Highway Plan Phase Info
Phase Funding FY Amount
Utility Relocation NH 2022 $3,350,000.00
Construction NH 2023 $19,470,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D NH $0.00 2024 AUTHORIZED 11/29/2022 $1,200,000.00
U NH $0.00 2026 AUTHORIZED 11/29/2022 $3,015,000.00
C NH $19,300,000.00 2027 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 94419 9441901D $549,509.10 $0.00 $483,126.65 $4,263.02 $95,013.11
U 94419 9441901U $3,015,000.00 $0.00 $181,518.65 $314,764.18 $2,538,786.57
D 94419 9441902D $650,490.90 $0.00 $650,505.04 $0.00 $0.00
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: IMPROVE KY-461 FROM US-150 TO THE EXISTING FOUR LANE APPROACH AT US-25.(16CCN)(18CCR) (2020CCR) (2022CCR)
Location:
Route 1 Rockcastle County KY-461 from MP 7 to MP 9.404
Route 2 County - from MP to MP
Item #: 8-8952.00
Project Manager: KYTC\JOSEPH.GOSSAGE
Road Engineer: CONSULTANT
Type of Work: RECONSTRUCTION
Concerns:
Bridge Engineer:
Bridge Structure Number: 102B00058N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 83.8
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-8952.00
Project Description: IMPROVE KY-461 FROM US-150 TO THE EXISTING FOUR LANE APPROACH AT US-25.(16CCN)(18CCR) (2020CCR) (2022CCR)

Milestones
Milestones Status Status Date Scheduled
DRAINAGE INSPECTION UNKNOWN 05/24/2016 05/24/2016
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
JOINT INSPECTION UNKNOWN 05/24/2016 05/24/2016
GEOTEC ENGINEERING - ROADWAY UNKNOWN 05/24/2016 05/24/2016
ROAD PLANS TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 05/24/2016 05/24/2016
TRAFFIC PLANS - SIGNALS UNKNOWN 05/24/2016 05/24/2016
RIGHT OF WAY PLANS TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
TRAFFIC PLANS - LIGHTING UNKNOWN 05/24/2016 05/24/2016
TRAFFIC PLANS - SIGNING UNKNOWN 05/24/2016 05/24/2016
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
GEOTEC ENGINEERING - BRIDGES UNKNOWN 05/24/2016 05/24/2016
PRELIMINARY LINE AND GRADE UNKNOWN 05/24/2016 05/24/2016
 
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-8952.00
Project Description: IMPROVE KY-461 FROM US-150 TO THE EXISTING FOUR LANE APPROACH AT US-25.(16CCN)(18CCR) (2020CCR) (2022CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
CE LVL 1 2/15/2019 Palmer Engineering 2/15/2019 8/30/2021 8/30/2023

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-8952.00
Project Description: IMPROVE KY-461 FROM US-150 TO THE EXISTING FOUR LANE APPROACH AT US-25.(16CCN)(18CCR) (2020CCR) (2022CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 8-8952.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-8952.00
Project Description: IMPROVE KY-461 FROM US-150 TO THE EXISTING FOUR LANE APPROACH AT US-25.(16CCN)(18CCR) (2020CCR) (2022CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
AT&T - KY Telephone
Windstream Holdings II, LLC Communication
Charter Communications Holdings, LLC dba Spectrum Communication
Rockcastle County Board of Education Communication
Kentucky Communications Network Authority Communication
Kentucky Utilities Electric
City of Mt. Vernon Water
Jackson Energy Cooperative Corporation Electric
Agreements
Utility Company Agreement Status Agreement Amnt Document Type Estimate Approval Date Plans Approval Date Working Days Estimated Completion Date Work Status
Charter Communications Holdings, LLC dba Spectrum - Communication Executed 0 No Charge Agreement 30
City of Mt. Vernon - Water Executed 373200 KRS 177 Engineering Service Agreement 10/6/2023 0
Jackson Energy Cooperative Corporation - Electric Executed 0 No Charge Agreement 10
Kentucky Communications Network Authority - Communication Executed 0 No Charge Agreement 20
Kentucky Utilities - Electric Executed 0 No Charge Agreement 20
Windstream Holdings II, LLC - Communication Executed 0 No Charge Agreement 20
Project Manager: KYTC\JOSEPH.GOSSAGE       Item #: 8-8952.00
Project Description: IMPROVE KY-461 FROM US-150 TO THE EXISTING FOUR LANE APPROACH AT US-25.(16CCN)(18CCR) (2020CCR) (2022CCR)
Phase Vendor
D VAUGHN & MELTON CONSULTING ENGINEERS INC