Highway Plan Phase Info
Phase Funding FY Amount
Right of way NH 2022 $1,900,000.00
Utility Relocation NH 2022 $1,800,000.00
Construction NH 2024 $36,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D $0.00 2022 AUTHORIZED 6/16/2023 $3,500,000.00
R NH $1,900,000.00 2024 ESTIMATED $0.00
U NH $1,800,000.00 2024 ESTIMATED $0.00
C NH $70,000,000.00 2024 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 89307 8930703D $3,500,000.00 $0.00 $1,513,199.16 $1,171,484.80 $854,433.34
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR)
Location:
Route 1 Oldham County I -71 from MP 14.1 to MP 18
Route 2 County - from MP to MP
Item #: 5-483.10
Project Manager: KYTC\ANDRE.JOHANNES
Road Engineer:
Type of Work: MAJOR WIDENING
Concerns:
Bridge Engineer:
Bridge Structure Number: 093B00009N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 64.9
NBI Rating: Not Deficient
Posting: YES
Project Manager: KYTC\ANDRE.JOHANNES       Item #: 5-483.10
Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR)

Milestones
Milestones Status Status Date Scheduled
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
PRELIMINARY LINE AND GRADE UNKNOWN 05/24/2016 05/24/2016
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 05/24/2016 05/24/2016
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
ROAD PLANS TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
DRAINAGE INSPECTION UNKNOWN 05/24/2016 05/24/2016
TRAFFIC PLANS - LIGHTING UNKNOWN 05/24/2016 05/24/2016
TRAFFIC PLANS - SIGNING UNKNOWN 05/24/2016 05/24/2016
GEOTEC ENGINEERING - BRIDGES UNKNOWN 05/24/2016 05/24/2016
JOINT INSPECTION UNKNOWN 05/24/2016 05/24/2016
GEOTEC ENGINEERING - ROADWAY UNKNOWN 05/24/2016 05/24/2016
TRAFFIC PLANS - SIGNALS UNKNOWN 05/24/2016 05/24/2016
RIGHT OF WAY PLANS TO CENTRAL OFFICE UNKNOWN 05/24/2016 05/24/2016
 
Project Manager: KYTC\ANDRE.JOHANNES       Item #: 5-483.10
Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
Design CE LVL 3 10/11/2021 HMB Professional Engineers, Inc. 10/11/2021 10/11/2023

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\ANDRE.JOHANNES       Item #: 5-483.10
Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 5-483.10
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\ANDRE.JOHANNES       Item #: 5-483.10
Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\ANDRE.JOHANNES       Item #: 5-483.10
Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR)
Phase Vendor
D RHA LLC
D STANTEC CONSULTING SERVICES INC
D HAWORTH MEYER BOLEYN INC
D HORN AND ASSOCIATES INC