Highway Plan Phase Info
Phase Funding FY Amount
Design STP 2023 $750,000.00
Right of way SPP 2025 $2,000,000.00
Utility Relocation SPP 2025 $1,850,000.00
Construction SPP 2027 $3,200,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D STP $0.00 2023 AUTHORIZED 6/23/2022 $750,000.00
R SPP $2,000,000.00 2025 ESTIMATED $0.00
U SPP $1,850,000.00 2025 ESTIMATED $0.00
C SPP $3,200,000.00 2027 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 15253 1525301D $750,000.00 $0.00 $285,222.02 $371,232.76 $96,823.57
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: IMPROVE KY-281 FROM ISLAND PARK DRIVE TO 0.25 MI NORTH OF CARRIAGE LANE (KY-2281).
Location:
Route 1 Hopkins County KY-281 from MP 0.996 to MP 2
Route 2 County - from MP to MP
Item #: 2-384.00
Project Manager: KYTC\RENEE.BOUCHERIE
Road Engineer:
Type of Work: MAJOR WIDENING(O)
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\RENEE.BOUCHERIE       Item #: 2-384.00
Project Description: IMPROVE KY-281 FROM ISLAND PARK DRIVE TO 0.25 MI NORTH OF CARRIAGE LANE (KY-2281).

Milestones
Milestones Status Status Date Scheduled
ROAD PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - SIGNING UNKNOWN 07/10/2018 07/10/2018
JOINT INSPECTION UNKNOWN 07/10/2018 07/10/2018
GEOTEC ENGINEERING - BRIDGES UNKNOWN 07/10/2018 07/10/2018
PRELIMINARY LINE AND GRADE UNKNOWN 07/10/2018 07/10/2018
RIGHT OF WAY PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - LIGHTING UNKNOWN 07/10/2018 07/10/2018
BRIDGE AND STRUCTURE PLANS TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - SIGNALS UNKNOWN 07/10/2018 07/10/2018
ADVANCE SITUATION TO CENTRAL OFFICE UNKNOWN 07/10/2018 07/10/2018
DRAINAGE INSPECTION UNKNOWN 07/10/2018 07/10/2018
TRAFFIC PLANS - TRAFFIC CONTROL UNKNOWN 07/10/2018 07/10/2018
GEOTEC ENGINEERING - ROADWAY UNKNOWN 07/10/2018 07/10/2018
 
Project Manager: KYTC\RENEE.BOUCHERIE       Item #: 2-384.00
Project Description: IMPROVE KY-281 FROM ISLAND PARK DRIVE TO 0.25 MI NORTH OF CARRIAGE LANE (KY-2281).
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
District Office CE LVL 1 9/27/2022 HMB Professional Engineers, Inc. 9/27/2022 6/1/2023

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\RENEE.BOUCHERIE       Item #: 2-384.00
Project Description: IMPROVE KY-281 FROM ISLAND PARK DRIVE TO 0.25 MI NORTH OF CARRIAGE LANE (KY-2281).
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 2-384.00
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\RENEE.BOUCHERIE       Item #: 2-384.00
Project Description: IMPROVE KY-281 FROM ISLAND PARK DRIVE TO 0.25 MI NORTH OF CARRIAGE LANE (KY-2281).
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\RENEE.BOUCHERIE       Item #: 2-384.00
Project Description: IMPROVE KY-281 FROM ISLAND PARK DRIVE TO 0.25 MI NORTH OF CARRIAGE LANE (KY-2281).
Phase Vendor
D AMERICAN ENGINEERS INC