Highway Plan Phase Info
Phase Funding FY Amount
Right of way STP 2023 $5,000,000.00
Utility Relocation STP 2024 $2,000,000.00
Construction STP 2024 $8,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D FED $0.00 2022 AUTHORIZED 10/2/2020 $400,000.00
R STP $5,000,000.00 2023 ESTIMATED $0.00
U STP $2,000,000.00 2024 ESTIMATED $0.00
C STP $9,500,000.00 2024 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 12373 1237301D $400,000.00 $0.00 $274,817.29 $0.00 $172,760.21
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: Reconstruct Turfway Road (KY 717) from Aero Parkway (MP 0.0) to Donaldson Road (MP 1.67). (2020CCN) (2022CCR)
Location:
Route 1 Boone County KY-717 from MP 0 to MP 0.368
Route 2 8 County KY - from MP 0.368 to MP 1.67717
Item #: 6-80150.00
Project Manager: KYTC\MIKE.BEZOLD
Road Engineer:
Type of Work: MAJOR WIDENING
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-80150.00
Project Description: Reconstruct Turfway Road (KY 717) from Aero Parkway (MP 0.0) to Donaldson Road (MP 1.67). (2020CCN) (2022CCR)

This Project has no Milesones defined.
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-80150.00
Project Description: Reconstruct Turfway Road (KY 717) from Aero Parkway (MP 0.0) to Donaldson Road (MP 1.67). (2020CCN) (2022CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
District Office CE LVL 2 1/2/2023 Lochner H. W., Inc. 1/2/2023 2/29/2024
CE LVL 1 1/2/2023 Lochner H. W., Inc. 1/2/2023 1/31/2024
Preliminary 1/27/2021

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-80150.00
Project Description: Reconstruct Turfway Road (KY 717) from Aero Parkway (MP 0.0) to Donaldson Road (MP 1.67). (2020CCN) (2022CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 6-80150.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-80150.00
Project Description: Reconstruct Turfway Road (KY 717) from Aero Parkway (MP 0.0) to Donaldson Road (MP 1.67). (2020CCN) (2022CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-80150.00
Project Description: Reconstruct Turfway Road (KY 717) from Aero Parkway (MP 0.0) to Donaldson Road (MP 1.67). (2020CCN) (2022CCR)
This Project has no Vendors Assigned.