Highway Plan Phase Info
Phase Funding FY Amount
Right of way NH 2025 $1,900,000.00
Utility Relocation NH 2025 $1,800,000.00
Construction NH 2026 $70,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D NH $0.00 2022 AUTHORIZED 6/16/2023 $3,500,000.00
R NH $1,900,000.00 2024 ESTIMATED $0.00
U NH $1,800,000.00 2024 ESTIMATED $0.00
C NH $77,000,000.00 2024 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 89307 8930703D $3,500,000.00 $0.00 $2,303,477.71 $607,836.25 $641,062.93
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR) (2024CCR)
Location:
Route 1 Oldham County I -71 from MP 14.1 to MP 18
Route 2 County - from MP to MP
Item #: 5-483.10
Project Manager: KYTC\ANDRE.JOHANNES
Road Engineer:
Type of Work: MAJOR WIDENING
Concerns:
Bridge Engineer:
Bridge Structure Number: 093B00009N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 65.5
NBI Rating: Not Deficient
Posting: YES
Project Manager: KYTC\ANDRE.JOHANNES       Item #: 5-483.10
Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR) (2024CCR)

Milestones
Milestones Status Status Date Scheduled
Planning 01/01/1900
Final Design 01/01/1900
Letting 01/01/1900
Environmental Approval 01/01/1900
Roadway Plans 01/01/1900
Preliminary Engineering 01/01/1900
Railroad Clearance 01/01/1900
ROW Clearance 01/01/1900
Geotechnical - Roadway Design Investigation 01/01/1900
Utility Agreement 01/01/1900
Right of Way Acquisition 01/01/1900
Alternative Selection 01/01/1900
Final Plans Submittal 01/01/1900
Right of Way Plans 01/01/1900
Structure Plans 01/01/1900
Utility Clearance 01/01/1900
 
Project Manager: KYTC\ANDRE.JOHANNES       Item #: 5-483.10
Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR) (2024CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
Design CE LVL 3 10/11/2021 HMB Professional Engineers, Inc. 10/11/2021 10/11/2023 4/29/2024 4/29/2026

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\ANDRE.JOHANNES       Item #: 5-483.10
Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR) (2024CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 5-483.10
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\ANDRE.JOHANNES       Item #: 5-483.10
Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR) (2024CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\ANDRE.JOHANNES       Item #: 5-483.10
Project Description: WIDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). (2022CCR) (2024CCR)
Phase Vendor
D HORN AND ASSOCIATES INC
D RHA LLC
D STANTEC CONSULTING SERVICES INC
D HAWORTH MEYER BOLEYN INC