Highway Plan Phase Info
Phase Funding FY Amount
Planning STP 2019 $2,000,000.00
Design STP 2020 $5,000,000.00
Right of way STP 2023 $1,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
P STP $2,000,000.00 2019 ESTIMATED $0.00
D STP $0.00 2020 AUTHORIZED 12/6/2018 $2,000,000.00
R STP $6,000,000.00 2023 ESTIMATED $0.00
U STP $500,000.00 2025 ESTIMATED $0.00
C STP $18,000,000.00 2025 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 94410 9441001D $2,000,000.00 $0.00 $10,894.94 $826,805.00 $1,162,300.06
R/W Clearance:
Utility Clearance:
Some critical dates have not been assigned. (Letting Date not Established)

Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ALONG KY-236 (DONALDSON ROAD) FROM KY-842 (HOUSTON ROAD) TO KY-3076 (MINEOLA PIKE). (18CCR)(DESIGN INCLUDES ITEM # 6-445)
Location:
Route 1 BOONE County KY-236 from MP 0 to MP 1.594
Route 2 KENTON County KY- from MP 2.684 to MP 2.801236
Item #: 6-444.00
Project Manager: KYTC\MIKE.BEZOLD
Road Engineer: consultant
Type of Work: MAJOR WIDENING(O)

Concerns:

Bridge Engineer:
Bridge Structure Number:
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-444.00
Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ALONG KY-236 (DONALDSON ROAD) FROM KY-842 (HOUSTON ROAD) TO KY-3076 (MINEOLA PIKE). (18CCR)(DESIGN INCLUDES ITEM # 6-445)
Milestones
Milestones Status Status Date Scheduled
PRELIMINARY LINE AND GRADE REQUIRED 02/28/2019 04/01/2020
DRAINAGE INSPECTION REQUIRED 02/28/2019
JOINT INSPECTION REQUIRED 02/28/2019 06/01/2021
GEOTEC ENGINEERING - ROADWAY REQUIRED 02/28/2019
GEOTEC ENGINEERING - BRIDGES UNKNOWN 07/10/2018
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 07/10/2018
RIGHT OF WAY PLANS TO CENTRAL OFFICE REQUIRED 02/28/2019 08/01/2021
ROAD PLANS TO CENTRAL OFFICE REQUIRED 02/28/2019 08/01/2024
TRAFFIC PLANS - SIGNING UNKNOWN 07/10/2018
TRAFFIC PLANS - LIGHTING UNKNOWN 07/10/2018
TRAFFIC PLANS - SIGNALS UNKNOWN 07/10/2018
TRAFFIC PLANS - TRAFFIC CONTROL REQUIRED 02/28/2019
 

Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-444.00
Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ALONG KY-236 (DONALDSON ROAD) FROM KY-842 (HOUSTON ROAD) TO KY-3076 (MINEOLA PIKE). (18CCR)(DESIGN INCLUDES ITEM # 6-445)

Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
Environmental Analysis CE LVL 3 5/13/2019 Lochner, H.W., Inc. 6/1/2020

No IND Permit Data Available

No NW Permit Data Available

No WQC Permit Data Available

No KPD Permit Data Available

No TVA Permit Data Available

Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-444.00
Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ALONG KY-236 (DONALDSON ROAD) FROM KY-842 (HOUSTON ROAD) TO KY-3076 (MINEOLA PIKE). (18CCR)(DESIGN INCLUDES ITEM # 6-445)

This Project has no Right Of Way Data available.

Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-444.00
Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ALONG KY-236 (DONALDSON ROAD) FROM KY-842 (HOUSTON ROAD) TO KY-3076 (MINEOLA PIKE). (18CCR)(DESIGN INCLUDES ITEM # 6-445)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\MIKE.BEZOLD       Item #: 6-444.00
Project Description: IMPROVE SAFETY AND REDUCE CONGESTION ALONG KY-236 (DONALDSON ROAD) FROM KY-842 (HOUSTON ROAD) TO KY-3076 (MINEOLA PIKE). (18CCR)(DESIGN INCLUDES ITEM # 6-445)
This Project has no Vendors Assigned.