Highway Plan Phase Info
Phase Funding FY Amount
Design SPP 2023 $2,000,000.00
Right of way SPP 2025 $7,000,000.00
Utility Relocation SPP 2026 $2,200,000.00
Construction SPP 2027 $60,000,000.00
Current Phase Info
Phase Funding Estimated Cost Scheduled FY Phase Funding Status
Authorized Date Authorized Amount
D SPP $0.00 2023 AUTHORIZED 4/16/2024 $2,000,000.00
R SPP $4,500,000.00 2025 ESTIMATED $0.00
U SPP $2,500,000.00 2026 ESTIMATED $0.00
C SPP $73,200,000.00 2027 ESTIMATED $0.00
Project Budget Info
Phase Authorization Number Program Code Project Budget Budget
Modifications
(e-MARS) Project Expenditures
(e-MARS) Encumbered Amount Remaining (e-MARS)
Unobligated Amount
D 48291 4829102D $3,500,000.00 $0.00 $788,462.38 $421,080.85 $2,295,432.31
R/W Clearance:
Utility Clearance:

Some critical dates have not been assigned. (Letting Date not Established)

Project Description: RECONSTRUCTION OF KY 15 FROM BONNYMAN TO NEAR KY 28. (14CCN) (2020CCN) (2022CCR)
Location:
Route 1 Perry County KY-15 from MP 16.847 to MP 20.135
Route 2 County - from MP to MP
Item #: 10-269.20
Project Manager: KYTC\ARIC.SKAGGS
Road Engineer:
Type of Work: RECONSTRUCTION
Concerns:
Bridge Engineer:
Bridge Structure Number:
Select the Structure Number for The NBI Kentucky Inventory and Appraisal Report
Bridge Suff. Rate:
NBI Rating:
Posting:
Project Manager: KYTC\ARIC.SKAGGS       Item #: 10-269.20
Project Description: RECONSTRUCTION OF KY 15 FROM BONNYMAN TO NEAR KY 28. (14CCN) (2020CCN) (2022CCR)

This Project has no Milesones defined.
Project Manager: KYTC\ARIC.SKAGGS       Item #: 10-269.20
Project Description: RECONSTRUCTION OF KY 15 FROM BONNYMAN TO NEAR KY 28. (14CCN) (2020CCN) (2022CCR)
Authoritative Source for Environmental Data:  EATS
Environmental Status
Requestor Request Type Request Date Assigned Name Assigned Date Scheduled Completion Date
Actual Completion Date Expiration Date
FONSI RE 9/13/2021 HMB Professional Engineers, Inc.

No 401 – WQC Permit Data Available

No 402 – KPDES Permit Data Available

No 404 – USACE Permit Data Available

No Intergovernmental Review Permit Data Available

No LOP Permit Data Available

No Tennessee Valley Authority Permit Data Available
Project Manager: KYTC\ARIC.SKAGGS       Item #: 10-269.20
Project Description: RECONSTRUCTION OF KY 15 FROM BONNYMAN TO NEAR KY 28. (14CCN) (2020CCN) (2022CCR)
Authoritative Source for R/W Data: KROWDS
View Communicating All Promises (CAP) Report for Item# 10-269.20
This Project has no Right Of Way Data available from RWMS.
This Project has no Right Of Way Data available from KROWDS.
Project Manager: KYTC\ARIC.SKAGGS       Item #: 10-269.20
Project Description: RECONSTRUCTION OF KY 15 FROM BONNYMAN TO NEAR KY 28. (14CCN) (2020CCN) (2022CCR)
Authoritative Source for Utilities and Rail Tracking Data: KURTS
Utility Companies
Utility Name Facility Name
This Project has no Utilities Data available.
Project Manager: KYTC\ARIC.SKAGGS       Item #: 10-269.20
Project Description: RECONSTRUCTION OF KY 15 FROM BONNYMAN TO NEAR KY 28. (14CCN) (2020CCN) (2022CCR)
Phase Vendor
D HDR ENGINEERING INC
D HMB Engineers Inc