Highway Plan Phase Info
Phase Funding FY Amount
Right of way NH 2026 $16,000,000.00
Utility Relocation NH 2027 $10,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D FED $0.00 2025 AUTHORIZED 4/8/2021 $3,200,000.00
R NH $20,000,000.00 2027 ESTIMATED $0.00
U NH $10,000,000.00 2027 ESTIMATED $0.00
C NH $260,000,000.00 2027 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 94411 9441101D $3,200,000.00 $0.00 $2,855,717.32 $280,371.88 $85,220.19
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: IMPROVE SAFETY, MOBILITY, OPERATIONS, AND GEOMETRICS AT THE JUNCTION OF I-75 AND I-275 AND THE SYSTEM-TO-SYSTEM RAMPS.
Location:
Route 1 Boone County I -75 from MP 182.978 to MP 183.312
Route 2 59 County I - from MP 183.312 to MP 185.3475
Item #: 6-79.00
Project Manager: KYTC\MIKE.BEZOLD
Road Engineer: Burgess and Niple, Inc.
Type of Work: CONGESTION MITIGATION
Concerns:
Bridge Engineer:
Bridge Structure Number: 059B00053L
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 96.3
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-79.00
Project Description: IMPROVE SAFETY, MOBILITY, OPERATIONS, AND GEOMETRICS AT THE JUNCTION OF I-75 AND I-275 AND THE SYSTEM-TO-SYSTEM RAMPS.

Milestones
Milestones Status Status Date Scheduled
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 07/10/2018 07/10/2018
ROAD PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
DRAINAGE INSPECTION UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - LIGHTING UNKNOWN 07/10/2018 07/10/2018
PRELIMINARY LINE AND GRADE UNKNOWN 07/10/2018 07/10/2018
GEOTEC ENGINEERING - BRIDGES UNKNOWN 07/10/2018 07/10/2018
RIGHT OF WAY PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - SIGNING UNKNOWN 07/10/2018 07/10/2018
JOINT INSPECTION UNKNOWN 07/10/2018 07/10/2018
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - SIGNALS UNKNOWN 07/10/2018 07/10/2018
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
GEOTEC ENGINEERING - ROADWAY UNKNOWN 07/10/2018 07/10/2018
 
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-79.00
Project Description: IMPROVE SAFETY, MOBILITY, OPERATIONS, AND GEOMETRICS AT THE JUNCTION OF I-75 AND I-275 AND THE SYSTEM-TO-SYSTEM RAMPS.
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
District Office CE LVL 3 9/1/2021 Burgess & Niple, Inc. 9/1/2021 4/30/2024

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-79.00
Project Description: IMPROVE SAFETY, MOBILITY, OPERATIONS, AND GEOMETRICS AT THE JUNCTION OF I-75 AND I-275 AND THE SYSTEM-TO-SYSTEM RAMPS.
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 6-79.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-79.00
Project Description: IMPROVE SAFETY, MOBILITY, OPERATIONS, AND GEOMETRICS AT THE JUNCTION OF I-75 AND I-275 AND THE SYSTEM-TO-SYSTEM RAMPS.
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
The Cincinnati, New Orleans and Texas Pacific Railway Company Railroad
This Project has no Utilities Data available.
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-79.00
Project Description: IMPROVE SAFETY, MOBILITY, OPERATIONS, AND GEOMETRICS AT THE JUNCTION OF I-75 AND I-275 AND THE SYSTEM-TO-SYSTEM RAMPS.
Phase Vendor
D BURGESS AND NIPLE INC