Highway Plan Phase Info
Phase Funding FY Amount
Design STP 2022 $470,000.00
Right of way STP 2023 $40,000.00
Utility Relocation STP 2023 $820,000.00
Construction STP 2024 $16,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D STP $0.00 2022 AUTHORIZED 10/4/2023 $1,057,500.00
R STP $3,214,000.00 2024 ESTIMATED $0.00
U STP $8,475,000.00 2024 ESTIMATED $0.00
C STP $21,460,000.00 2025 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 13028 1302801D $1,094,805.53 $0.00 $633,378.35 $403,985.50 $78,086.79
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: CONSTRUCT A 2+1 ROAD ON KY 55/155 (TAYLORSVILLE ROAD) IN SPENCER COUNTY AND KY 155 (TAYLORSVILLE LAKE ROAD) IN JEFFERSON COUNTY BY ADDING A CONTINUOUS THIRD LANE THAT SERVES AS AN ALTERNATING PASSING LANE.(16CCN)(18CCN) (2020CCR) (2022CCR)
Location:
Route 1 Jefferson County KY-155 from MP 0 to MP 4
Route 2 108 County KY - from MP 10.56 to MP 11.2755
Item #: 5-8954.00
Project Manager: KYTC\KEITH.DOWNS
Road Engineer:
Type of Work: RECONSTRUCTION
Concerns:
Bridge Engineer:
Bridge Structure Number: 056B00294N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 73
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\KEITH.DOWNS       Item #: 5-8954.00
Project Description: CONSTRUCT A 2+1 ROAD ON KY 55/155 (TAYLORSVILLE ROAD) IN SPENCER COUNTY AND KY 155 (TAYLORSVILLE LAKE ROAD) IN JEFFERSON COUNTY BY ADDING A CONTINUOUS THIRD LANE THAT SERVES AS AN ALTERNATING PASSING LANE.(16CCN)(18CCN) (2020CCR) (2022CCR)

Milestones
Milestones Status Status Date Scheduled
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 05/24/2016 05/24/2016
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
TRAFFIC PLANS - SIGNING UNKNOWN 05/24/2016 05/24/2016
TRAFFIC PLANS - SIGNALS UNKNOWN 05/24/2016 05/24/2016
PRELIMINARY LINE AND GRADE UNKNOWN 05/24/2016 05/24/2016
ROAD PLANS TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
JOINT INSPECTION UNKNOWN 05/24/2016 05/24/2016
RIGHT OF WAY PLANS TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
GEOTEC ENGINEERING - ROADWAY UNKNOWN 05/24/2016 05/24/2016
TRAFFIC PLANS - LIGHTING UNKNOWN 05/24/2016 05/24/2016
DRAINAGE INSPECTION UNKNOWN 05/24/2016 05/24/2016
GEOTEC ENGINEERING - BRIDGES UNKNOWN 05/24/2016 05/24/2016
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
 
Project Manager: KYTC\KEITH.DOWNS       Item #: 5-8954.00
Project Description: CONSTRUCT A 2+1 ROAD ON KY 55/155 (TAYLORSVILLE ROAD) IN SPENCER COUNTY AND KY 155 (TAYLORSVILLE LAKE ROAD) IN JEFFERSON COUNTY BY ADDING A CONTINUOUS THIRD LANE THAT SERVES AS AN ALTERNATING PASSING LANE.(16CCN)(18CCN) (2020CCR) (2022CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
Design Preliminary 8/3/2021 HDR Engineering, Inc. 8/3/2021 2/14/2022

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\KEITH.DOWNS       Item #: 5-8954.00
Project Description: CONSTRUCT A 2+1 ROAD ON KY 55/155 (TAYLORSVILLE ROAD) IN SPENCER COUNTY AND KY 155 (TAYLORSVILLE LAKE ROAD) IN JEFFERSON COUNTY BY ADDING A CONTINUOUS THIRD LANE THAT SERVES AS AN ALTERNATING PASSING LANE.(16CCN)(18CCN) (2020CCR) (2022CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 5-8954.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\KEITH.DOWNS       Item #: 5-8954.00
Project Description: CONSTRUCT A 2+1 ROAD ON KY 55/155 (TAYLORSVILLE ROAD) IN SPENCER COUNTY AND KY 155 (TAYLORSVILLE LAKE ROAD) IN JEFFERSON COUNTY BY ADDING A CONTINUOUS THIRD LANE THAT SERVES AS AN ALTERNATING PASSING LANE.(16CCN)(18CCN) (2020CCR) (2022CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\KEITH.DOWNS       Item #: 5-8954.00
Project Description: CONSTRUCT A 2+1 ROAD ON KY 55/155 (TAYLORSVILLE ROAD) IN SPENCER COUNTY AND KY 155 (TAYLORSVILLE LAKE ROAD) IN JEFFERSON COUNTY BY ADDING A CONTINUOUS THIRD LANE THAT SERVES AS AN ALTERNATING PASSING LANE.(16CCN)(18CCN) (2020CCR) (2022CCR)
Phase Vendor
D UNIVERSITY OF KENTUCKY RESEARCH FOUNDATION
D PARSONS TRANSPORTATION GROUP INC