Highway Plan Phase Info
Phase Funding FY Amount
Right of way BRO 2023 $2,690,000.00
Utility Relocation BRO 2023 $1,270,000.00
Construction BRO 2024 $64,080,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D FED $0.00 2021 AUTHORIZED 4/4/2024 $6,898,000.00
R FED $2,690,000.00 2023 ESTIMATED $0.00
U FED $1,270,000.00 2024 ESTIMATED $0.00
C NH $95,000,000.00 2024 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 12099 1209901D $6,755,000.00 $0.00 $4,397,267.77 $2,432,266.06 ($19,110.26)
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: Replace 4th Street Bridge over the Licking River between Covington and Newport; Bridge Number 059B00037N
Location:
Route 1 Campbell County KY-8 from MP 0 to MP 0.19
Route 2 59 County KY - from MP 7.6 to MP 7.6628
Item #: 6-1086.00
Project Manager: KYTC\CAROL.CALLAN-RAMLER
Road Engineer:
Type of Work: AM-BRIDGE (P)
Concerns:
Bridge Engineer:
Bridge Structure Number: 059B00037N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 23.8
NBI Rating: Structurally Deficient
Posting: YES
Project Manager: KYTC\CAROL.CALLAN-RAMLER       Item #: 6-1086.00
Project Description: Replace 4th Street Bridge over the Licking River between Covington and Newport; Bridge Number 059B00037N

Milestones
Milestones Status Status Date Scheduled
TRAFFIC PLANS - LIGHTING UNKNOWN 05/29/2014 05/29/2014
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 05/29/2014 05/29/2014
DRAINAGE INSPECTION UNKNOWN 05/29/2014 05/29/2014
RIGHT OF WAY PLANS TO CENTRAL OFFICE UNKNOWN 05/29/2014 05/29/2014
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 05/29/2014 05/29/2014
GEOTEC ENGINEERING - ROADWAY UNKNOWN 05/29/2014 05/29/2014
TRAFFIC PLANS - SIGNALS UNKNOWN 05/29/2014 05/29/2014
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 05/29/2014 05/29/2014
PRELIMINARY LINE AND GRADE UNKNOWN 05/29/2014 05/29/2014
JOINT INSPECTION UNKNOWN 05/29/2014 05/29/2014
ROAD PLANS TO CENTRAL OFFICE UNKNOWN 05/29/2014 05/29/2014
TRAFFIC PLANS - SIGNING UNKNOWN 05/29/2014 05/29/2014
GEOTEC ENGINEERING - BRIDGES UNKNOWN 05/29/2014 05/29/2014
 
Project Manager: KYTC\CAROL.CALLAN-RAMLER       Item #: 6-1086.00
Project Description: Replace 4th Street Bridge over the Licking River between Covington and Newport; Bridge Number 059B00037N
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
District Office CE LVL 3 1/5/2021 QK4, Inc. 1/5/2021 1/31/2022
Preliminary 2/4/2019

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\CAROL.CALLAN-RAMLER       Item #: 6-1086.00
Project Description: Replace 4th Street Bridge over the Licking River between Covington and Newport; Bridge Number 059B00037N
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 6-1086.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\CAROL.CALLAN-RAMLER       Item #: 6-1086.00
Project Description: Replace 4th Street Bridge over the Licking River between Covington and Newport; Bridge Number 059B00037N
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
Northern Kentucky Water District Water
Duke Energy Kentucky (Gas) Natural Gas
Duke Energy Kentucky (Electric) Electric
CenturyLink Communications LLC dba Lumen Technologies Group Communication
Altafiber Communication
Windstream Communications LLC Telephone
Sanitation District No. 1 Sewer
This Project has no Utilities Data available.
Project Manager: KYTC\CAROL.CALLAN-RAMLER       Item #: 6-1086.00
Project Description: Replace 4th Street Bridge over the Licking River between Covington and Newport; Bridge Number 059B00037N
Phase Vendor
D Rasor Marketing Communications
D STANTEC CONSULTING SERVICES INC
D American Structurepoint Inc
D QK4 INC
D PALMER ENGINEERING CO
D Innovative Contracting & Engineering LLC