Highway Plan Phase Info
Phase Funding FY Amount
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D FED $0.00 2022 AUTHORIZED 10/21/2020 $2,080,000.00
R STP $6,600,000.00 2024 ESTIMATED $0.00
U STP $3,000,000.00 2024 ESTIMATED $0.00
C STP $13,700,000.00 2024 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 12498 1249801D $2,080,000.00 $0.00 $755,569.57 $146,332.96 $1,212,050.91
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: CONSTRUCT A NEW CONNECTOR ROAD ON THE EAST SIDE OF DANVILLE CONNECTING KY-34 AND US-150 BYPASS(18CCN) (2020CCR)
Location:
Route 1 Boyle County CO-0 from MP to MP
Route 2 11 County PF- from MP to MP 9999
Item #: 7-80000.00
Project Manager: KYTC\LAUREN.MEIGHAN
Road Engineer:
Type of Work: NEW ROUTE(O)
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-80000.00
Project Description: CONSTRUCT A NEW CONNECTOR ROAD ON THE EAST SIDE OF DANVILLE CONNECTING KY-34 AND US-150 BYPASS(18CCN) (2020CCR)

Milestones
Milestones Status Status Date Scheduled
TRAFFIC PLANS - LIGHTING UNKNOWN 07/10/2018 07/10/2018
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
JOINT INSPECTION UNKNOWN 07/10/2018 07/10/2018
DRAINAGE INSPECTION UNKNOWN 07/10/2018 07/10/2018
GEOTEC ENGINEERING - ROADWAY UNKNOWN 07/10/2018 07/10/2018
GEOTEC ENGINEERING - BRIDGES UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - SIGNING UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - SIGNALS UNKNOWN 07/10/2018 07/10/2018
RIGHT OF WAY PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
PRELIMINARY LINE AND GRADE UNKNOWN 07/10/2018 07/10/2018
ROAD PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
 
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-80000.00
Project Description: CONSTRUCT A NEW CONNECTOR ROAD ON THE EAST SIDE OF DANVILLE CONNECTING KY-34 AND US-150 BYPASS(18CCN) (2020CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
District Office CE LVL 1 9/1/2021 Third Rock Consultants, LLC 9/1/2021 9/30/2022
Preliminary 9/29/2020 9/29/2020

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-80000.00
Project Description: CONSTRUCT A NEW CONNECTOR ROAD ON THE EAST SIDE OF DANVILLE CONNECTING KY-34 AND US-150 BYPASS(18CCN) (2020CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 7-80000.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-80000.00
Project Description: CONSTRUCT A NEW CONNECTOR ROAD ON THE EAST SIDE OF DANVILLE CONNECTING KY-34 AND US-150 BYPASS(18CCN) (2020CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\LAUREN.MEIGHAN       Item #: 7-80000.00
Project Description: CONSTRUCT A NEW CONNECTOR ROAD ON THE EAST SIDE OF DANVILLE CONNECTING KY-34 AND US-150 BYPASS(18CCN) (2020CCR)
This Project has no Vendors Assigned.