Highway Plan Phase Info
Phase Funding FY Amount
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D FED $0.00 2021 AUTHORIZED 3/15/2024 $10,950,000.00
C FED $54,000,000.00 2023 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 13777 1377701D $10,250,000.00 $0.00 $4,298,160.11 $5,664,234.70 $298,906.90
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: Address Pavement needs on I-65 between MP 131.24 and MP 135.672 and to replace bridge over Hill Street at MP 133.873; replace bridge over Brook Street at MP 134.753, and to replace bridge over Jacob and Broadway at MP 135.273.
Location:
Route 1 Jefferson County I -65 from MP 131.24 to MP 135.672
Route 2 County - from MP to MP
Item #: 5-20061.00
Project Manager: KYTC\ROYCE.MEREDITH
Road Engineer:
Type of Work: AM-PAVEMENT (PRI)(P)
Concerns:
Bridge Engineer:
Bridge Structure Number: 056B00179N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 53
NBI Rating: Structurally Deficient
Posting: NO
Project Manager: KYTC\ROYCE.MEREDITH       Item #: 5-20061.00
Project Description: Address Pavement needs on I-65 between MP 131.24 and MP 135.672 and to replace bridge over Hill Street at MP 133.873; replace bridge over Brook Street at MP 134.753, and to replace bridge over Jacob and Broadway at MP 135.273.

This Project has no Milesones defined.
Project Manager: KYTC\ROYCE.MEREDITH       Item #: 5-20061.00
Project Description: Address Pavement needs on I-65 between MP 131.24 and MP 135.672 and to replace bridge over Hill Street at MP 133.873; replace bridge over Brook Street at MP 134.753, and to replace bridge over Jacob and Broadway at MP 135.273.
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
Design CE MP 1/4/2021 DEA 1/4/2021 1/6/2021 1/6/2021 1/6/2023

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\ROYCE.MEREDITH       Item #: 5-20061.00
Project Description: Address Pavement needs on I-65 between MP 131.24 and MP 135.672 and to replace bridge over Hill Street at MP 133.873; replace bridge over Brook Street at MP 134.753, and to replace bridge over Jacob and Broadway at MP 135.273.
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 5-20061.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\ROYCE.MEREDITH       Item #: 5-20061.00
Project Description: Address Pavement needs on I-65 between MP 131.24 and MP 135.672 and to replace bridge over Hill Street at MP 133.873; replace bridge over Brook Street at MP 134.753, and to replace bridge over Jacob and Broadway at MP 135.273.
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\ROYCE.MEREDITH       Item #: 5-20061.00
Project Description: Address Pavement needs on I-65 between MP 131.24 and MP 135.672 and to replace bridge over Hill Street at MP 133.873; replace bridge over Brook Street at MP 134.753, and to replace bridge over Jacob and Broadway at MP 135.273.
This Project has no Vendors Assigned.