Highway Plan Phase Info
Phase Funding FY Amount
Right of way STP 2022 $1,158,000.00
Utility Relocation STP 2023 $1,406,000.00
Construction STP 2025 $8,517,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D SPP $0.00 2023 AUTHORIZED 5/25/2023 $1,226,000.00
R STP $5,155,000.00 2024 ESTIMATED $0.00
U STP $1,600,000.00 2024 ESTIMATED $0.00
C STP $6,464,771.00 2024 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 14073 1407301D $1,226,000.00 $0.00 $953,692.93 $338,526.00 $3,662.08
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: IMPROVE CAPACITY AND ACCESS ON KY 2906 FROM US 460 TO US 62 (2020CCN) (2022CCR)
Location:
Route 1 Scott County KY-2906 from MP 0 to MP 1.118
Route 2 County - from MP to MP
Item #: 7-80102.00
Project Manager: KYTC\LAUREN.MEIGHAN
Road Engineer:
Type of Work: CONGESTION MITIGTN(O)
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-80102.00
Project Description: IMPROVE CAPACITY AND ACCESS ON KY 2906 FROM US 460 TO US 62 (2020CCN) (2022CCR)

This Project has no Milesones defined.
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-80102.00
Project Description: IMPROVE CAPACITY AND ACCESS ON KY 2906 FROM US 460 TO US 62 (2020CCN) (2022CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
CE LVL 1 RE 3/12/2024 3/12/2024 3/12/2024 3/12/2026
District Office CE LVL 1 4/1/2022 Lochner H. W., Inc. 4/1/2022 2/28/2023 11/27/2023 11/27/2025
Preliminary 6/3/2021 6/3/2021

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-80102.00
Project Description: IMPROVE CAPACITY AND ACCESS ON KY 2906 FROM US 460 TO US 62 (2020CCN) (2022CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 7-80102.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-80102.00
Project Description: IMPROVE CAPACITY AND ACCESS ON KY 2906 FROM US 460 TO US 62 (2020CCN) (2022CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-80102.00
Project Description: IMPROVE CAPACITY AND ACCESS ON KY 2906 FROM US 460 TO US 62 (2020CCN) (2022CCR)
This Project has no Vendors Assigned.