Highway Plan Phase Info
Phase Funding FY Amount
Right of way STP 2025 $1,600,000.00
Utility Relocation STP 2027 $4,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D $0.00 2022 AUTHORIZED 2/9/2023 $2,110,000.00
R STP $1,250,000.00 2025 ESTIMATED $0.00
U STP $7,925,000.00 2027 ESTIMATED $0.00
C STP $7,850,000.00 2029 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 12097 1209701D $2,110,000.00 $0.00 $1,389,200.86 $456,522.72 $321,314.29
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: IMPROVE US-31W FROM KY-1008 TO KY-621. (14CCN)(16CCR) (2020CCR)
Location:
Route 1 Simpson County US-31W from MP 8.477 to MP 10.799
Route 2 County - from MP to MP
Item #: 3-8856.00
Project Manager: KYTC\STEWART.LICH
Road Engineer:
Type of Work: MAJOR WIDENING
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\STEWART.LICH       Item #: 3-8856.00
Project Description: IMPROVE US-31W FROM KY-1008 TO KY-621. (14CCN)(16CCR) (2020CCR)

Milestones
Milestones Status Status Date Scheduled
ROAD PLANS TO CENTRAL OFFICE UNKNOWN 05/29/2014 05/29/2014
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 05/29/2014 05/29/2014
TRAFFIC PLANS - LIGHTING UNKNOWN 05/29/2014 05/29/2014
GEOTEC ENGINEERING - BRIDGES UNKNOWN 05/29/2014 05/29/2014
DRAINAGE INSPECTION UNKNOWN 05/29/2014 05/29/2014
GEOTEC ENGINEERING - ROADWAY UNKNOWN 05/29/2014 05/29/2014
PRELIMINARY LINE AND GRADE UNKNOWN 05/29/2014 05/29/2014
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 05/29/2014 05/29/2014
TRAFFIC PLANS - SIGNALS UNKNOWN 05/29/2014 05/29/2014
TRAFFIC PLANS - SIGNING UNKNOWN 05/29/2014 05/29/2014
RIGHT OF WAY PLANS TO CENTRAL OFFICE UNKNOWN 05/29/2014 05/29/2014
JOINT INSPECTION UNKNOWN 05/29/2014 05/29/2014
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 05/29/2014 05/29/2014
 
Project Manager: KYTC\STEWART.LICH       Item #: 3-8856.00
Project Description: IMPROVE US-31W FROM KY-1008 TO KY-621. (14CCN)(16CCR) (2020CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
District Office CE LVL 3 8/11/2022 Strand Associates, Inc. 8/11/2022 3/30/2023
Design Preliminary 7/26/2021 Strand Associates, Inc. c/o PEH 7/26/2021 7/18/2022

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\STEWART.LICH       Item #: 3-8856.00
Project Description: IMPROVE US-31W FROM KY-1008 TO KY-621. (14CCN)(16CCR) (2020CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 3-8856.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\STEWART.LICH       Item #: 3-8856.00
Project Description: IMPROVE US-31W FROM KY-1008 TO KY-621. (14CCN)(16CCR) (2020CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\STEWART.LICH       Item #: 3-8856.00
Project Description: IMPROVE US-31W FROM KY-1008 TO KY-621. (14CCN)(16CCR) (2020CCR)
Phase Vendor
D GRW AERIAL SURVEYS INC
D HMB Engineers Inc
D STRAND ASSOCIATES INC