Highway Plan Phase Info
Phase Funding FY Amount
Right of way NH 2024 $12,740,000.00
Utility Relocation NH 2026 $20,810,000.00
Construction NH 2027 $59,010,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D FED $0.00 2023 AUTHORIZED 1/19/2021 $1,500,000.00
R NH $0.00 REESTIMATED $0.00
U NH $0.00 REESTIMATED $0.00
C NH $0.00 REESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 12805 1280501D $1,500,000.00 $0.00 $1,418,184.36 $61,838.09 $33,594.79
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: WIDEN US-79 TO 4 LANES FROM TODD COUNTY LINE TO INTERSECTION WITH RUSSELLVILLE BYPASS.(18CCN) (2020CCR) (2022CCR)
Location:
Route 1 Logan County US-79 from MP 0 to MP 10.713
Route 2 County - from MP to MP
Item #: 3-80050.00
Project Manager: KYTC\STEWART.LICH
Road Engineer:
Type of Work: MINOR WIDENING
Concerns:
Bridge Engineer:
Bridge Structure Number: 071B00024N
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate: 91.5
NBI Rating: Not Deficient
Posting: NO
Project Manager: KYTC\STEWART.LICH       Item #: 3-80050.00
Project Description: WIDEN US-79 TO 4 LANES FROM TODD COUNTY LINE TO INTERSECTION WITH RUSSELLVILLE BYPASS.(18CCN) (2020CCR) (2022CCR)

Milestones
Milestones Status Status Date Scheduled
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 07/10/2018 07/10/2018
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
JOINT INSPECTION UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - SIGNALS UNKNOWN 07/10/2018 07/10/2018
GEOTEC ENGINEERING - ROADWAY UNKNOWN 07/10/2018 07/10/2018
ROAD PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - SIGNING UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - LIGHTING UNKNOWN 07/10/2018 07/10/2018
DRAINAGE INSPECTION UNKNOWN 07/10/2018 07/10/2018
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
GEOTEC ENGINEERING - BRIDGES UNKNOWN 07/10/2018 07/10/2018
RIGHT OF WAY PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
PRELIMINARY LINE AND GRADE UNKNOWN 07/10/2018 07/10/2018
 
Project Manager: KYTC\STEWART.LICH       Item #: 3-80050.00
Project Description: WIDEN US-79 TO 4 LANES FROM TODD COUNTY LINE TO INTERSECTION WITH RUSSELLVILLE BYPASS.(18CCN) (2020CCR) (2022CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
District Office CE LVL 2 9/29/2021 HMB Professional Engineers, Inc. 9/29/2021 10/4/2022

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\STEWART.LICH       Item #: 3-80050.00
Project Description: WIDEN US-79 TO 4 LANES FROM TODD COUNTY LINE TO INTERSECTION WITH RUSSELLVILLE BYPASS.(18CCN) (2020CCR) (2022CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 3-80050.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\STEWART.LICH       Item #: 3-80050.00
Project Description: WIDEN US-79 TO 4 LANES FROM TODD COUNTY LINE TO INTERSECTION WITH RUSSELLVILLE BYPASS.(18CCN) (2020CCR) (2022CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
This Project has no Utilities Data available.
Project Manager: KYTC\STEWART.LICH       Item #: 3-80050.00
Project Description: WIDEN US-79 TO 4 LANES FROM TODD COUNTY LINE TO INTERSECTION WITH RUSSELLVILLE BYPASS.(18CCN) (2020CCR) (2022CCR)
This Project has no Vendors Assigned.