP 0 to MP 0.845
Route 2 22 County KY - from MP 0 to MP 0.33567
Item #: 9-397.00
Project Manager: KYTC\DARRIN.ELDRIDGE
Road Engineer: GRW Engineers, Inc.
Type of Work: SAFETY(P)
Concerns:
Bridge Engineer:
Bridge Structure Number: 010B00069N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 95
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\DARRIN.ELDRIDGE       Item #: 9-397.00
Project Description: SAFETY, SPOT IMPROVEMENTS AND CONGESTION MITIGATION FOR INDUSTRIAL PARKWAY (KY 67) IN CARTER, BOYD, AND GREENUP COUNTIES FOR BRAIDY INDUSTRIES ALUMINUM PLANT DEVELOPMENT.

Milestones
Milestones Status Status Date Scheduled
GEOTEC ENGINEERING - BRIDGES SCHEDULED COMPLETION DATE 03/29/2019 03/29/2019
RIGHT OF WAY PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 02/14/2020 02/14/2020
TRAFFIC PLANS - TRAFFIC CONTROL REQUIRED 03/18/2019 03/18/2019
ROAD PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 07/31/2020 07/31/2020
DRAINAGE INSPECTION SCHEDULED COMPLETION DATE 11/15/2019 11/15/2019
ROAD PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 07/31/2020 07/31/2020
DRAINAGE INSPECTION SCHEDULED COMPLETION DATE 11/15/2019 11/15/2019
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 07/31/2020 07/31/2020
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 07/31/2020 07/31/2020
JOINT INSPECTION SCHEDULED COMPLETION DATE 11/15/2019 11/15/2019
PRELIMINARY LINE AND GRADE INSPECTION HELD 08/27/2019 08/27/2019
TRAFFIC PLANS - SIGNALS NOT REQUIRED 03/18/2019 03/18/2019
TRAFFIC PLANS - SIGNING REQUIRED 03/18/2019 03/18/2019
ADVANCE SITUATION TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 02/14/2020 02/14/2020
GEOTEC ENGINEERING - ROADWAY SCHEDULED COMPLETION DATE 03/29/2019 03/29/2019
RIGHT OF WAY PLANS TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 02/14/2020 02/14/2020
JOINT INSPECTION SCHEDULED COMPLETION DATE 11/15/2019 11/15/2019
GEOTEC ENGINEERING - BRIDGES SCHEDULED COMPLETION DATE 03/29/2019 03/29/2019
ADVANCE SITUATION TO CENTRAL OFFICE SCHEDULED COMPLETION DATE 02/14/2020 02/14/2020
GEOTEC ENGINEERING - ROADWAY SCHEDULED COMPLETION DATE 03/29/2019 03/29/2019
TRAFFIC PLANS - LIGHTING REQUIRED 03/18/2019 03/18/2019
 
Project Manager: KYTC\DARRIN.ELDRIDGE       Item #: 9-397.00
Project Description: SAFETY, SPOT IMPROVEMENTS AND CONGESTION MITIGATION FOR INDUSTRIAL PARKWAY (KY 67) IN CARTER, BOYD, AND GREENUP COUNTIES FOR BRAIDY INDUSTRIES ALUMINUM PLANT DEVELOPMENT.
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
CE LVL 1 7/12/2019 1/15/2020 4/7/2020 4/7/2022

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\DARRIN.ELDRIDGE       Item #: 9-397.00
Project Description: SAFETY, SPOT IMPROVEMENTS AND CONGESTION MITIGATION FOR INDUSTRIAL PARKWAY (KY 67) IN CARTER, BOYD, AND GREENUP COUNTIES FOR BRAIDY INDUSTRIES ALUMINUM PLANT DEVELOPMENT.
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 9-397.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\DARRIN.ELDRIDGE       Item #: 9-397.00
Project Description: SAFETY, SPOT IMPROVEMENTS AND CONGESTION MITIGATION FOR INDUSTRIAL PARKWAY (KY 67) IN CARTER, BOYD, AND GREENUP COUNTIES FOR BRAIDY INDUSTRIES ALUMINUM PLANT DEVELOPMENT.
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
Cannonsburg Water District Water
City of Ashland Sewer
American Electric Power/Kentucky Power Electric
Sanitation District #4 Sewer
City of Ashland Water
Natural Energy Utility Corporation Natural Gas
Ledcor Communication
Windstream Communications LLC Telephone
This Project has no Utilities Data available.
Project Manager: KYTC\DARRIN.ELDRIDGE       Item #: 9-397.00
Project Description: SAFETY, SPOT IMPROVEMENTS AND CONGESTION MITIGATION FOR INDUSTRIAL PARKWAY (KY 67) IN CARTER, BOYD, AND GREENUP COUNTIES FOR BRAIDY INDUSTRIES ALUMINUM PLANT DEVELOPMENT.
Phase Vendor
D GRW ENGINEERS INC
D H W Lochner Inc